johnson street bridge replacement project quarterly update
play

Johnson Street Bridge Replacement Project Quarterly Update - PowerPoint PPT Presentation

Johnson Street Bridge Replacement Project Quarterly Update Governance and Priorities Committee March 21 2013 Progress Update Project remains within the approved budget Several risks have been reduced or eliminated with the award of


  1. Johnson Street Bridge Replacement Project Quarterly Update Governance and Priorities Committee March 21 2013

  2. Progress Update • Project remains within the approved budget • Several risks have been reduced or eliminated with the award of the fixed-price contract • Value engineering process to further identify opportunities for costs savings continues

  3. Progress Update • Construction to begin in mid-April with visible work starting in June • PCL is currently advertising for trades people • Public information sessions planned for late April as well as ongoing communication activities through to project completion

  4. Construction Schedule June 2013

  5. Construction Schedule July 2013

  6. Construction Schedule August 2013

  7. Construction Schedule February 2014

  8. Construction Schedule October 2014

  9. Communication and Stakeholder Consultation

  10. Engagement Principles • Keep the public informed through clear, accessible, timely communication • Consult and involve stakeholders most affected by the project • Use tools and methods to reach people “where they are” • Be an Engaged Neighbour • Close the loop

  11. Upcoming Communications Activities • Internal coordination to anticipate and avoid duplication • New print and web materials • Information session(s) to outline construction schedule and impacts • Establish routine meetings with most affected • Proactive media approach • Identify opportunities for community to learn from historic project • Outreach to over 100 diverse stakeholders • Project kickoff event

  12. Recommendation That Council receive this update as information and approve the amendments to the Johnson Street Bridge Project Charter.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend