Kopeopeo Canal Remediation Project
Community Liaison Group Meeting
24 April 2018
Kopeopeo Canal Remediation Project Community Liaison Group Meeting - - PowerPoint PPT Presentation
Kopeopeo Canal Remediation Project Community Liaison Group Meeting 24 April 2018 1 Meeting agenda topics Welcome & introduction John Pullar Approval of minutes from previous meeting Communications update Abby Tozer
1
24 April 2018
2
3
4
updates are published
5
6
7
8
9
270m 660m
1180m
1850m
Containment Site 1 CS1
FCS West Dredged to date 20-04-2018 Validated to date 20-04-2018 Lift over bridge 1 Lift over bridge 2 Lift over Paroa Rd Bridge 3 Lift over SH30 Bridge 4
10
Bags 2-7 full & closed Bags 9-10 actively being filled Bag 8 Unrolled ready to fill Bag 1 initial bag partially full
11
12
13
14
15
16
17
18
See the Reports and Key documents page
19
dredging
20
21
The canal sediment Total PCDD/F WHO-TEQ Upperbound results ranged between 23 and 45 pg/g, which is below the remedial target of 60 pg/g.
22
– Tested – Awaiting results for review
Air
Tested – Awaiting results for review
Groundwater
Six groundwater samples (including two duplicates ) were collected from the four monitoring wells located at CS1. Total PCDD/F I-TEQ Upperbound results of between 6.67 and 9.53 pg/L were recorded in the water samples. All were below the adopted Tier 1 trigger level criteria outlined in the Environmental Monitoring and Validation Plan (EMVP) of 13.5 pg/L and the consented limit of 30 pg/g.
Geobags
Tested – Awaiting results for review
Over-sized bulk bags
Tested – Awaiting results for review
23
24
25
At Kope/Orini Pump station Mobile dust monitor at CS3 Example false alarm 3:47am 27 March No dust exceedances in period
26
27