Joint Convention on the Safety of Spent Fuel Management and on the - - PowerPoint PPT Presentation

joint convention on the safety of spent fuel management
SMART_READER_LITE
LIVE PREVIEW

Joint Convention on the Safety of Spent Fuel Management and on the - - PowerPoint PPT Presentation

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management The United Kingdom of Great Britain and Northern Ireland NATIONAL REPORT PRESENTATION for the Third Review Meeting 11 th to 20 th May


slide-1
SLIDE 1

1

The United Kingdom of Great Britain and Northern Ireland NATIONAL REPORT PRESENTATION for the Third Review Meeting 11th to 20th May 2009 Vienna

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management

slide-2
SLIDE 2

2

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management

Presented by Dr Mike Weightman

HM Chief Inspector of Nuclear Installations, Health & Safety Executive and

Dr Joe McHugh

Head of Radioactive Substances Regulation, Environment Agency

slide-3
SLIDE 3

3

Presentation Structure

Morning

  • Introduction
  • Overview of Radioactive Waste and Spent

Fuel Management in the UK

  • Major Developments since 2006
  • Action on Challenges from last Review

Meeting

  • Current Challenges
  • Significant Events since last Review Meeting

Afternoon

  • Questions and Comments
  • Planned measures to improve safety
  • Summary
slide-4
SLIDE 4

4

The UK Report

  • Prepared from inputs of

Government Departments, Regulatory Bodies, and Industry

  • Explains how the UK

achieves and maintains a high level of safety and environmental protection in spent fuel and radioactive waste management

slide-5
SLIDE 5

5

Scope

9Reprocessing

X Naturally

  • ccurring

radioactive material X Defence programme waste

slide-6
SLIDE 6

6

National Overview

  • Regulatory Bodies and
  • verall objectives of

National Arrangements

  • Overview of:
  • policy
  • funding of liabilities
  • current practices

and

  • planned practices
slide-7
SLIDE 7

7

Regulatory Bodies

National Overview

  • HSE) / Nuclear

NII)

  • ) or Scottish

SEPA) Health & Safety Executive ( Installations Inspectorate ( Environment Agency (EA Environment Protection Agency (

slide-8
SLIDE 8

8

Safety Environment Regulatory Bodies

National Overview

slide-9
SLIDE 9

9

Northern Ireland

National Overview

There are no nuclear installations in Northern Ireland Northern Ireland has its own regulatory system and bodies that parallel those in the rest of the UK

slide-10
SLIDE 10

10

Nature of UK Regulatory Framework

  • Goal Setting

– Minimisation of risk so far as is reasonably practicable – ALARP / ALARA / BPEO / BPM

  • Emphasis in legislation

– Responsibilities and competence of Operators – Robust arrangements – Early, open and transparent engagement

Regulatory Framework

National Overview

slide-11
SLIDE 11

11

Nuclear Site Licence HSE grant this under the Nuclear Installations Act, and can attach conditions:

  • In the interests of safety
  • With respect to handling, treatment

and disposal of nuclear matter Nuclear Site Licence applies to all people

  • n the site. The site licensee is responsible

for ensuring compliance

Regulatory System

National Overview

slide-12
SLIDE 12

Regulatory System

Licence Conditions Goal setting: “Licensee must make and implement adequate arrangements” “Adequate arrangements” can be tailored to:

  • Suit business need
  • Suit the stage of operation – from

construction to decommissioning Covers various aspects including radioactive waste management and decommissioning

National Overview

12

slide-13
SLIDE 13

13

Disposal Authorisation

  • Prior authorisation needed from EA or SEPA

for the discharge and disposal of radioactive waste

  • Determining an application involves

appropriate consultation with stakeholders e.g. HSE, FSA, Local Authority, public

  • Reviewed periodically
  • Attach conditions to the authorisation

Regulatory System

National Overview

slide-14
SLIDE 14

14

Basic Policy Safety and Environment

National Overview

UK Government’s basic policy is to ensure adequate statutory powers and

  • ther measures to

protect people and the natural environment from harmful levels of radioactivity

slide-15
SLIDE 15

15

  • Must meet LIMITS

and

  • Reduce further in

line with: ALARP/BPEO/BPM (Taking into account all relevant factors)

No of Persons >6mSv/y 20 40 60 80 100 2000 2001 2002 2003 2004 2005 2006 YEAR No of Persons

2000 2001 2002 2003 2004 2005 2006 2007 0.5 1.0 1.5 2.0 2.5

Trends in radioactive discharges to water and air

Weighted discharges relative to 2000

Water Air

Basic Policy Safety and Environment

National Overview

slide-16
SLIDE 16

16

Overview - Policies

Specific Policies for:

  • Spent Fuel

Management

  • Nuclear Fuel Cycle

and Application Wastes Management

  • Decommissioning

and

  • Disused Sealed

Sources

slide-17
SLIDE 17

17

Reprocess/not reprocess - commercial judgment of the

  • wners

Spent fuel is not waste while the option of reprocessing the fuel remains open The current assumption is that the spent nuclear fuel from new UK reactors will not be reprocessed

Spent Fuel

Overview Policies Spent Fuel

slide-18
SLIDE 18

18

Overview Policies Radwaste Management

Definition of Waste

Definition of Waste

  • It is the decision of the owner of any radioactive

material as to whether there is any foreseen use and hence whether it is radioactive waste

  • Regulatory control is the same under nuclear

licensing whether or not it is declared as waste – hence the type and level of regulatory control does not depend on such decisions by the

  • wners
slide-19
SLIDE 19

19

Overview Policies Radwaste Management

Radwaste Management General

  • Sustainable development principles

Application of the waste hierarchy Wastes to be safely and appropriately managed, treated, and then disposed of in ways which protect public, workforce and the environment

slide-20
SLIDE 20

20

Overview Policies Radwaste Management

Categorisation

  • VLLW

– Can be disposed of with ordinary refuse – <400kBq (βγ) in 0.1m3, <40kBq (βγ) per item

  • LLW

– not exceeding 4GBq/te (α) or 12 GBq/te (βγ)

  • ILW

– Greater specific activity than LLW but no need to consider self heating

  • HLW

– Need to consider self heating

slide-21
SLIDE 21

21

Overview Policies Radwaste Management

Higher Activity Wastes

(HLW, ILW and LLW not suitable for existing LLW disposal facilities)

  • Safe and secure interim storage, followed by:

– (England and Wales) geological disposal – (Scotland) long term near site near surface storage

  • More details later under developments since

2006

slide-22
SLIDE 22

22

Overview Policies Radwaste Management

Low Level Waste

  • Priorities

– Minimise creation – Greater flexibility than currently exists – Maintain focus on safety and environmental protection – Create a UK wide strategy

slide-23
SLIDE 23

23

Overview Policies Radwaste Management

Discharges

Based on optimisation: Best Practicable Environmental Option (BPEO) and Best Practicable Means (BPM) Progressive reduction of discharge limits

slide-24
SLIDE 24

24

Overview Policies Decommissioning

Decommissioning

  • Progressive reduction of hazards

As soon as reasonably practicable Development of Strategies and plans – The objective of a strategy is to get the best solution overall taking into account the needs of the environment, and safety of workers and the local community

slide-25
SLIDE 25

25

Disused Sealed Sources

Overview Policies Disused Sealed Sources

  • The holder is responsible for any disused

sealed sources until: – returned to supplier – transferred to another holder – sent for storage, disposal or recycling

  • The holder is also responsible for security and

financial provision

slide-26
SLIDE 26

26

Overview - Funding

Funding arrangements etc. for:

  • General Liabilities
  • NDA owned sites
  • New Build Reactors and
  • Disused Sealed Sources
slide-27
SLIDE 27

27

Overview Funding of Liabilities Spent Fuel & Radwaste

General Funding

  • It is the responsibility of the waste owners to

provide funds for radioactive waste/ spent fuel management and decommissioning

  • The published audited accounts of UK
  • perators include details of waste

management costs and of the provisions made in order to meet them

slide-28
SLIDE 28

28

Overview Funding of Liabilities Spent Fuel & Radwaste

NDA Owned Sites

  • Site Licensees may charge radioactive waste

& spent fuel management and decommissioning costs to the NDA provided they are incurred in compliance with their contract

  • NDA is funded directly from central

Government, through its sponsoring Department, DECC

slide-29
SLIDE 29

29

Overview Funding of Liabilities Spent Fuel & Radwaste

New Build Reactors

  • A Funded Decommissioning Programme

(FDP), approved by Government, must be in place before construction The Nuclear Liabilities Financing Assurance Board (NLFAB) will scrutinise the financing plans Arrangements have had the benefit of consultation

slide-30
SLIDE 30

30

Overview Funding of Liabilities Disused Sealed Sources

Disused Sealed Sources

High-Activity Sealed Sources (HASS) Regulations require financial provision for disposal or an acceptable alternative (for example, return to supplier) when sources are acquired

slide-31
SLIDE 31

31

Overview Funding of Liabilities Disused Sealed Sources

Disused Sealed Sources

Legacy UK Government funded programme 2004-2008 Contingency funds for removal of orphan sources

slide-32
SLIDE 32

32

Overview – Current Practices and Facilities

UK Facilities

slide-33
SLIDE 33

33

Overview Current Practices UK Facilities

Magnox Stations

slide-34
SLIDE 34

34

Overview Current Practices UK Facilities

Magnox Stations

  • Berkeley
  • Bradwell
  • Calder Hall
  • Chapelcross
  • Dungeness A
  • Hunterston A
  • Hinkley Point A
  • Sizewell A
  • Trawsfynydd
  • Oldbury
  • Wylfa
slide-35
SLIDE 35

35

Overview Current Practices UK Facilities

AGR and PWR Stations

slide-36
SLIDE 36

36

Overview Current Practices UK Facilities

AGR and PWR Stations

AGR Stations PWR Station

  • Dungeness B
  • Hartlepool
  • Heysham I and II
  • Hinkley Point B
  • Hunterston B
  • Torness
  • Sizewell B
slide-37
SLIDE 37

37

Overview Current Practices UK Facilities

Research Sites

  • Dounreay
  • Windscale
  • Harwell
  • Winfrith
slide-38
SLIDE 38

38

Overview – Current Practices and Facilities

Spent Fuel Management Facilities

slide-39
SLIDE 39

Magnox Stations

  • Wet storage for at least 90

days - except Wylfa dry storage AGR Stations PWR Station

  • Wet storage for at least

100 days

  • Long term storage in ponds

Storage

Overview Current Practices Spent Fuel

39

slide-40
SLIDE 40

40

Overview Current Practices Spent Fuel

Storage

Sellafield

Storage in various ponds awaiting reprocessing or for long term storage

slide-41
SLIDE 41

41

Sellafield

  • Magnox
  • Thorp

Reprocessing

Overview Current Practices Spent Fuel

slide-42
SLIDE 42

42

Fuel cycle and application waste management

Overview – Current Practices and Facilities

slide-43
SLIDE 43

43

Overview Current Practices Fuel Cycles & Application Wastes

Waste Storage

Magnox Stations

  • Underground vaults
  • Above ground vaults
  • Voids
  • Tanks
  • Voids
  • Wet waste storage tanks
  • Desiccant storage
  • Ion exchange resin

storage tanks AGR and PWR Stations

slide-44
SLIDE 44

44

Overview Current Practices Fuel Cycles & Application Wastes

Waste Storage

  • Engineered Stores
  • Vaults and Silos
  • ILW liquid waste tanks
  • HLW tanks
  • Miscellaneous stores

Application Waste

  • Decay storage in stainless

steel drums Other Fuel Cycle Sites

slide-45
SLIDE 45

45

Overview Current Practices Fuel Cycles & Application Wastes

  • Vitrification
  • Cementation
  • Decontamination
  • Compaction
  • Sorting, segregation

and repacking

Waste Processing

slide-46
SLIDE 46

46

Overview Current Practices Fuel Cycles & Application Wastes

Waste Disposal

Low-level waste repository near Drigg, Cumbria

Low level waste disposal to specific facilities Very low level waste disposal to landfill sites

slide-47
SLIDE 47

47

Overview – Current Practices and Facilities

Decommissioning Liabilities

slide-48
SLIDE 48

48

Overview Current Practices Decommissioning

Magnox Stations

  • Berkeley
  • Bradwell
  • Calder Hall
  • Chapelcross
  • Dungeness A
  • Hinkley Point A
  • Hunterston A
  • Sizewell A
  • Trawsfynydd
slide-49
SLIDE 49

49

Overview Current Practices Decommissioning

Research Sites

Sites being decommissioned

  • Dounreay
  • Windscale
  • Harwell
  • Winfrith
slide-50
SLIDE 50

50

Overview Current Practices Decommissioning

UK Decommissioned Sites

Fully Decommissioned Sites Research Reactors at:

  • Scottish Universities
  • Northern Universities
  • ICI Billingham
slide-51
SLIDE 51

51

Overview Planned Facilities

Planned Facilities

Fuel Cycle Waste under construction for reprocessing waste Decommissioning Liabilities – 5 facilities under construction at three sites Sellafield, Harwell and Dounreay . Others to be constructed as the decommissioning challenge progresses Disused Sealed Sources – future location identified as the Geological Disposal Facility – One additional store is (GDF)

slide-52
SLIDE 52

52

Major Developments since 2006

Dr M Weightman – Nuclear Safety Policy – Organisational – Nuclear Safety Guidance Dr J McHugh – Environmental Policy – Organisational – Environmental Guidance

slide-53
SLIDE 53

53

Major Developments since 2006

Nuclear Safety Policy

White Papers Energy/nuclear power

  • Government confirmed nuclear power option

as part of energy strategy New Build

  • Legislative arrangements to secure financing

arrangements for decommissioning and waste management costs

slide-54
SLIDE 54

54

Major Developments since 2006

Government and Regulator

DECC

  • departmental reorganisations

HSE

  • OCNS and Safeguards joined
  • merger of Executive and Commission
  • change of status of NII – independent

nuclear regulatory body

slide-55
SLIDE 55

55

Licensee restructuring & PBOs

Site(s) Licensee PBO Sellafield, Calder Hall, Windscale, Capenhurst Sellafield Ltd Nuclear Management Partners Ltd (NMP) [from 24/11/2008] Chapelcross, Hunterston A, Trawsfynydd, Wylfa, Oldbury Magnox North Ltd Energy Solutions (to be competed) Berkeley; Bradwell; Dungeness A; Hinkley Point A & Sizewell A Magnox South Ltd Energy Solutions (to be competed) Dounreay Dounreay Site Restoration Ltd UKAEA ltd (to be competed) Harwell, Winfrith Research Sites Restoration Ltd UKAEA ltd (to be competed) LLW repository LLW Repository Ltd UK Nuclear Waste Management Ltd (UKNWM Ltd) [from 1/4/2008] Springfields Springfields fuels Ltd. Westinghouse Electric UK Ltd (to be competed)

Licensees

Major Developments since 2006

slide-56
SLIDE 56

56

Major Developments since 2006

Nuclear Safety Guidance

HSE’s Safety Assessment Principles (SAPs)

  • Revision of the SAPs based on IAEA safety

standards was finalised in 2006 Joint Guidance

  • management of higher-activity wastes on

nuclear licensed sites

slide-57
SLIDE 57

57

Major Developments since 2006

Geological disposal policy, June 2008 Policy covers HLW, ILW and some LLW

MRWS Policy

slide-58
SLIDE 58

58

Major Developments since 2006

MRWS Policy

Policy is based on:

  • geological disposal
  • safe and secure interim storage
  • R&D – optimised implementation

Programme timing is flexible

  • need to maintain momentum

recognised

slide-59
SLIDE 59

59

Major Developments since 2006

Geological Disposal Policy

Site selection process based on partnership with volunteer communities Invitations to local authorities to express an interest in hosting a facility – 3 local authorities expressed interest (April 09)

slide-60
SLIDE 60

60

Major Developments since 2006

Geological Disposal Policy Site Selection Process

Stage 1:

Invitation issued and expression of interest from communities

Stage 4:

Desk-based studies in participating areas

Stage 5:

Surface investigations on remaining candidates

Stage 6:

Underground operations

Stage 3:

Community consideration leading to decision to participate Advise community not suitable

Unsuitable Potentially suitable

Stage 2:

Consistently applied ‘sub- surface unsuitability’ test

slide-61
SLIDE 61

61

Major Developments since 2006

Nuclear Decommissioning Authority (NDA)

NDA Radioactive Waste Management Directorate – set up to deliver a geological disposal facility – incorporates UK Nirex – provides advice on conditioning and packaging of radioactive waste

slide-62
SLIDE 62

62

Major Developments since 2006

Committee on Radioactive Waste Management (CoRWM)

CoRWM has been reconstituted Provides independent scrutiny and advice to UK Government Open and consultative approach

slide-63
SLIDE 63

63

Major Developments since 2006

Low Level Radioactive Waste

Plastic/rubber (13%) Miscellaneous (1%) Cellulose (16%) Metal scrap (30%)

Types of material in LLW inventory

Cement/ concrete (6%) Graphite (1%) Rubble/soil (33%) Plastic/rubber (13%) Miscellaneous (1%) Cellulose (16%) Metal scrap (30%)

Types of material in LLW inventory

Cement/ concrete (6%) Graphite (1%) Rubble/soil (33%)

Low-level radioactive waste (LLW) policy, March 2007 Policy covers generation, management and regulation of solid LLW Policy applies across the UK

slide-64
SLIDE 64

64

Major Developments since 2006

LLW Categories

LLW is defined as not exceeding 4000 MBq/te α

  • r 12000 MBq/te βγ

Two sub-categories recognised:

  • High volume very low level waste (HV-LLW)

Maximum activity of 4 MBq/Te; controlled disposal

  • Low volume very low level waste (LV-

VLLW) Activity <0.4 MBq (or <4 MBq H-3 or C-14) per 0.1m3; safe for disposal with other wastes

slide-65
SLIDE 65

65

Major Developments since 2006

LLW Repository

Low Level Waste Repository (LLWR) at Drigg – principal route for disposal

  • f solid LLW disposal

Revised authorisation in May 2006 – allows disposal in current disposal area to continue

Low Level Waste Repository at Drigg

slide-66
SLIDE 66

66

Major Developments since 2006

LLW Repository

Planning permission for new disposal area granted January 2008 New disposal area will need authorisation

  • Review of site radiological

capacity and disposal limits Updated Environmental Safety Case required by May 2011

Low-level waste repository near Drigg, Cumbria

slide-67
SLIDE 67

67

Major Developments since 2006

Regulatory Guidance

Updated ‘Guidance on Requirements for Authorisation’ published February 2008 for:

  • Near-surface disposal

facilities

  • Geological disposal

Principles and requirements for long-term protection of people and the environment

slide-68
SLIDE 68

68

Draft ‘UK Strategy for Radioactive Discharges 2006-2030’, published June 2008 Includes aerial and liquid discharges from:

  • nuclear industry
  • non-nuclear sector (e.g. hospitals,

universities and research laboratories)

  • decommissioning as well as operational

activities

Radioactive Discharges

Major Developments since 2006

slide-69
SLIDE 69

69

Major Developments since 2006

Radioactive Discharges

Expect progressive reductions in:

  • radioactive discharges
  • concentrations of radionuclides in the marine

environment - by 2020, should add close to zero to historic levels

  • human exposures to ionising radiation

resulting from radioactive discharges

slide-70
SLIDE 70

70

Major Developments since 2006

Environmental Principles

Environment Agency’s draft Radioactive Substances Regulation Environmental Principles’ (REPs) published June 2008 Standardised framework for regulatory decision-making Require operators to apply BAT

slide-71
SLIDE 71

71

Action on Challenges from last Review Meeting

The UK has made, and will continue to make, progress on many of the issues highlighted in the second review meeting Notably -

slide-72
SLIDE 72

72

Action on Challenges

Complete Review of Options for Very Low Level Waste

Completed in March 2007 Priorities:

  • Minimise creation
  • Greater flexibility
  • Maintain focus on safety

etc.

  • create a UK wide strategy
  • NDA tasked with delivery
slide-73
SLIDE 73

73

Action on Challenges

Review the classification system for radioactive waste

UK classification has been modified for VLLW to distinguish low and high volumes

  • Low Volume VLLW:

to an unspecified destination <400kBq (total) and <40kBq (single items)

  • High Volume VLLW

can be disposed of to specified safely disposed of waste <4MBq/te facilities

slide-74
SLIDE 74

74

Action on Challenges

Finalise Contaminated Land Regulations

The Radioactive Contaminated Land Regulations 2006, as amended in 2007, were introduced to put into place certain requirements of the Basic Safety Standards Directive in England and Wales Similar enactments apply in Scotland and Northern Ireland

slide-75
SLIDE 75

75

Contaminated land on nuclear sites regulated under licensing regime Number of non nuclear affected sites is uncertain The person who caused the contamination will be responsible for remediation - if they cannot be found the owner or occupier of the land will be responsible The relevant environment agency will regulate remediation

Identify contaminated land sites requiring remediation

Action on Challenges

slide-76
SLIDE 76

76

Complete review of remaining capacity of the LLW repository near Drigg (3 – 5 years)

Action on Challenges

Work is ongoing Target for completion of national LLW operational strategy is December 2009

slide-77
SLIDE 77

77

NDA has carried out an initial review of spent fuel management as described in UK’s third national report Complete the evaluation of

  • ptions for management of spent

fuel (2007)

Action on Challenges

slide-78
SLIDE 78

78

Current Challenges

slide-79
SLIDE 79

79

Current Challenges

Large amount of decommissioning – e.g.

MAGNOX Reactors

  • Decomm. Progress

Ceased Generation Fuel removed

Bradwell Y Y Calder Hall Y N Chapelcross Y N Dungeness A Y N Hinkley Point A Y Y Hunterston A Y Y Oldbury N N Sizewell A Y N Trawsfynydd Y Y Wylfa N N

slide-80
SLIDE 80

80

Current Challenges

NDA conducting reviews of:

  • Radioactive waste storage
  • Spent fuel management
  • U and Pu disposition

Strategy for all materials

slide-81
SLIDE 81

81

Magnox and Oxide operating plans – Magnox reprocessing until ~2016 – AGR reprocessing until ~2015 AGR fuel storage: – Wet storage for fuel not being reprocessed – Fuel drying and dry storage being evaluated

Spent Fuel Management

Current Challenges

slide-82
SLIDE 82

82

HA Evaporators and Storage Tanks

  • New evaporators /storage tanks being

procured to ensure adequate capacity when the current plant ends its service life

  • Controls are in place to ensure that HAL

arisings do not exceed the capacity of the site to manage them

High Active Liquid Waste

Current Challenges

slide-83
SLIDE 83

83

LLW Disposal Capacity

  • Calder Landfill Extension Segregated Area

– application expected which will more than double the available space

  • Clifton Marsh Disposal Facility

– The future, after 2012, is uncertain - depends operator’s business plans

  • Dounreay LLW disposal facility

– On-site facility for LLW disposal closed in 2005 – a new LLW near-surface facility is planned

Current Challenges

slide-84
SLIDE 84

84

Significant Events since last Review Meeting

slide-85
SLIDE 85

85

– Leakage of ~83,000 litres liquor in 8 months prior to 20 April 2005 – Cat ‘3’ on INES – Cause was motion induced fatigue – Sellafield Ltd prosecuted by HSE and fined by the court – Learning Points

  • Attention needed to maintaining barriers
  • Adequate safety culture is important

THORP Clarification Cell Event

Significant Events

slide-86
SLIDE 86

86

Answers to Questions Received

142 Questions received from 22 Countries Written answers have been provided to all questions

slide-87
SLIDE 87

87

Answers to Questions Received

Cannot present all questions and answers Key themes in questions presented (where not covered elsewhere in the presentation)

slide-88
SLIDE 88

88

How does the UK maintain consistency across devolved administrations? – Devolved administrations in Scotland, Wales (and Northern Ireland) – UK Parliament responsible for legislation on Health and Safety and on Nuclear Safety – Scotland and Wales have powers over environmental matters

  • Policy can be different

Regulatory Control

Answers to Questions

slide-89
SLIDE 89

89

Staged regulation of geological disposal

  • UK Government planning to implement under

Environmental Permitting Regulations (EPR)

  • EPR will replace Radioactive Substances Act

1993 in England and Wales – New powers for regulation of geological disposal from start of intrusive site investigation – EPR will not apply in Scotland but existing regulatory control will continue to apply

Regulatory Control

Answers to Questions

slide-90
SLIDE 90

90

Radioactive Substances Regulation Environmental Principles (REPS)

  • Take account of legislation and Government

policy

  • Framework for technical assessments and

judgements – Complementary to HSE’s Safety Assessment Principles

  • REPs revised to reflect consultation comments
  • publish later in 2009

Regulatory Control

Answers to Questions

slide-91
SLIDE 91

91

Licence and Authorisation Conditions to govern nuclear sites

  • Licence and Authorisation Conditions have

legal status - non-compliance is a criminal

  • ffence
  • Effect similar to regulations
  • Benefit: easier to change Conditions than

regulations – can react to changing needs without amending legislation

Regulatory Control

Answers to Questions

slide-92
SLIDE 92

92

Answers to Questions

Low Level Waste Disposal

Capacity

  • National LLW strategy being implemented

– includes planning for future capacity

  • LLW Repository: potential capacity to 2020

– capacity under review

  • Dounreay: new disposal facility planned

– on-site disposal ceased in 2005

  • VLLW – policy allows more disposal options

– disposal of high volume VLLW to specified landfills

slide-93
SLIDE 93

93

Waste acceptance criteria

  • Responsibility of disposal facility operator
  • Regulatory control through authorisations of

waste producers and disposal facility operator

  • Disposal of VLLW – control through waste

producers’ authorisations – Authorisation required for specialised VLLW disposal facility

Low Level Waste Disposal

Answers to Questions

slide-94
SLIDE 94

94

Institutional control

  • 2002 safety case for LLW Repository – put no

reliance on institutional control beyond 2150 – ~100 years after expected closure

  • No parameters for deciding when to withdraw

control specified in regulatory guidance – Reasonable arrangements must be in place to fund closure – Unlikely to accept period longer than ~ 300 years

Low Level Waste Disposal

Answers to Questions

slide-95
SLIDE 95

95

Answers to Questions

UK Discharge Strategy

2000 2001 2002 2003 2004 2005 2006 2007 0.5 1.0 1.5 2.0 2.5 Weighted discharges relative to 2000

Water Air Water Air

  • Data for nuclear industry in England and Wales
slide-96
SLIDE 96

Beach Monitoring

Answers to Questions

Dounreay Sand grain sized particles of irradiated fuel released with liquid effluent from 1963 to 1984 Sellafield Over 600 finds recovered from 4.4 km2 (April ’09) – Two groups: α-rich (Pu, Am) and β-rich (Cs- 137)

Monitoring vehicle

96

slide-97
SLIDE 97

97

Answers to Questions

Disused Radioactive Sources

‘Surplus Source Disposal Programme’

Hospital University Museums Orphan Others Schools & colleges

Number of sources by institution

500 1000 1500 2000 2500 3000 3500 Number of sources Hospital University Museums Orphan Others Schools & colleges

Number of sources by institution

500 1000 1500 2000 2500 3000 3500 Hospital University Museums Orphan Others Schools & colleges

Number of sources by institution

500 1000 1500 2000 2500 3000 3500 Number of sources

Purpose: Removal to secure long-term storage, recycling or disposal sites Duration: 2004-2008 Cost: £7.14M (~ US $10.4M) – UK Government Over 11,000 sources removed – Total activity >850 TBq

slide-98
SLIDE 98

98

The Plant Safety Review process -

  • At all times safety must be substantiated and

documented (Safety Case)

  • major reviews of safety
  • normally carried out every ten years
  • identify shortfalls against modern standards
  • leads to a programme of reasonably

practicable improvements HSE assesses on a sample basis

Regulators

Answers to Questions

slide-99
SLIDE 99

99

How are stakeholders views taken on board? Examples

  • The planning application process
  • Site Stakeholder Groups (SSGs)
  • National Stakeholder Group (NSG)
  • Community Siting Partnership for geological

disposal

Stakeholders

Answers to Questions

slide-100
SLIDE 100

100

National Skills Academy for Nuclear (NSAN)

  • training to foundation degree level and

apprenticeships

  • HSE is a member of NSAN as an employer -

no legal responsibility National Nuclear Laboratory (NNL)

  • identify and preserve key nuclear skills and

facilities

  • lead UK's strategic technology programmes

Skills

Answers to Questions

slide-101
SLIDE 101

101

Ageing Profile in HSE/NII

  • 70% over 50 (8%>60) - experienced regulatory

inspectors

  • challenges and opportunities include:

– Knowledge Retention and Transfer – Leadership and Management Gaps

  • need:

– targeted recruitment activities – measures to enhance retention HSE’s Nuclear Directorate moving to “Statutory Corporation” status – more flexibility to address these issues

Skills

Answers to Questions

slide-102
SLIDE 102

102

Siting rules for radioactive waste management facilities vs. new reactors – 2008 HSE demographics methodology for all types of nuclear facilities – based on UK long standing nuclear siting policies updated to reflect international good practice

Siting

Answers to Questions

slide-103
SLIDE 103

103

Spent Fuel from new reactors

  • Planning assumption - spent fuel stored until

a disposal route becomes available

  • Requesting Parties commissioned work to

assess the 'disposability' of spent fuel

  • Disposability assessments are not complete -

no indication that the new reactor fuel will raise unique disposability issues

Spent Fuels

Answers to Questions

slide-104
SLIDE 104

104

‘Exotic’ Spent Fuel

  • NDA is developing disposition options for its

non-standard fuels, commonly referred to as ‘Exotics’

  • Storage regime dependent on

– the physical properties of the fuel – length of storage period required

Spent Fuels

Answers to Questions

slide-105
SLIDE 105

105

Planned measures to improve safety

Planned measures to improve safety

slide-106
SLIDE 106

106

Planned measures to improve safety

Environmental Improvements

  • UK discharge strategy
  • Environmental Permitting
slide-107
SLIDE 107

107

Planned measures to improve safety

Safety Improvements

  • Progress in decommissioning
  • Focus on high hazard plants
slide-108
SLIDE 108

108

Planned measures to improve safety

Institutional Improvements

  • Institutional changes to facilitate improvements
slide-109
SLIDE 109

109

Summary

The UK has made, and will continue to make, progress on many of the issues highlighted in the second Review Meeting, notably :

slide-110
SLIDE 110

110

Summary

Review of Policy

  • geological disposal plus safe and secure

storage Organisational changes

  • Nirex integrated into NDA – to progress GDF
  • NDA restructured its estate and early PBO

contracts awarded

  • Nuclear Skills Academy established
slide-111
SLIDE 111

111

Summary

Progress in Decommissioning Successful progress in: – safe shutdown, defuelling and decommissioning of Magnox Power Reactor fleet – decommissioning of research sites – decommissioning legacy plant at Sellafield

slide-112
SLIDE 112

Summary

Progress in Radioactive Waste Management Successful progress in: – reducing liquid HLW stocks through vitrification – repackaging PCM to modern standards – treating active sodium from PFR

112

slide-113
SLIDE 113

113

Summary

Learning from the past to better address today’s issues and address future challenges

slide-114
SLIDE 114

114

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management

The United Kingdom of Great Britain and Northern Ireland NATIONAL REPORT PRESENTATION for the Third Review Meeting 11th to 20th May 2009 Vienna