Presentation Outline Role of the Local Advisory Committee - - PowerPoint PPT Presentation
Presentation Outline Role of the Local Advisory Committee - - PowerPoint PPT Presentation
Toronto Local Advisory Committee Inaugural Meeting January 28, 2016 Presentation Outline Role of the Local Advisory Committee Regional Electricity Planning Process Highlights from Regional Planning Activities in Toronto
- Role of the Local Advisory Committee
- Regional Electricity Planning Process
- Highlights from Regional Planning Activities in
Toronto
- Overview of Distribution System Plans
- Longer Term Electricity Needs
- Questions from Public
Presentation Outline
2
3 3
ROLE OF THE LOCAL ADVI SORY COMMI TTEE
Role of the Local Advisory Committee
- Provide advice and recommendations on the
development and implementation of the plan
- Provide input and recommendations throughout the
electricity planning process including the design of engagement approaches related to regional planning
- Share information on local priorities to be considered
in the procurement of conservation and supply side resources
Meetings are a Forum for Information Sharing
- Updates on the status of regional planning
- Working Group to provide information on identified
- ptions for meeting the region’s longer term electricity
needs
- A venue for a broader energy dialogue and a bridge
between regional planning cycles
REGI ONAL ELECTRI CI TY PLANNI NG PROCESS
6
Background
- A Working Group consisting of the Independent Electricity System Operator (IESO),
Toronto Hydro and Hydro One Networks have been examining the electrical needs in Central Toronto since 2011
- A report, “Central Toronto Integrated Regional Resource Plan” (IRRP), was prepared
and posted at the end of April 2015. It documents the findings and recommendations from that study
- Needs in the rest of Toronto were assessed by a Hydro One led Working Group in
2015 – no additional needs requiring regional coordination were identified in this area
- The reports fulfill the requirement for regional planning for the Region as mandated
by the Ontario Energy Board
- The recommendations lay the foundation for continued planning to address needs
arising in the medium and long term
7
Key Participants in Ontario’s Electricity Sector
8
Ontario Energy Board
Ontario Electricity System and its Customers
Regulation Generation Distribution Transmission System Operation, Planning and Procurement
Hydro One, Great Lakes Power Transmission, Five Nations and others Local Distribution Companies (LDCs), e.g., Toronto Hydro Electric System Limited Ontario Power Generation (OPG) and other generators Ministry of Energy
Illustration of a Typical Electricity System
9
- A process for identifying and addressing local electricity needs
- Link between provincial bulk system planning (led by the IESO) and local
distribution system planning (led by LDCs)
- Objective of maintaining a safe, reliable and economic electricity supply
- Operates in the context of existing criteria and frameworks
– Applies the IESO’s reliability standards – Seeks to align with provincial/municipal planning policies, and where possible, with local interests
- Either an integrated approach (considers conservation, generation, wires
and other innovative solutions) led by the IESO, for studies with more expansive needs; or for studies with “wires only” solutions, led by Hydro One or other Transmitters
What is Regional Electricity Planning?
10
Context for Regional Electricity Planning
- A key objective for regional planning is to
ensure that the electricity system supplying an area has:
– The capacity to supply the demand at peak levels (the highest anticipated demand level of the day/year), – Meets all reliability standards, and – Manages supply security risk, such that the system is resilient / capable of limiting the impact to customers
- f extreme events, such as the ice storm of 2014
Regional Planning Focus
12
13 13
CENTRAL TORONTO I NTEGRATED REGI ONAL RESOURCE PLAN
- Toronto was the first region to fully implement the formal regional
planning framework, introduced in 2013
- A number of communication tools were used throughout the development
- f the IRRP to engage with stakeholders and understand their preferences
- Qualitative and quantitative research results indicate cost is a key issue:
– “Reduce rates” was the leading answer to the question of what could be done to improve the system – Customers also looking for increased reliability – Focus Groups understood the need to replace aging infrastructure but suggested the system look within for savings and to harness “waste” before asking customers to pay more
- This research was used to inform the development of the IRRP and the
recommendations
What’s Been Done, What we Heard
14
- Toronto is supplied by a
diverse network of 230kV and 115kV transmission facilities
- Two distinct electrical sub-
areas:
– Metro Toronto North (230 kV) – Central Toronto (115/230 kV)
- Peak electricity demand about
5,000 MW (summer peaking)
– 2,000 MW in Central Toronto
- Canada’s largest city
– 4th largest in North America
Overview of Electricity Supply in Toronto (1)
15
- Electricity supply to the City
includes:
– Several transmission links to the provincial grid – 550 MW Portlands Energy Centre – 140 MW Distributed Generation – 88 MW renewable generation contracted (FIT, microFIT, etc.)
- Electricity conservation is a
key component of meeting Toronto’s future needs
– Conservation resources expected to offset nearly 40% of growth until 2036
Overview of Electricity Supply in Toronto (2)
16
Drivers of Near-term Needs
- Continued growth and urban renewal
– Record tall building development – Increasing density
- New large transit projects
- System reliability, security and resilience
– Ensuring customers continue to receive a high level of service considering changing weather patterns
- Replacement of aging infrastructure
17
Forecast for Electricity Demand in the Area
18
200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200 2,400 2,600
Peak Demand (MW) Year
Actual historic peak demand
Factors that can drive demand upward:
- More economic growth
- More people moving into the city
- Electrification of transportation
- Less than expected Conservation results
Factors that can bring demand down:
- Shifting to less energy intensive commerce
- Reduced pace of growth
- Increasing end-use efficiency
- More stringent building codes
Growth and Urban Renewal
19
- Intensification concentrated in pockets, mainly downtown and West
Near-term Projects Being Implemented
20
2 3 4
- 1. Conservation efforts and distributed
generation development are underway (throughout Toronto)
- 2. Special Protection Systems will provide
additional supply security under low- probability events
- 3. Expansion of Runnymede Transformer
Station (TS) and 115 kV upgrades will accommodate new community growth and the new Eglinton Crosstown LRT
- 4. Expansion of Horner TS will relieve
- verloading at Manby TS and allow for future
growth in the area
- 5. Completing Phase Two of Copeland TS will
allow for connecting new customers in the downtown core
5
These near-term projects maximize the capability of the existing system, and support growth to the end of the decade
230 kV Transmission Supply to Downtown: Recommendation from April 2015 IRRP
Driver
- Growth in the downtown core
and west Toronto, new transit
Need
- Ensure sufficient supply capacity
- n 230 kV Richview to Manby TS
transmission system
Recommendation
- Implement conservation
initiatives to manage 40 MW of peak demand growth
- Monitor demand and upgrade
corridor when necessary
21
230 kV Transmission Supply to Downtown: Changes Since April 2015 IRRP
- Since the IRRP was completed, new
information regarding Metrolinx’ plans to add a traction power station in the area to support electrification of Lakeshore West line (2020)
- This project alone will add another
40 MW of new demand to be supplied by the Richview to Manby TS transmission (total need: 80 MW by 2020)
- This will trigger the need for line
reinforcement
22
Other Highlights from the Regional Plan
- Maintaining high service levels
- Building system/customer resilience given
effects of climate change
- Preparing the City to address needs in the long
term timeframe
23
Needs Arising in the Long-Term
24
- Infrastructure limits are
projected to be reached as early as the mid to late 2020s
– Transformers at Manby and Leaside – 115 kV transmission system supplying downtown
- Capacity constraints occur
during the summertime peak demand period
- High degree of uncertainty with
respect to the timing
- Actions will be needed starting
in the near term to manage these long term needs
Options for Meeting Long-Term Needs
25
- Full achievement of government
Conservation targets could help defer these needs by as much as 10 years
- Distributed generation in the
Central and downtown areas
- Large scale generation facility
- Additional transmission supply
into downtown (Hearn station in the Portlands area was designed to accommodate an additional supply point)
Approaches to Addressing Longer-Term Needs
26
Conservation & Small-Scale, Distributed Resources Larger, Localized Generation Wires
Deliver Provincial Resources Community Self-Sufficiency
Final plan may have elements from each
- f the approaches
Centralized Local Resources
- The next step in the regional planning process is to
- btain input and advice from the LAC
– Local preferences and concerns – Policies in Toronto affecting growth and development – Evolution of technologies – Impact of conservation – Concerns about resilience / climate change
- We will also seek input on further engagement strategies
- The IESO, Toronto Hydro and Hydro One will continue
to study and report on the effects of conservation and distributed generation, and effect on the transmission and distribution systems
27
Addressing Toronto’s Long Term Needs
Some Questions for the LAC’s Consideration
- What would you like to know in order to
prepare you to inform the discussion?
– Approach – Criteria – Engagement – Other
- What format(s) would you prefer to provide
your feedback?
28
29 29