Kamehameha Highway Emergency Shoreline Improvements, Vicinity of Kaaawa Project No. 83D-01-15 Kaaawa Elementary School Public Meeting April 21, 2015 7:00 p.m. STATE OF HAWAII -1- Department of Transportation MEE EETIN ING G AGEN


  1. Kamehameha Highway Emergency Shoreline Improvements, Vicinity of Kaaawa Project No. 83D-01-15 Kaaawa Elementary School Public Meeting April 21, 2015 7:00 p.m. STATE OF HAWAII -1- Department of Transportation

  2. MEE EETIN ING G AGEN ENDA • Project Purpose • Discuss Alternative Concepts • Receive Community Input STATE OF HAWAII -2- Department of Transportation

  3. PR PROJEC ECT T LOCATION TION MAP Crouching Lion Inn Utility Poles STATE OF HAWAII -3- Department of Transportation

  4. SI SITE E PH PHOTOS Condition in January 2015 STATE OF HAWAII -4- Department of Transportation

  5. SI SITE E PH PHOTOS Temporary Fix STATE OF HAWAII -5- Department of Transportation

  6. SI SITE E PH PHOTOS Continual Pavement Cracking along Lane Line STATE OF HAWAII -6- Department of Transportation

  7. SI SITE E PH PHOTOS Undermining of Pavement Structure STATE OF HAWAII -7- Department of Transportation

  8. SI SITE E PH PHOTOS CRM Wall Overturning STATE OF HAWAII -8- Department of Transportation

  9. EM EMER ERGEN ENCY CY PR PROCLAMA LAMATION TION • Emergency Proclamation dated 4-10-15 • Intended to “prevent the danger of disaster damages, losses, and suffering, and to protect the health, safety, and welfare of the people” • Emergency shoreline work is proposed to prevent closure of the highway due to wave erosion damage • http://1.usa.gov/1FuVbWl STATE OF HAWAII -9- Department of Transportation

  10. CONST STRU RUCTI CTION ON OPT PTIONS ONS • Option 1 – 24/7 Lane Closure – 1 Lane closed 24/7 – No night work – Approx. Construction Duration: 3½ - 4 months – Probable Construction Cost: ~$5.4M • Option 2 – 24/7 Lane Closure with Continuous Work – 1 Lane closed with work on-going 24/7 (including nights and weekends) – Approx. Construction Duration: 3 months – Probable Construction Cost: ~$7.1M • Option 3 – Lane Closure during Working Hours Only – 1 Lane closed during daytime working hours – 2 Lanes open during night-time non-working hours – Approx. Construction Duration: 5 months – Probable Construction Cost: ~$6.6M STATE OF HAWAII -10 10- Department of Transportation

  11. OPT PTIO ION 1 – 24/7 LANE C E CLOSU SURE • 1 Lane closed 24/7 • Temporary Traffic Signal for Contraflow • Work Hours – Monday to Friday - 7:00 a.m. to 6:00 p.m. • No Night Work • Moderate Duration • Least Costly (~$5.4M) STATE OF HAWAII -11 11- Department of Transportation

  12. OPTI PTION ON 2 – 24/7 /7 LAN ANE CL E CLOSU SURE E WITH CONTIN TINUOU UOUS S WORK • 1 Lane Closed 24/7 • Temporary Traffic Signal for Contraflow • Work 24/7 (including nights and weekends) • Shortest Duration • Most Costly (~$7.1M) • Most Noise Nuisance STATE OF HAWAII -12 12- Department of Transportation

  13. OPT PTIO ION 1 & 2 & 2 – CONTRAFL FLOW OW LANE STATE OF HAWAII -13 13- Department of Transportation

  14. OPTI PTION ON 1 & 2 & 2 – 24/7 /7 LAN ANE CL E CLOSU SURE RE Excavated Gravity Wall STATE OF HAWAII -14 14- Department of Transportation

  15. OPTI PTION ON 3 – LAN ANE CL E CLOSU SURE E DURING G WORKI KING G HOURS S ONLY • 1 Lane closed during daytime working hours – Monday to Friday - 7:00 a.m. to 6:00 p.m. • 2 Lanes open during night-time non-working hours • No Night Work • Moderate Cost (~$6.6M) • Longest Duration STATE OF HAWAII -15 15- Department of Transportation

  16. OPTI PTION ON 3 – LAN ANE CL E CLOSU SURE E DURING G WORKI KING G HOURS S ONLY Sheetpile Wall STATE OF HAWAII -16 16- Department of Transportation

  17. ROCK K REV EVET ETMEN ENT T PR PREC ECAST ST WALL • Option 1 or Option 2 – 24/7 Lane Closure – Construction can proceed in large increments – Multiple activities can occur concurrently – Shorter duration • Option 3 - Lane Closure during Working Hours Only – Staged for daily completion – Longer duration STATE OF HAWAII -17 17- Department of Transportation

  18. ROCK K REV EVET ETMEN ENT T PR PREC ECAST ST WALL Precast Wall STATE OF HAWAII -18 18- Department of Transportation

  19. OTHER ER PR PROPO POSE SED PR PROJEC ECT T EL ELEM EMEN ENTS • Existing roadside trees to be removed • Existing bus stop to be relocated nearby during construction • Resurface entire roadway width at project completion • Archaeological monitor will be on site during all ground disturbing activities • Contractor’s staging and storage area will be located in Crouching Lion Inn parking lot STATE OF HAWAII -19 19- Department of Transportation

  20. SC SCHED EDULE August April 2015 May 2015 April 2015 2015 Environmental Engineering Begin Permitting and Complete Design Construction Public Input Construction STATE OF HAWAII -20 20- Department of Transportation

  21. LIST STEN ENING ING SE SESS SSION • Questions / Comments STATE OF HAWAII -21 21- Department of Transportation

  22. MAHALO Hawaii Department of Transportation (808) 587-2160 dotpao@hawaii.gov Presentation is available for viewing at: http://hidot.hawaii.gov/presentations/ Project Updates and Lane Closure Information: http://hidot.hawaii.gov/ STATE OF HAWAII -22 22- Department of Transportation

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.