Kopeopeo Canal Remediation Project Community Liaison Group Meeting - - PowerPoint PPT Presentation

kopeopeo canal remediation project
SMART_READER_LITE
LIVE PREVIEW

Kopeopeo Canal Remediation Project Community Liaison Group Meeting - - PowerPoint PPT Presentation

Kopeopeo Canal Remediation Project Community Liaison Group Meeting 24 April 2018 1 Meeting agenda topics Welcome & introduction John Pullar Approval of minutes from previous meeting Communications update Abby Tozer


slide-1
SLIDE 1

1

Kopeopeo Canal Remediation Project

Community Liaison Group Meeting

24 April 2018

slide-2
SLIDE 2

2

Meeting agenda topics

  • Welcome & introduction – John Pullar
  • Approval of minutes from previous meeting
  • Communications update – Abby Tozer
  • Project update – Brendon Love/Ken Tarboton
  • Independent Monitor – Matt James
  • Cultural Monitor – Eula Toko
  • Health, Safety and Monitoring – Des McCleary
  • Other business
  • Light lunch
slide-3
SLIDE 3

3

Communications

  • Website www.boprc.govt.nz/kopeopeo
  • Project page updates
  • Pedestrian accessway open
  • CLG site tour
slide-4
SLIDE 4

4

Project page

  • Register to follow the project
  • You’ll get email alerts when

updates are published

  • You can unfollow at any time
slide-5
SLIDE 5

5

Kopeopeo – Orini Public Access Path

slide-6
SLIDE 6

6

CLG Site Tour

slide-7
SLIDE 7

7

Project update

Overview

  • Progress made over previous period
  • Dredging (progress, monitoring, validation)
  • CS3 Enabling works
  • CS3 Works
  • Public access
  • Activities planned for upcoming period
slide-8
SLIDE 8

8

Overview of progress

(5 March – 20 April)

 Main dredging completed to Paroa Road  First section complete and validated  Second lift over bridge completed  CS3 enabling works mostly complete  CS3 final design approved by Consent Authority  Pump station canal dredging started  Weed removal carried out to Paroa Road  Alternative pedestrian access to Whakatāne river stopbank constructed

slide-9
SLIDE 9

9

Dredging progress

270m 660m

  • S1. 270m
  • S2. 390m

1180m

  • S3. 520m

1850m

  • S4. 670m

Containment Site 1 CS1

FCS West Dredged to date 20-04-2018 Validated to date 20-04-2018 Lift over bridge 1 Lift over bridge 2 Lift over Paroa Rd Bridge 3 Lift over SH30 Bridge 4

slide-10
SLIDE 10

10

Geobags filled

Bags 2-7 full & closed Bags 9-10 actively being filled Bag 8 Unrolled ready to fill Bag 1 initial bag partially full

slide-11
SLIDE 11

11

Barge lift over second bridge

slide-12
SLIDE 12

12

Sand bug operations

slide-13
SLIDE 13

13

Weed removal

slide-14
SLIDE 14

14

Wood pellet processing

slide-15
SLIDE 15

15

CS3 preliminary works

slide-16
SLIDE 16

16

CS3 works

slide-17
SLIDE 17

17

Activities planned for upcoming period

  • Progress dredging in Section 4
  • CS3 construction based on final design
  • Processing of eels
  • Ongoing weed removal ahead of large
  • bjects
  • Sand-bug dredging under bridges and

Kope/Orini pump intake channel

slide-18
SLIDE 18

18

Independent Monitor monthly report available on website

See the Reports and Key documents page

slide-19
SLIDE 19

19

Independent Monitor update

  • Powerpole incident investigation ongoing
  • CLG site visit
  • Excavator removing weed ahead of

dredging

  • Complaints received – Dredging and dust
  • Eel removal report reviewed
  • MP8 turbidity monitor installed
  • Bone finds at CS3
  • FCS-East fixed
  • Sand bug dredging
slide-20
SLIDE 20

20

ACM & Wood Waste at CS3

slide-21
SLIDE 21

21

Canal Sediment Validation

The canal sediment Total PCDD/F WHO-TEQ Upperbound results ranged between 23 and 45 pg/g, which is below the remedial target of 60 pg/g.

slide-22
SLIDE 22

22

Dioxin Air & Groundwater Monitoring

– Tested – Awaiting results for review

Air

Tested – Awaiting results for review

Groundwater

Six groundwater samples (including two duplicates ) were collected from the four monitoring wells located at CS1. Total PCDD/F I-TEQ Upperbound results of between 6.67 and 9.53 pg/L were recorded in the water samples. All were below the adopted Tier 1 trigger level criteria outlined in the Environmental Monitoring and Validation Plan (EMVP) of 13.5 pg/L and the consented limit of 30 pg/g.

Geobags

Tested – Awaiting results for review

Over-sized bulk bags

Tested – Awaiting results for review

slide-23
SLIDE 23

23

Cultural Monitor update

  • Recent finds –

determined by Archaeologist to be modern, not archaeological artefacts

  • Modified protocol
slide-24
SLIDE 24

24

Health, Safety & Environment

  • Safety incident regarding
  • verhead powerlines

investigated

  • CS3 Site closed to public
  • Asbestos find at CS3 and

sampling

  • Disposal of material from

trial site

slide-25
SLIDE 25

25

Dust Monitoring – CS3

At Kope/Orini Pump station Mobile dust monitor at CS3 Example false alarm 3:47am 27 March No dust exceedances in period

slide-26
SLIDE 26

26

Traffic Management

  • CS3 traffic

management

  • Road closures

associated with each crane lift

slide-27
SLIDE 27

27

Other Business

  • Next meeting: Tuesday 29th May 2018
  • Tech Talk at next meeting – Monitoring

system by Karam de Lacey of Control Tech