LEXINGTON CLUB LEXINGTON HOMES HANK STILLWELL LEGAL Developer: - - PowerPoint PPT Presentation

lexington club
SMART_READER_LITE
LIVE PREVIEW

LEXINGTON CLUB LEXINGTON HOMES HANK STILLWELL LEGAL Developer: - - PowerPoint PPT Presentation

Presentation to Planning Commission September 20 2011 LEXINGTON CLUB LEXINGTON HOMES HANK STILLWELL LEGAL Developer: Lexington Homes Legal: PROJECT Rathje & Woodward, LLC TEAM Environmental: Huff & Huff, Inc.


slide-1
SLIDE 1

LEXINGTON CLUB

LEXINGTON HOMES

Presentation to Planning Commission September 20 2011

slide-2
SLIDE 2

LEGAL

HANK STILLWELL

slide-3
SLIDE 3
  • Developer:

Lexington Homes

  • Legal:

Rathje & Woodward, LLC

  • Environmental:

Huff & Huff, Inc.

  • Planner & Architect:

BSB Design, Inc.

  • Landscape Architect:

Pugsley & La Haie, Ltd.

  • Civil Engineer:

Wills Burke Kelsey Associates, Ltd. (WBK)

  • Traffic Engineer:

Kenig, Lindgren, O’Hara, Aboona, Inc. (KLOA) PROJECT TEAM

slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6

ENVIRONMENTAL

JIM HUFF

slide-7
SLIDE 7
  • Huff & Huff has worked for the City of St. Charles

for over 25 years. – Consultant of Record for the First Street Redevelopment remediation – Just completed a remediation of a LUST at the St. Charles CC – Completed the environmental work on the new Red Gate Bridge

  • Huff & Huff, Inc. has been involved with this site

since 2006. We have: – Reviewed previous reports – Conducted soil borings – Conducted a series of test pits across the site BACKGROUND

slide-8
SLIDE 8
  • Original Manufacturing Buildings constructed in

early 1900s.

  • Rope nets and hammocks were manufactured

from early 1900s into the late 1920s.

  • From the late 1920s to 2005, pressed wood pulp

and fibrous composite products were

  • manufactured. Large Quantity Generator of

Hazardous Waste.

  • Had coal‐fired boiler at one time.

SITE HISTORY

slide-9
SLIDE 9
slide-10
SLIDE 10
  • REC‐1: Former Buried Drum Area
  • REC‐2: Former Settling Lagoons
  • REC‐3: Mounds on Western Portion of Property
  • REC‐4: Former Leaking Gasoline UST
  • REC‐5: Former Panapol UST
  • REC‐6, 7, 8 & 9:

Former Heating Oil UST and Press Pits

  • REC‐10: Abandoned Phenol UST
  • RC‐11: Former Lacquer AST and Peroxide Storage Shed

IDENTIFIED RECOGNIZED ENVIRONMENTAL CONDITIONS

slide-11
SLIDE 11
  • Install Monitoring wells at RECs and at perimeter of

site

  • Remove all pits and sumps and associated impacted

soil and sample

  • Enroll in IEPA Site Remediation Program for focused

No Further Remediation Letter for Contaminants associated with this site

  • Prioritize RECs by location
  • Complete delineation and remediation by REC
  • Prepare Reports by REC, including Site Investigation

Report, Risk Assessment, Remedial Action Plan, and Remedial Action Completion Reports and submit to IEPA for review

REMEDIATION APPROACH

slide-12
SLIDE 12
  • Based on work completed to date, an estimated

8,000 to 9,000 cubic yards of impacted soil will need to be removed and landfilled.

  • Our goal is to remediate the site so as not require

any engineered barriers or construction worker cautions. ESTIMATED REMEDIATION

slide-13
SLIDE 13

PLANNING

TERRY SMITH

slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17

LANDSCAPE ARCHITECTURE

SHARON DICKSON

slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20

ARCHITECTURE

JOE SAFIN

slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24
slide-25
SLIDE 25
slide-26
SLIDE 26
slide-27
SLIDE 27
slide-28
SLIDE 28
slide-29
SLIDE 29
slide-30
SLIDE 30

TRAFFIC ENGINEERING

LUAY ABOONA

slide-31
SLIDE 31
slide-32
SLIDE 32

CIVIL ENGINEERING

CHRIS LINDLEY

slide-33
SLIDE 33
slide-34
SLIDE 34