Johnson Street Bridge Replacement Project Quarterly Update Governance and Priorities Committee March 21 2013 Progress Update Project remains within the approved budget Several risks have been reduced or eliminated with the award of


slide-1
SLIDE 1

Johnson Street Bridge Replacement Project Quarterly Update

Governance and Priorities Committee March 21 2013

slide-2
SLIDE 2

Progress Update

  • Project remains within the approved budget
  • Several risks have been reduced or eliminated

with the award of the fixed-price contract

  • Value engineering process to further identify
  • pportunities for costs savings continues
slide-3
SLIDE 3

Progress Update

  • Construction to begin in mid-April with visible

work starting in June

  • PCL is currently advertising for trades people
  • Public information sessions planned for late April

as well as ongoing communication activities through to project completion

slide-4
SLIDE 4

Construction Schedule

June 2013

slide-5
SLIDE 5

Construction Schedule

July 2013

slide-6
SLIDE 6

Construction Schedule

August 2013

slide-7
SLIDE 7

Construction Schedule

February 2014

slide-8
SLIDE 8

Construction Schedule

October 2014

slide-9
SLIDE 9
slide-10
SLIDE 10

Communication and Stakeholder Consultation

slide-11
SLIDE 11

Engagement Principles

  • Keep the public informed through clear, accessible,

timely communication

  • Consult and involve stakeholders most affected by the

project

  • Use tools and methods to reach people “where they are”
  • Be an Engaged Neighbour
  • Close the loop
slide-12
SLIDE 12

Upcoming Communications Activities

  • Internal coordination to anticipate and avoid duplication
  • New print and web materials
  • Information session(s) to outline construction schedule

and impacts

  • Establish routine meetings with most affected
  • Proactive media approach
  • Identify opportunities for community to learn from historic

project

  • Outreach to over 100 diverse stakeholders
  • Project kickoff event
slide-13
SLIDE 13

Recommendation

That Council receive this update as information and approve the amendments to the Johnson Street Bridge Project Charter.