Woodbrook Landfill Coastal Protection And Cliff Stabilisation - - PowerPoint PPT Presentation

woodbrook landfill
SMART_READER_LITE
LIVE PREVIEW

Woodbrook Landfill Coastal Protection And Cliff Stabilisation - - PowerPoint PPT Presentation

Woodbrook Landfill Coastal Protection And Cliff Stabilisation Preferred Emerging Solution Woodbrook Landfill Historic Landfill along 300m of coastline Eroding coastline 0.3m/year Oversteep cliff Landfill material is falling from


slide-1
SLIDE 1

Woodbrook Landfill

Coastal Protection And Cliff Stabilisation Preferred Emerging Solution

slide-2
SLIDE 2

Woodbrook Landfill

  • Historic Landfill along 300m of coastline
  • Eroding coastline 0.3m/year
  • Oversteep cliff
  • Landfill material is falling from the cliff face
  • nto the beach at Woodbrook

2 Woodbrook landfill Rev A 09/05/2018

slide-3
SLIDE 3

Coastal Protection - Need

  • Ongoing erosion – 0.3m/year
  • Cliff instability – Over-steep Cliff
  • Historic Landfill Site
  • Prevention of historic landfill material entering

the sea

3 Woodbrook landfill Rev A 09/05/2018

slide-4
SLIDE 4

Woodbrook Landfill

  • Coastal Protection

– Reduce ongoing Cliff Erosion

  • Cliff Stabilisation

– Prevent Cliff Failure

4 Woodbrook landfill Rev A 09/05/2018

slide-5
SLIDE 5

Landfill Site

  • Historic – pre 1968
  • Mostly builder’s rubble
  • Top 2m to full height
  • Contaminant Levels Low
  • Tier 2 Assessment
  • Remedial Measures Appraisal

Woodbrook landfill Rev A 5 09/05/2018

slide-6
SLIDE 6

Landfill Site – Recent Assessments

  • Tier 2 Risk Assessment - FT
  • Appraisal of Remedial Measures - FT

– Construction materials and some ACM – Risk from leachate is low – Leave material on site – Prevent further loss of material into sea

  • Coastal Protection Measures - MWP

– Reinforced concrete seawall – Sheet piling – Full height revetment – Revetment to cliff toe with cliff stabilisation

  • Preliminary Design

– Revetment options

Woodbrook landfill Rev A 6 09/05/2018

slide-7
SLIDE 7

Preliminary Design

  • Full Height Revetment
  • Revetment to cliff toe and regrade face of

upper cliff to stable slope

  • Sediment sampling and Analysis
  • Preferred design

– Revetment to cliff toe and regrade face of upper cliff is feasible

Woodbrook landfill Rev A 7 09/05/2018

slide-8
SLIDE 8

Preliminary Design

09/05/2018 Woodbrook landfill Rev A 8

slide-9
SLIDE 9

Preliminary Design

  • Key Quantities

– Primary Armour:9,000m3 – Underlayer:4,500m3 – Mattressing: 600m2 – Cliff regrading: 5,500m3

Woodbrook landfill Rev A 9 09/05/2018

slide-10
SLIDE 10

Preliminary Design

  • Programme

– 4 to 6 months

  • Source of materials

– Primary armour

  • Access to Site

– By Road

Woodbrook landfill Rev A 10 09/05/2018

slide-11
SLIDE 11

Assessments

  • Conservation architecture
  • Archaeology
  • AA screening
  • Coastal Processes

09/05/2018 Woodbrook landfill Rev A 11

slide-12
SLIDE 12

Conservation Architecture

  • Railway Bridge Abutments
  • Historic Railway Seawall
  • The abutments are within the footprint of the

proposed works

  • The abutments will be lost whether or not the

works proceed.

09/05/2018 Woodbrook landfill Rev A 12

slide-13
SLIDE 13

Archaeology

  • Railway structures
  • Historic forest
  • Avoid if possible
  • Preserve by record if not
  • Monitor construction works

09/05/2018 Woodbrook landfill Rev A 13

slide-14
SLIDE 14

AA Screening

  • Assesses potential impacts on SAC/SPA
  • No significant adverse impact

09/05/2018 Woodbrook landfill Rev A 14

slide-15
SLIDE 15

Coastal Processes

  • Extreme water levels – 2%AEP
  • Extreme wave conditions – depth limited
  • Shingle and cobbles on upper shore
  • Sand on lower shore
  • Sediment transport analysis
  • Potential impacts:

– Lack of material for sediment budget – 4% – Increased erosion immediately north - localised

09/05/2018 Woodbrook landfill Rev A 15

slide-16
SLIDE 16

Woodbrook Landfill

Coastal Protection And Cliff Stabilisation Preferred Emerging Solution