Kopeopeo Canal Remediation Project
Community Liaison Group Meeting
26 February 2019
Kopeopeo Canal Remediation Project Community Liaison Group Meeting - - PowerPoint PPT Presentation
Kopeopeo Canal Remediation Project Community Liaison Group Meeting 26 February 2019 1 Meeting agenda topics Welcome & introduction John Pullar Approval of minutes from previous meeting Communications update Abby
1
26 February 2019
2
3
Dredging trial, 2015 Open day, 2013
4
www.boprc.govt.nz/kopeopeo
former pages
attention)
5
Not perfect (as new website, two websites to one etc). All Kopeopeo related pages on the website in the 2018 year:
History
6
7
8
Legend Containment Site Project Site Boundary Dredging Progress
2.8 km dredged and validated. 21 December 2018 Sections 1-5 Section 7 Section 6
9
10
11
12
13
14
15
16
17
18
19
See the Reports and Key documents page
20
21
The 95% UCL for Total PCDD/F I-TEQ Upperbound results up to the end of Section 5 was 36 pg/g, which is below the remedial target of 60 pg/g.
22
23
24
The 95% UCL for Total PCDD/F I-TEQ Upperbound results up to the end of Section 5 was 36 pg/g, which is below the remedial target of 60 pg/g.
25
26
Karakia – 8 February 2019 Sheep jaw – 21/2/19 Bird bones 20/2/19
27
28
29
30
31
Item No. Comment Incidents 3 H&S: Merlo Env: bulk bin overflow, hose release Dredging 44 Metres dredged in Section 6 Oversize material 18 Oversize bags filled Geotube Bags 2 Part filled From restart to week ending 24 February 2019
32
WE Sunday 24/02/2019
Reset end date 16/06/2019 Inductions CS3 (CS1-302) 41 Refresh and new inductions on going at CS3 site Incidents 1 Merlo rollover into canal - Report to BOPRC pending First Aid 1 WCL operator cut hand - on site Medical Treatment Injury Lost Time Environmental 2 Overflow of bulk bin & main hose release inside WTP area - Internal reports. Security / Other 1 Blue box pump, damage to side door, NZPGS verbally advised ESL - no report Noise monitoring dBA Pending - Comment plant is quieter balance to be reviewed * Oversize records Dates and weights at time of clearing oversize bin GT Bags in use 2 GT 1&2 being filled via one port, adv volume @sg2.2 = 2102t - 955m3 / 44mtrs
33
Dredge instruction/process 18-Feb Restart of dredging operations all checks completed - Section 6 start 14:25 - KP 2.83434 Weekly Operational Information Date Comments Ready Mtrs O/S Weight Bag # Chainage Start Chainage stop Monday 18-Feb Section 6 start. Restart of dredging operations all checks completed. Dredging east to west towards WWTP pipe. Filling GT 1&2, one port loading monitoring GT bags. 15 mins in shaker 2 breaker tripped. Oversize bin clean up - Spill material 4 2.83434 2.83152 Tuesday 19-Feb Continue dredge settling into processes 10 1655 2 2.83152 2.83169 Wednesday 20-Feb Continued dredging west to 11:30am, turned barge and pump connection to start dredging
down canal). 21 1404 4 2.83152 2.85118 Thursday 21-Feb Dredging East to West delivery rubber hose at WTP after magflow slipped off twice. Chain blocked to assist holding it and refitted. Valve vibrated partly closed, secured all ok 4951 11 2.85118 2.87513 Friday 22-Feb FCSE set up to suit FMP for expected rain / bad weather 13 5663 18 2.87513 2.8545 Saturday 23-Feb Non dredge Saturday Sunday 24-Feb Day off. Sub totals 44 13673 18
34