Local Advisory Committee Meeting #3 Item # 3 January 12, 2016 - - PowerPoint PPT Presentation

local advisory committee
SMART_READER_LITE
LIVE PREVIEW

Local Advisory Committee Meeting #3 Item # 3 January 12, 2016 - - PowerPoint PPT Presentation

Greater Ottawa Region Local Advisory Committee Meeting #3 Item # 3 January 12, 2016 Outline of this Presentation Part 1: Supplying Demand Growth in South Nepean Part 2: How South Nepean Fits in as Part of the Broader West Ottawa Area and


slide-1
SLIDE 1

Greater Ottawa Region Local Advisory Committee Meeting #3 – Item # 3

January 12, 2016

slide-2
SLIDE 2

Part 1: Supplying Demand Growth in South Nepean Part 2: How South Nepean Fits in as Part of the Broader West Ottawa Area and it’s Supply Needs Part 3: Recommend an Integrated Plan to Address the Needs in South Nepean and the Broader West Ottawa Area

Outline of this Presentation

2

slide-3
SLIDE 3

Part 1: Supplying Demand Growth in South Nepean

3

slide-4
SLIDE 4

Need to Supply Growth in South Nepean

4

  • The area is supplied from three

stations:

– Longfield DS from the north (off Nepean TS) – 2 feeders off Limebank MTS from across the Rideau River – Fallowfield DS from the west

  • The growth in South Nepean is

due to a number of developments in this area:

– Nepean town center – Strandherd Business Park – Development of Barrhaven south community – Expansion of Barrhaven and Longfield community

230 kV 115 kV

slide-5
SLIDE 5

Need to Supply Growth in South Nepean (2)

5

  • Total station capacity for the

area based on planning criteria is 57 MW

  • Today the peak demand in the

area already exceeds the station level planning capability

– Hydro Ottawa is managing the supply to the area through distribution transfer capability – The need for additional supply capacity is forecasted to grow to 60 MW by 2032

  • The 115 kV circuit supplying

Fallowfield will also reach its supply capacity by 2022

Total Need: > 60 MW

slide-6
SLIDE 6

Approaches to Address Need in South Nepean

6

  • For comparison:

– 10 MW peak demand = 2,500 rooftop solar installations of 10 kW each – 10 MW peak demand = ~12 grocery stores (Superstore) or ~ 3,000 homes

  • The magnitude (~ 30 MW near-term and ~60 MW longer-term) and

timing (as soon as possible) make it infeasible to reduce demand growth on the distribution system

Two Possible Approaches to Address Need Option 1: Reduce demand

  • n the distribution system

Option 2: Increase transmission supply capacity by building a new transformer station

Could be achieved by:

  • Distribution-connected Generation
  • Demand Response

Variations:

  • New supply station at 230 kV
  • New supply station at 115 kV
slide-7
SLIDE 7
  • A new supply station and connection line in South

Nepean is recommended to support the growth in the area

  • Due to the capacity limit on the existing 115 kV circuit

supplying Fallowfield, Richmond and Manotick, a 230 kV connection is recommended for the new station

Recommended Plan to Supply Demand Growth in South Nepean

7

slide-8
SLIDE 8

Part 2: South Nepean as Part of the Broader West Ottawa Area

8

slide-9
SLIDE 9

Additional Overlapping Need to Supply the Broader West Ottawa Area

9

  • West Ottawa is defined

as the 20 stations supplied by the 115 kV system originating from Merivale TS

– South Nepean is part of the West Ottawa area

  • The need for additional

230/115 kV transformer capacity at Merivale TS, the main supply point for West Ottawa, was identified in the April 2015 IRRP

– Due to growth across the broader region

Downtown

West Ottawa

South Nepean 230 kV 115 kV

slide-10
SLIDE 10

10

Need for Additional 230/115 kV Transformer Capacity at Merivale TS

  • Based on the planning forecast

the two 230/115 kV transformers at Merivale TS will reach their capacity around 2019

  • Because South Nepean is part
  • f the West Ottawa area, the

recommended solution for South Nepean, a new 230 kV station and connection line, will help address this broader need in West Ottawa

2019, Merivale transformers reach their capacity Total Need: 150 MW

slide-11
SLIDE 11

11

  • The recommended new 230 kV

station and connection line will supply ~ 50 MW of demand in South Nepean, reducing the demand on the West Ottawa 115 kV system and therefore reduces the need for new capacity at Merivale

  • However there is still a large

capacity need remaining at Merivale TS

– As much as 100 MW by 2032 Stage 1: new 230 kV station South Nepean

The Recommended Solution for South Nepean Helps Address the Capacity Need at Merivale

Remaining need for Stage 2: 100 MW

slide-12
SLIDE 12

Approaches to Address Remaining Supply Capacity Need at Merivale TS

12

  • If a portion of West Ottawa demand is supplied from a new 230

kV station in South Nepean, and therefore removed from the 115 kV system forecast (consistent with Option 1) then there is more time available to address the remaining longer term need, avoiding Option 2

Two Possible Approaches to Address Need Option 1: Reduce demand on the West Ottawa 115 kV system Option 2: Add a third transformer at Merivale TS

Could be achieved by:

  • transmission or distribution connected

conservation and/or generation

  • other technologies
  • moving demand from 115 kV to 230 kV

Potential constraints:

  • cost and complexity due to limited space at

the station

  • would increase the 115 kV system short

circuit current level

slide-13
SLIDE 13
  • A bundle of different non-wires and wires components may be used to

reduce demand across the West Ottawa area

  • Bundling different types of components has several advantages:

– will address the need incrementally and therefore allow flexibility – can be implemented in stages, making longer-lead-time components feasible – enables opportunity to collect community input on options and objectives

  • Examples of possible components are:

– Local Demand Response Program – Local generation (transmission or distribution connected renewables, or small scale CHP) – Local storage, or other new technologies – Additional load transfer from 115 kV system to 230 kV system

Reducing Demand on the West Ottawa 115 kV System

13

slide-14
SLIDE 14

Part 3: Integrated Planning Recommendations

14

slide-15
SLIDE 15
  • A staged plan is recommended to address the two needs

identified in the West Ottawa area:

Stage 1: A new 230 kV station and connection line to supply growth in the South Nepean area Stage 2: An integrated plan, to be informed by community input, which will avoid the need for additional 230/115 kV transformer capacity at Merivale TS by reducing demand across the West Ottawa area

Overview of the Recommended Plan

15

slide-16
SLIDE 16
  • A new 230 kV transformer station and connection line are

recommended to increase supply to South Nepean

– Development, approvals and construction will take approximately 5 years

  • Hydro One and Hydro Ottawa should initiate the

development work and proceed to the required approval processes including Environmental Assessment, and Leave to Construct

– Broader public engagement on this project will take place as part

  • f the Environmental Assessment process
  • No plan level engagement is planned for Stage 1, due to the

lack of feasible alternatives

Recommendations – Stage 1

16

slide-17
SLIDE 17
  • Public engagement will inform Stage 2 of the Plan

– Input will be sought on potential options, and the community’s priority objectives

  • The Regional Planning Working Group will continue to

monitor the planning forecast for West Ottawa

– The need for demand reduction will be reassessed periodically

  • A plan for Stage 2 it targeted for completion by mid 2017

– Including options for long-tem flexibility – Cost allocation issues must be addressed

Recommendations – Developing Stage 2 of the Plan

17

slide-18
SLIDE 18
  • A meeting with City of Ottawa staff is being planned for

February, prior to finalizing and posting the Integrated Plan

  • The IESO will host a public webinar on the Integrated

Plan in the spring of 2016

  • For Stage 1, project level public engagement will be

carried out as part of the Environmental Assessment process (Hydro Ottawa and/or Hydro One)

  • For Stage 2, plan level public engagement will be carried
  • ut in 2016 as part of the planning process (Regional

Planning Working Group)

Summary of Public Engagement Recommendations

18