Lac qui Parle Bridge Project Update Teal Spellman | Project Manager - PowerPoint PPT Presentation

Lac qui Parle Bridge Project Update Teal Spellman | Project Manager June 6, 2017 Agenda Project history Project process and timeline Current activities Next steps Questions mndot.gov/d8/projects/hwy40-bridge-milan/ 2


  1. Lac qui Parle Bridge Project Update Teal Spellman | Project Manager June 6, 2017

  2. Agenda • Project history • Project process and timeline • Current activities • Next steps • Questions mndot.gov/d8/projects/hwy40-bridge-milan/ 2

  3. Project History • 2014 – MnDOT decides to rehabilitate the existing bridge given its historic status. • 2015 – Based on public input, MnDOT delays rehabilitation project and forms Milan Task Force. • 2015/2016 – Milan Task Force makes bridge replacement recommendation to MnDOT. Based on that input, and other public input, MnDOT decides to pursue bridge replacement rather than rehabilitation. • 2017 – MnDOT begins bridge replacement preliminary design. mndot.gov/d8/projects/hwy40-bridge-milan/ 3

  4. Project Process and Timeline 3/22/19 mndot.gov/d8/projects/hwy40-bridge-milan/ 4

  5. Current Activities • Developing preliminary design • Coordinating project activities with Army Corps • Engaging with public and key stakeholders mndot.gov/d8/projects/hwy40-bridge-milan/ 5

  6. Next Steps • Work with State Historic Preservation Office (SHPO) on impacts to historic district • Engage with community on preliminary design concepts • Public open house #1 – June 28 • Public engagement plan (details on next slide) • Prepare preliminary layout • Public open house #2 – September 2017 (tentative date) • Finalize layout - December 2017 (tentative date) • Finalize detail design - 2018 mndot.gov/d8/project s/hwy40-bridge-milan/ 6

  7. Public Engagement ( dates are tentative ) • Local government updates - June 2017; September 2017; winter 2018 • Public open houses - June 2017; September 2017; winter 2018 • Targeted meetings with key stakeholders – June 2017; September 2017, winter 2018 • On-line surveys – July 2017, fall 2017 • Focus groups – July/August 2017 mndot.gov/d8/project s/hwy40-bridge-milan/ 7

  8. Questions? Teal Spellman teal.spellman@state.mn.us 320-214-6350 mndot.gov/d8/project s/hwy40-bridge-milan/ 8

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.