LREC/ZREC YEAR 3 RFP
Bidder Meeting May 5, 2014
1
LREC/ZREC YEAR 3 RFP Bidder Meeting May 5, 2014 1 Program Overview - - PowerPoint PPT Presentation
LREC/ZREC YEAR 3 RFP Bidder Meeting May 5, 2014 1 Program Overview CL&P Christie Bradway Denae Corcoran Laura Stilwell UI Gary Zielanski 2 Standard Contract is the Controlling Document In the event of any inconsistency between the
1
CL&P Christie Bradway Denae Corcoran Laura Stilwell UI Gary Zielanski
2
In the event of any inconsistency between the provisions of the LREC/ZREC RFP or any part this presentation, the provisions of the Standard Contract are controlling. Applicants should review the Standard Contract and all associated documents thoroughly and submit their Bids based upon the Standard Contract, which will solely govern the transactions between the selected Bidder and their counterparty Company through the term of the resulting contract.
3
4
1) Competitive Solicitation - (RFP) 2) Small ZREC Tariff
Project Type Size Annual Budget Renewable Energy Credit Price Cap Large ZRECs ≥250 kW to 1,000 kW Approximately $2.7 M
Medium ZRECs >100 kW < 250 kW Approximately $2.7 M
LRECs Up to 2,000 kW $4 M
Project Type Size Annual Budget Renewable Energy Credit Price Small ZRECs Up to 100 kW Approximately $2.7 M Weighted Average of the Medium ZREC price + 10% up to $302.71/REC
5
6
Example 1: 200 kW Solar System ~ 311 RECs/year Annual Payment ~ $46,650 $150/REC x 311 RECs/year ~$46,650 Total Payment over 15 years ~ $699,750
Example 2: 400 kW Fuel Cell ~ 3,312 RECs/year Annual Payment ~ $264,960 $80/REC x 3,312 ~ $264,960 Total Payment over 15 years ~ $4.0M Examples show sample REC prices. The market will set actual REC prices.
7
8
Year #1 Year #2 Year #3
9
Category Size Total # Projects Selected (To Date) Avg $/REC (CL&P) Year 1 Avg $/REC (CL&P) Year 2 Total # UI Projects Selected (To Date) Weighted Avg $/REC (UI) Year 1 Weighted Avg $/REC (UI) Year 2 LRECs Up to 2 MW 22 $66 $57 (↓14%) 8 $51.08 $49.43(↓3%) Large ZRECs 250 – 1,000 kW 39 $101 $77 (↓24%) 10 $117.27 $90.43(↓23%) Medium ZRECs +100 – 250 kW 106 $149 $94 (↓37%) 37 $135.36 $102.31(↓24%) Small ZRECs 0 – 100 kW 420 $164.22 $103.01 (↓37%) 77 $148.89 $112.54(↓24%) Total 587 132 All programs have been oversubscribed to date
10
Small ZREC Projects are not covered by this RFP Third year of Small ZREC program will commence after PURA decision approving Year 3 Medium ZREC contracts & Year 3 Small ZREC rates
RFP, Standard Contract, Solicitation Plan, PURA Decision – Docket 11-12-06, Question and Answer Document (updated periodically)
11
ACTION ITEM DATE RELEASE OF RFP APRIL 24, 2014 BIDDERS CONFERENCE MAY 5, 2014 DEADLINE FOR SUBMISSION OF QUESTIONS MAY 16, 2014 BID FORMS DUE JUNE 5, 2014 BY 1:00 P.M. (EASTERN PREVAILING TIME “EPT”), AT
WHICH TIME THE PRICING SHALL BECOME FIRM, IRREVOCABLE AND BINDING.
SELECTION AND NOTIFICATION OF WINNING BIDDERS ON OR ABOUT JULY 17, 2014 STANDARD CONTRACTS EXECUTION & PROVISION OF PERFORMANCE ASSURANCE AFTER SELECTION AND NOTIFICATION OF WINNING BIDDERS. BIDDERS
WILL HAVE TO RETURN PARTIALLY EXECUTED CONTRACTS AND
PERFORMANCE ASSURANCE BY THE DATE ESTABLISHED BY THE COMPANIES WHICH IS EXPECTED TO BE APPROXIMATELY 10 BUSINESS
DAYS AFTER TRANSMITTAL OF EXECUTION VERSION OF STANDARD
CONTRACT. STANDARD CONTRACT(S) FILED WITH PURA FOLLOWING SELECTION OF WINNING BIDDER(S) AND EXECUTION OF STANDARD CONTRACTS DURING EACH ROUND. COMMENCEMENT OF SERVICE IN ACCORDANCE WITH STANDARD CONTRACTS
12
13
14
For CL&P: www.cl-p.com/rec For UI: www.uinet.com/powerprocurement, click on RFP for LRECs and ZRECs (April 24, 2014)
Bid Certification Form (4 pages including affidavit - mandatory) LREC/ZREC CT Licensed Professional Engineer (PE) Certification Pending CEFIA Grant and/or Rebate Disclosure Statement CT Manufactured, Researched or Developed Affidavits
15
16
17
Page 1: Instructions Page 2: Bidder Signature - Bidder is defined as the individual or business submitting a proposal (“Bid”) Page 3: Contract Counterparty Signature - Contract Counterparty is defined as the legal entity desiring to enter into a Standard Contract Page 4: Owner of the Project Site Signature - Owner of the Project Site is defined as the legal owner of the Project site (Notarized Affidavit)
18
Two affidavits required (if seeking M/R/D designation): Bidder affidavit that project uses CT Manufactured, Researched or Developed Generation Technologies
Must constitute no less than 50% of the total value of Generation Technology to be used by its’ project.
Technology supplier’s affidavit that it supplies CT Manufactured, Researched or Developed Generation Technologies Amended R & D definition in RFP
19
PE Certification only required if:
seeking alternate capacity factor not using 1 of the technologies with a capacity factor defined in the IRP one bid combines multiple technologies
20
21
22
23
Partially Executed Standard Contract & Provide Performance Assurance Company will email you an executable version of the Standard Contract Partially executed contract must be received by Company by the Effective Date of Standard Contract, or project is disqualified Performance Assurance must be received by Company by the Effective Date
Amount of Performance Assurance will be listed on the Cover Sheet of the Standard Contract (Section 9.1) Company will return a fully executed contract
24
272 RECs x $120.00/REC x 10% = $3,264.00
932 RECs x $90.00/REC x 20% = $16,776.00
8,279 RECs x $50.00 x 20% = $82,790.00
25
Both companies have detailed instructions for how to successfully provide Performance Assurance Acceptable forms of Performance Assurance
Cash (electronic) Please note that ACH payments take longer to process than Wire Transfers. Please plan accordingly for receipt by Company on or before the due date. Bank Check or Cashier’s Check (personal or business check not accepted) Letter of Credit Surety Bond
26
27
Must meet all Project Eligibility Requirements, Plus: In service and producing CT Class I RECs CT PURA rules require you submit a separate application to PURA for CT Class I Qualification after your project is in service In service no later than 1 year after selected Delivery Term Start Date (1/1/15, 4/1/15, 7/1/15, 10/1/15) Must have a functioning, dedicated REC meter Metering requirements (to be discussed later) Interconnection Agreement required (to be discussed later) NEPOOL GIS registration
28
29
30
Same rate, quarterly payments vary based on number of REC’s delivered
Forward Certificate Transfer
31
NEPOOL GIS
Verification& Settlement & Verification
RECs
From Seller’s account to the Utility’s account
33
Payment ~ On or before Creation Date/ last day of month Transfer Date following delivery month Q1 (Jan, Feb, Mar) 7/15/2014 8/31/2014 Q2 (Apr, May, Jun) 10/15/2014 11/30/2014 Q3 (Jul, Aug, Sep) 1/15/2015 2/28/2015 Q4 (Oct, Nov, Dec) 4/15/2015 5/31/2015
Please refer to Article 11
Requires Notice to Company Company has 30 days to review and approve/reject
Sell to 3rd party “Bank” RECs to meet next year’s MAQ Excess RECs may be sold to utility with both parties’ consent
34
If, in accordance with Article 14, Buyer receives notice and request for voluntary termination of this Agreement from Seller prior to the selected Delivery Term Start Date as specified on the Cover Sheet, then, provided that an event of default by Seller is not then existing, Buyer will return to Seller twenty percent (20%)
Buyer receives such notice.
35
CL&P = LREC.ZREC@NU.COM UI = lrec.zrec@uinet.com
CL&P = www.cl-p.com/rec UI = www.uinet.com/powerprocurement, click on “RFP for LRECs and ZRECs (April 24, 2014)”
36
37
CL&P – Joseph Debs UI – Nic Baldenko
Distributed Generation 2005-2013
Type CL&P UI TOTAL
CHP
112 MW 41 MW 153 MW
Photovoltaic
62 MW 13 MW 75 MW
Fuel Cells
13 MW 17 MW 30 MW
Others
115 MW 36 MW 151 MW
Total MW(connected)
302 MW 107 MW 409 MW
Total Projects
4037 780 4817
Process Rating Time (Business
Days)
Application Fees Witness Test Fee Liability Insurance
Inverter Based 0-10 kw 15 $100 1st Test $300,000
COMPLETENESS OF APPLICATION RECEIVED CONTINGENT APPROVAL NOTIFICATION SCHEDULE WITNESS AND TEST AND INSTALL NET METER APPROVAL TO ENERGIZE 10 BUSINESS DAYS 15 BUSINESS DAYS FROM COMPLETE APPLICATION 10 BUSINESS DAYS FROM TOWN INSPECTION APPROVAL
APPROXIMATE 30 BUSINESS DAY APPROVAL PROCESS
APPLICATION RECEIPT NOTIFICATION 3 BUSINESS DAYS Submit Application
Additional Paper Work
Application Submittal Application Request Complete Customer submits all information Application Withdrawn
No No
Inverter based & Certified ≤2 MW Passes Screen Conduct Application Review (30 Business Days)
No
Customer installs generator and returns certificate of completion to EDC Generator => 5 MW Customer Signs IA & authorizes EDC modification EDC issues final approval to energize. Witness Commissioning Test
Yes Yes Yes No
Studies Required
No No Yes Yes
Studies Completed
Yes No
Conduct Application Review (15 Business Days)
Yes Yes
Conduct Studies as appropriate: 1-Feasibility Study 2-Impact Study 3- Facility Study 4- Transmission Studies ISO-NE Generator Interconnection Process (I.3.9 )
Process Rating Time (Business Days) Application Fees Witness Test Fee Liability Insurance Fast Track 0-2 MW 15 $500 Cost Based $300,000 to $2,000,000
Meet all the screen requirements Generators which do not meet the Fast Track requirements may require additional studies ISO-NE notification form for projects >1MW Interconnection agreement required
COMPLETENESS OF APPLICATION RECEIVED CONTINGENT APPROVAL INSTALLATION & WITNESS TEST APPROVAL TO ENERGIZE 10 BUSINESS DAYS 15 BUSINESS DAYS FROM COMPLETE APPLICATION 10 BUSINESS DAYS FROM TOWN INSPECTION APPROVAL APPLICATION RECEIPT NOTIFICATION 3 BUSINESS DAYS Interconnection Agreement (IA)
Submit Application - The Application, One Line diagram, Layout Diagram, Proof of Insurance, Inverter Data sheet, $500 Application Fee Additional Deliverables - Interconnection Agreement, Test Plan, Inspector’s Approval, Witness Test, Net Meter Installation
Process Rating Application Fees Witness Test Fee Liability Insurance Study 1) >2 MW and <20 MW 2) 2 MW and not certified. 3) 2 MW, certified, failed Fast Track $1000 Cost Based Generator Size Dependent
ISO-NE transmission impact studies required for projects >=5MW Interconnection agreement required
APPLICATION REVIEW FEASIBILITY STUDY IMPACT STUDY FACILITY STUDY CONSTRUCTION & WITNESS TEST JURISDICTION DETERMINATION
Submit Application - The Application, One Line diagram, Layout Diagram, Proof of Insurance, Generator Data Sheet, $1,000 Application Fee
30 BUSINESS DAYS 15 BUSINESS DAYS 30 BUSINESS DAYS 30 BUSINESS DAYS APPROVAL TO ENERGIZE
Additional Deliverables - Interconnection Agreement, Test Plan, Inspector’s Approval, Witness Test, Net Meter Installation
IA
Application Guidelines Complete Application Application Signature Insurance Technical data sheets Number of inverters / Generation Utility account and/or meter number Ownership Property Third party ownership of generator
Technical Exhibit B of the Guidelines Electrical One-Line diagram with standard symbols and labels Timely communication and data transfer Receive contingent approval prior to construction Disconnect switch Compliance with meter and service requirements Detailed sequence of operation and test plan Provide detailed relaying information when required
Guidelines for Generator Interconnection
54
55
High level requirements: Facilities will purchase and install their own meter as specified within the CL&P REC Meter Specifications as well as the List of Acceptable Meters. Both can be found at http://www.cl-p.com/rec Design with communications in mind
Communications method will be specified with the meter type for your project If we cannot communicate with the meter this may require a design change Procurement will be following the review by the CL&P Meter Engineering group
CL&P will assist procurement by providing vendor contact information as well as product keys
56
57
Facility Size Meter Group Level 1 0.0-19.9kW A,B,C Level 2 20.0-49.9 kW A,B,C Level 3 50.0-100.00 kW A,B,C Level 4 101kW to 999.9 kW* B,C Level 4 (LREC only) 1MW to 2 MW* C
Form Manufacturer/Model NU Product Key Class Communications
Group A *2S,12S,16S
Centron 3 ERT
CxSLZREC 200/320 High powered ERT *5S,9S
Centron 3 ERT
CxSLZREC 20 High powered ERT
2S,3S,4S,12S
L+G with Metrum Focus AXxSMD 200/320 Cell
3S,4S
L+G with Metrum Focus AXxSMD 20 Cell Group B 9S ,16S Itron/L+G with Metrum Varies 20/200/320 Cell Panel mount Ion/7330
P7330A0B0B0M1A0A-AA150
20 Ethernet, Analog Phone Group C *9S, Panel Ion/8600 Provide during review 20 Ethernet, Analog Phone * Other forms may be available upon request
Meter types, manufacturers and communications are subject to change
Similar to the interconnection review You contact your interconnection project manager from CL&P to coordinate the review.
Please do not contact specific individuals to complete a review unless they have been assigned to your project. Reviews cannot be completed if multiple projects are aggregated into one submission/email
We will assign a meter type when you initiate the process. We will then require cut sheets, one-lines, three-lines, etc.
We must be able to electrically see the entire system from the panels to the street
This includes the inverter, the REC meter, the customers main breaker, the customer loads, and the CL&P revenue meter You must clearly show the location of any other REC facilities behind one CL&P Revenue meter
59 59
60
Marc Colca (UI) Ed Davis (CL&P)
61
Net Energy Billing Distributed Generation Rider Virtual Net Metering Power Purchase
62
Class I Renewable Energy and Hydropower Resources Qualifying Facilities and NON-Class I Renewable Resources
63
Class I Renewable Energy and Hydropower Resources Up to 2,000 kW nameplate capacity Billing based upon customer’s electric service tariff Net energy billing and “banking” of excess net energy production (killowatt-hours or kWh) performed monthly Annual end-of-period credit for any unused banked kWh Riders
CL&P: “Rider N – Class I Renewable or Hydroelectric” UI: “Class I Renewable Energy Rider NEC1” (Rider NEC1)
Additional Details
Annual Banking and Credits
At the end of each annual period (April through March):
Any unused, banked kWh will be “purchased” at the average ISO-NE CT Zone real-time locational marginal price (“LMP”) of that period Purchase Price
PV: Average annual LMP (all hours between 10 am and 4 pm) Other resources: Average annual LMP (all hours)
Bank reset to zero kWh
64
Qualifying Facilities and NON-Class I Renewable Resources Nameplate capacity of up to
50 kW Qualifying Facilities 500 kW Non-Class I Renewable Resources
Billing based upon customer’s electric tariff Net Energy billing performed and credit applied for excess energy delivered to EDC on a monthly basis Pricing based on power purchase schedule Riders:
CL&P: “Rider N - Non-Class I Renewable and QF” UI: “Distributed Generation Facility Net Energy Rider NE” (Rider NE)
Electric DG Rider
Applicable to customers who receive electric service under a firm service rate that includes a distribution demand ratchet Subject to enrollment and qualification requirements Provides for waiver of the distirbution demand ratchet Applicable rate schedules
CL&P: Distributed Generation Rider UI: Rider DG
Gas Distributed Generation (DG) Delivery Rebate Rider
Available to customers under specified gas service rebates Subject to enrollment and qualification requirements Provides rebate of delivery service charges for the DG system Comparable rate schedules for CNG, SCG and Yankee Gas
66
The Virtual Net Metering (VNM) Rider program has been expanded to include Agricultural, Municipal and State customers (Public Act 13-298) Under Docket No. 13-08-14 a technical meeting was held and working group was formed to address program specifics and administrative processes. The EDC’s submitted proposed VNM riders on February 3, 2014. Program features include: Facilities up to 3 MW Class I (all) or Class III (Municipal & State) VNM Credit Determined Monthly VNM Credit = (Excess kWh of Host) x (SS or LRS rate + % T & D) Allocations of VNM Credits to Beneficial Accounts
Municipal & State: 5 Municipal or State + 5 Non-State or Municipal Critical Facilities Connected to Microgrid Agricultural: Up to 10 Beneficial Accounts (Agricultural, Municipal or non-commercial critical facility)
VNM credits for unused excess kWh, if any, are calculated monthly at rates for the applicable generation service plus a declining percentage of T & D components of service of the Host Account Customer Host account compensated at end of calendar year
Annual VNM Credits
The maximum, aggregated annual compensation to all customers under the VNM program is $2 million for UI and $8 million for CL&P Maximum of 40% (e.g., CL&P: $3.2 M) per classification Individual Customer Host annual caps assigned at the time of enrollment If during a calendar year an individual Customer Host’s annual cap is reached, net energy billing continues and all excess kWh produced is compensated under the applicable power purchase rate for the remainder of the year
Available to any self-generation facility not under long-term electric purchase agreement Purchase of electricity delivered to EDC Energy (kWh) only Pricing based on ISO-NE CT Zone Real-Time LMP Applicable rate schedules: CL&P: Rate 980 UI: Power purchased at SG2 rate (energy component of LMP only) Questions?
69