SLIDE 1 Kitchen Creek CREP & Stream Bank Stabilization Project
Project Sponsors: Greenbrier Valley Conservation District West Virginia Conservation Agency U.S.D.A Natural Resources Conservation Service U.S.D.A NRCS Appalachian Plant Materials Center U.S.D.A Farm Service Agency U.S. Fish & Wildlife Service Trout Unlimited Greenbrier River Watershed Association West Virginia Division of Highways District Nine Ducks Unlimited Clinton Kirk, Landowner
This project is intended to demonstrate the importance and feasibility of utilizing buffers along streams to prevent non-point source pollution from agriculture and cost effective methods of stream bank stabilization for erosion control.
SLIDE 2
Eroded stream bank is sloped to reduce energy from high water Site 1
SLIDE 3
Straw erosion control blanket is put down to hold soil short term
SLIDE 4
Erosion control blanket is trenched in to prevent high water from undercutting
SLIDE 5
Trees and grass is planted to hold soil long term
Trees provided by NRCS Plant Materials Center
SLIDE 6
Site 1, one week after completion
SLIDE 7
Site 2
SLIDE 8
Stream bank is sloped
SLIDE 9
Erosion control blanket, trees and grass is applied to the site
SLIDE 10
Grass seed is applied to the disturbed riparian area and a 4- weeler is used as a cultipacker
SLIDE 11
Site 2, one week after completion
SLIDE 12
Site 3, before restoration
SLIDE 13
Banks are sloped and seeded
SLIDE 14
Footers are dug for log vain construction
SLIDE 15
When necessary, wildlife was removed from the site and relocated
SLIDE 16
Log vain anchored into stream bank
SLIDE 17
When available, rocks and trees from the site were used
SLIDE 18
Completed log structure
SLIDE 19
Completed log structure
SLIDE 20
Sometimes the erosion control blankets needed to be cut to fit the site
SLIDE 21
Site 3, after completion
SLIDE 22
Site 4
SLIDE 23
Bermuda Grass from NRCS Plant Materials Center used to mulch and re-vegetate site
Rock bar pulled out of stream and used to re-build the eroded stream bank
SLIDE 24
Landowner spreads Bermuda grass sprigs
SLIDE 25
Bermuda grass sprigs must be watered when they are applied
SLIDE 26
Bermuda grass sprigs one week after application
SLIDE 27
Site 4 Before After restoration restoration
SLIDE 28
Site 5
SLIDE 29
Highly eroded banks
SLIDE 30
SLIDE 31
SLIDE 32
SLIDE 33
Placing rock for structure near bridge
SLIDE 34
SLIDE 35
SLIDE 36
Large rock was brought in from a local quarry for the structure
SLIDE 37
Large flat rocks existing on the property were used as footers for the rock vain
SLIDE 38
Completed rock vain
SLIDE 39
Fence building crew form the U.S. Fish & Wildlife Service and Trout Unlimited build CREP buffer fence
SLIDE 40
SLIDE 41
SLIDE 42
SLIDE 43
Spring gates are installed as needed
SLIDE 44
Electric fence charger and signs are included with this fence
SLIDE 45
Bird house and wood duck box also provided