Lovers Point Coastal Access Project April 17, 2019 City Council - PowerPoint PPT Presentation

Lovers Point Coastal Access Project April 17, 2019 City Council City of Pacific Grove Conceptual Design 1st conceptual design developed in 2014 Discussion In 2018 100% construction drawings City received first bids for the project


  1. Lovers Point Coastal Access Project April 17, 2019 City Council City of Pacific Grove

  2. Conceptual Design  1st conceptual design developed in 2014

  3. Discussion  In 2018 100% construction drawings  City received first bids for the project in May of 2018  All bids rejected due to high construction cost

  4. Discussion  Value Engineering occurred to reduce cost  A revised project plan set was released for a re-bid in November, 2018

  5. Value Engineering  Complete removal of electrical, stairway, pervious paver crosswalks and sitting area at Recreation Trail  The Parking Lot Slurry Seal to be completed later with the annual project  City to complete the irrigation system, and plantings  Rock wall seating has been replaced with concrete seating walls

  6. Rendering Changes

  7. Re-Bid Received  Monterey Peninsula Engineering $466,712  Earthworks Paving Contractors $520,387  Precision Grade Inc. $559,285  Graniterock $782,702  Engineers Estimate $350,091

  8. Questions? City Council City of Pacific Grove

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.