CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE
SITE CONSTRAINTS and POTENTIALS CONCEPT MASTERPLAN OF FORMER - - PowerPoint PPT Presentation
SITE CONSTRAINTS and POTENTIALS CONCEPT MASTERPLAN OF FORMER - - PowerPoint PPT Presentation
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE SITE CONSTRAINTS and POTENTIALS CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE SITE CONSTRAINTS FLOOD MAP CARRICKLEE LANDFILL SITE CONCEPT MASTERPLAN OF
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE SITE CONSTRAINTS – FLOOD MAP
CARRICKLEE LANDFILL SITE
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE SITE CONSTRAINTS – DRAWING NR 83733-03
KEY SITE CONSTRAINTS
- EXISTING LANDFILL SITE
- ACCESS TO RIVER
- LEVEL CHANGES
- POTENTIAL CONTAMINATION AND COSTS
- DEVELOPMENT COSTS (ABNORMAL COSTS)
- COSTS FOR SURVEYS + MONITORING TIME
(COULD BE 2 YEARS+)
- PLANNING COSTS AND ENVIRONMENTAL
STATEMENT, AND TIMESCALE
- A5 WTC CONSTRUCTION PROGRAMME
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE SITE POTENTIALS – DRAWING NR 83733-04
KEY SITE POTENTIALS
- NEW ACCESS TO RIVER AND
BLUE WAY AND PROVISION OF BLUE WAY RESTING AREA, AND IMPROVED ANGLING ACCESS
- DEVELOPMENT OF UNDERUTILISED
LAND BANK
- PROVISION OF NEW FACILITIES
NOT WITHIN THE REGION - FOR CYCLISTS, BOAT USERS AND MOTORHOME USERS
- RURAL LOCATION ACCESSIBLE BY
ROAD, CYCLE, FOOT AND BOATS
- POTENTIAL EMPLOYMENT - PARK
AND CAFÉ
- INCREASED TOURISM AND VISITOR
- POTRNTIAL
FOR STRABANE AREA
- RESTORATION OF DCSDC LANDS
SITE CONSTRAINTS – INDICITIVE SURVEY AND INVESTIGATIONS AND COSTS THAT MAY BE REQUIRED TO PROGRESS THE SCHEME THROUGH TO PLANNING STAGE
Item Description Notes Estimated Cost Range Excluding VAT
1. Additional Topographical Survey of trees on site and particularly along the Urney Road and a Tree/Arboricultural Report for the existing trees undertaken Likely to be required by Planning Timescale potentially 4-8 weeks - Existing trees are likely to be removed for sight line purposes £3,500 - £4,500 2. Preliminary Risk Assessment (PRA) Tendered and completed £325.00 - £325.00 3. Site investigation / Generic Quantative Risk Assessment (GQRA) £50k included in RPS Report in 2010. Timeframe TBC £50,000 - £70,000 4. Flood Constraints Report Already tendered for and would take 2-3 weeks to- complete. No Client instruction to make an appointment.
- verview – likely to be required for Planning
- Approx. Costs to eradicate Himalayan Balsam - may take 2- 3
- nly
POTENTIAL SURVEYS/INVESTIGATIONS REQUIRED FOR PLANNING AND DESIGN AND DEVELOPMENT (AND COSTS) Potential/surveys/studies/investigations/planning costs that may be required and for further Design Development, and an indicative cost estimate range of the same based on initial desktop studies and background to the Stage 1 and Stage 2 elements of the works is outlined in Table 1 (Right) Note: The Costs provided are estimates only, and the purpose of this collation of survey/investigation and costs is to provide the Client with a best estimate of an overall potential cost for this work, for their
- consideration. All surveys and additional studies required for this complex
site would need to be confirmed by Planning Service and their Statutory advisors e.g. NIEA. This list cannot be fully ratified until direction and guidance is provided by Planning Service during the PAD process, an also as a Concept Design is better developed, and the function and use of the site is better determined, and agreed with the Client Team. Excludes Construction Costs and Professional Fees, Economic Appraisal and Project Management and CPD Costs etc.
Note: Items in Blue Text - Prices already received - No VAT applicable on Planning Fees – TBC
TOTAL ESTIMATED COST RANGE TO DATE: £242,157.00 - £312,232.00 Ex VAT where applicable
TIMESCALES
MANY OF THE INVESTIGATIONS AND REPORTS WOULD REQUIRE EXTENSIVE TIMESCALES FOR PRODUCTION AND COMPLETION.
- LOUGHS AGENCY HAVE SUGGESTED A 2 YEAR PERIOD OF
GAS AND LEACHATE STUDIES AND REPORTING BEFORE ANY WORK COMMENCES ON SITE
- ECOLOGICAL SURVEYS ARE RESTRICTED TO CERTAIN TIMES
OF THE YEAR
- AN ENVIRONMEMTAL STATEMENT / IMPACT ASSESSMENT MAY
REQUIRE 6-8 MONTHS TO COMPLETE (ONCE OTHER SURVEYS HAVE BEEN UNDERTAKEN)
- PLANNING TIMESCALES ARE ALWAYS UNCERTAIN AND ARE
DIFFICULT TO QUANTIFY EXACTLY
TABLE 1 - POTENTIAL LIST OF SURVEYS, INVESTIGATIONS, PLANNING FEES AND ESTIMATED COSTS
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE
CONSULTATIONS
SUMMARY OF CONSULTEES CONTACTED DURING THE STAGE 1 AND STAGE 2 PROCESS:
- Loughs Agency – Kevin Wilson (Director of Development)
- A5 WTC Team – Manny Gault (Dept. of Infrastructure)
- NIEA (Countryside and Coast Section) – Donna Thompson
- Glen Oaks Day Centre ( A Disability Action Centre operated by the Western Health Trust) Which have
clients with all 3 main types of disabilities – Visual Impairment; Physical Disabilities; and Impaired Brain Injuries) – Patricia Doherty
- Planning Service PAD application Nr. LA/11/2018/1176 PAD (Meeting held on 15.11.2018 and Completed NI
Biodiversity checklist issued January 2019 (Andree McNee and Sarah Barrett)
- DERRY CITY AND STRABANE DISTRICT COUNCIL:
- Parks Manager – Colin Kennedy
- Play Officer – Helen Turton
- Greenway Development Section – Manager Jonathan Henderson and Mike Savage
- Biodiversity Officer – Christine Doherty
- Inclusion and Access Officer – Louise Boyce
- Grounds Maintenance Section – John Quinn
- Environmental Health Dept. – Richard Black
- Environmental Engineering Dept. – Niall McLaughlin
- Environment Regeneration Directorate. – Conor Canning and Karen Kirkegaard
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE
STAGE 2 INITIAL CONCEPT MASTERPLAN
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE INITIAL CONCEPT – DRAWING NR 83733- 05
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE TAYLOR + BOYD - PRELIMINARY SECTIONS
SECTION LINES - LOCATION TYPICAL SECTION - B TYPICAL SECTION - A
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE CONCEPT MASTERPLAN – DRAWING NR 83733- 06
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE CONCEPT MASTERPLAN – CONCEPT IMAGES
RIVERSIDE IMAGES AND BLUE WAY AIRES DE SERVICE PARK AND SMALL SERVICES BUILDING THEMED PLAY PARK DISABLED TOILETS AND SHELTER JUNIOR AND SENIOR PUMP TRACK BMX TRACK MEADOW/WILDFLOWER/ YOUNG WOODLAND GARDENS PUBLIC ARTWORKS CARRICKLEE CENTRAL HUB BUILDING AS IN BROOKE PARK PAVILION CANOE STEPS AND SLIPWAY
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE
PROGRAMME (To be updated)
CONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE PROGRAMME SHEET 1 of 2
DATE OF PROJECT BOARD MEETING TBCCONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE PROGRAMME SHEET 2 of 2
DATE OF PROJECT BOARD MEETING TBCCONCEPT MASTERPLAN OF FORMER CARRICKLEE LANDFILL SITE, STRABANE
COSTS
NOTES ON INITIAL COSTS FOR THE STAGE 2 PROCESS (WORK IN PROGRESS TO BE UPDATED ON MORE DETAILED DESIGN DEVELOPMENT CURRENTLY BEING PROGRESSED):
- ESTIMATED SURVEY AND INVESTIGATION COSTS FOR PLANNING
TOTAL ESTIMATED COST RANGE TO DATE: £242,157.00 - £312,232.00 Ex VAT
- MOST SIGNIFICANT SURVEY COSTS IN THE ABOVE ARE FOR A SITE INVESTIGATION /GENERIC
QUANTATIVE RISK ASSESSMENT (GQRA) IN THE ORDER OF £50,000 - £70,000……THEN THERE IS THE TIMESCALE FOR PEPARING THE BRIEF, PROCUREMENT OF SITE INVESTIGATION CONTRACTORS, TIMESCALE ON SITE, TIMESCALE FOR FORENSIC ANALYSIS OF MATERIALS AND COSTS ASSOCIATED WITH RECOMMENDATIONS PRIOR TO ANY FURTHER DETIL DESIGN WORK
- ABNORMAL COSTS FOR CONSTUCTION ON A LANDFILL SITE), AND WILL HAVE A SIGNIFICANT
IMPACT ON ANY IDENTIFIED CONSTRUCTION AND DEVELOPMENT COSTS.
- SITE MONITORING COSTS OVER A REQUIRED PERIOD FOR GAS AND LEACHATE MONITORING
(PERHAPS OVER A 2-3 YEAR PERIOD – LOUGHS AGENCT SUGGESTED SEVERAL YEARS OF MONITORING)
- POTENTIAL FUNDERS ASSISTANCE E.G. SPORTS NI (FOR SPECIALIST CYCLING TRACKS)
- FITURE DCSDC INTERNAL ADMINISTRATION AND PROJECT MANAGEMENT COSTS
- FUTURE ICT DESIGN FEES AND SUPERVISION
- CONSTRUCTION COSTS AND ABNORMAL SITE WORKS COSTS FOR A LANDFILL SITE