johnson street bridge replacement project
play

Johnson Street Bridge Replacement Project Quarterly Update - PowerPoint PPT Presentation

Johnson Street Bridge Replacement Project Quarterly Update Governance and Priorities Committee Meeting September 26 2013 Progress Update Project remains within the approved budget Planning Risk: Loss of schedule float (additional


  1. Johnson Street Bridge Replacement Project Quarterly Update Governance and Priorities Committee Meeting September 26 2013

  2. Progress Update • Project remains within the approved budget • Planning Risk: Loss of schedule float (additional time allowed for unforeseen events) has been eliminated • Recent construction activity includes site clearing and construction of temporary work platforms for crews and equipment for building the new bridge • Construction is on schedule

  3. Budget • Project remains within $92.8 million budget • Value Engineering opportunities remain at $775,000

  4. Value Engineering Value engineering continues for: • East Abutment ($150,000) • Rest Pier ($125,000) • Lighting ($500,000) • Value engineering is expected to be complete in October 2013 with potential for further savings of up to $775,000, reducing contract price and increasing the construction contingency

  5. Upcoming Construction Activity • continued installation of the bascule pier piles from now until February 2014 • installation of the cofferdam and start of construction of the west abutment • installation of the rest pier piles in the west side of the harbour • fabrication of the bascule span

  6. Utility Replacement • Work to upgrade century-old water, sewer, and stormwater pipes is currently underway near the bridge • These utilities are being replaced in advance of new road alignments that will be built for the new bridge • Crews are working downtown until November 2013 • Work will continue on the west side of the bridge along Esquimalt Rd in November with completion expected in December 2013

  7. Recent Engagement Activities • Staff attended Chinatown Night Market in July and September • Ongoing correspondence with Victoria West and Downtown neighbourhood associations, as well as Mermaid Wharf and Dockside Green buildings • Regular updates and correspondence with neighbouring hotels and business groups • Message that bridge will remain open through construction remains important

  8. Recent Engagement Activities • Project eNews currently has 600 subscribers with an average of 30 new subscribers each month • More than 4,100 unique visitors to JohnsonStreetBridge.com from June to August • Following completion of design as approved by Council in December 2012, new renderings of the bridge will be added to the project website

  9. Public Art • City’s staff will oversee the process and will be guided by the City’s Art in Public Places Policy • Artist may use a piece of steel from the rail bridge • Nation-wide call with a three stage jury selection process • Call for Expression of Interest to begin week of September 30

  10. Public Art • In March 2012, Council adjusted project budget to $92.8 million. At the time, the Project Definition Report anticipated a public art budget of $350,000 • The City’s Public Art Advisory committee is supportive of a public art budget of $250,000 • A public art budget of $250,000 will be the largest in the City’s history and more than sufficient to produce a substantial piece

  11. New Public Green Space Known conditions that will guide development of s-curve lands: � Official Community Plan identifies area as a proposed park and preserves rail corridor through the area � Downtown Core Area Plan identifies as a waterfront lookout � Council direction in Oct 2011 was to retain land as green space � Pedestrian connections constructed as part of the bridge project � Road access from Esquimalt Rd to Delta Hotel that will be built as part of the bridge project

  12. New Public Green Space Known conditions that will guide development of s-curve lands, continued: � new plaza area constructed on the south-west side of the bridge � Maintaining a max grade of 3:1 to increase programming possibilities and allow a reduction in maintenance costs � Ownership of adjacent properties � History of area as a First Nations village site � Public input received to date through previous Johnson Street Bridge engagement activities in 2012

  13. New Public Green Space Unknown conditions which will also impact the future use space: � Soil conditions which may restrict some uses of the space � Archeological assessment � Future uses of adjacent properties � Future uses of the adjacent water lot • Staff expect more information in the coming months and will develop an engagement strategy to be brought to Council in November • Engagement activities are anticipated to begin in December or early 2014

  14. Recommendation • That Council approve a Public Art budget of $250,000 • That Council receive this report as information

  15. Thank You

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend