improvements project
play

Improvements Project Hopkinton-Westborough- Southborough December, - PowerPoint PPT Presentation

I-90 / I-495 Interchange Improvements Project Hopkinton-Westborough- Southborough December, 2014 Introduction / Welcome Paul Matthews, Executive Director, 495 MetroWest Partnership Renata Welch, MassDOT Project Manager Jonathan


  1. I-90 / I-495 Interchange Improvements Project Hopkinton-Westborough- Southborough December, 2014

  2. Introduction / Welcome • Paul Matthews, Executive Director, 495 MetroWest Partnership • Renata Welch, MassDOT Project Manager • Jonathan Gulliver, MassDOT District Highway Director

  3. Background • Historic congestion at interchange associated with toll plaza • MassDOT planning study (2012-2013) identified deficiencies and need for improvements • Implementation of All Electronic Toll System (AETS) July 15, 2016 • Subsequent elimination of toll plaza will not eliminate congestion and safety issues

  4. Project Area

  5. Immediate Study Area

  6. 2035 Design Volumes • Based upon 2035 Priority Development Areas scenario • Weekday AM and PM peak hours

  7. Previous Concept from Planning Study

  8. Background Safety and Operational Issues • Substandard geometry • Magnitude of passenger vehicle traffic • Magnitude of truck traffic • Vehicle conflicts (weaving sections) within interchange area

  9. Advocacy

  10. Advocacy

  11. Advocacy

  12. Advocacy

  13. Project Goals What Are We Trying to Do • Eliminate Weaving Movement Conflicts • Improve Interstate-to-Interstate Design • Reduce Congestion and Travel Time • Minimize Resource Impacts

  14. Existing Conditions

  15. Environmental Concerns

  16. Environmental Concerns

  17. Environmental Concerns

  18. Environmental Concerns

  19. Environmental Concerns

  20. Concept Development • MassDOT internal working group started with a blank slate to envision new interchange configurations • New interchange configurations were then modified while still maintaining appropriate design speeds and geometry • All design standards are met • New ramp designs to provide direct connections and eliminate weaves

  21. Concept Development DIRECTIONAL (60MPH)

  22. Concept Development FULL CLOVERLEAF

  23. Screening Categories and Considerations Design/Operations Environmental Socioeconomic • Eliminate weaves • Wetlands • Noise / distance from residences • Direct connections • Flood zone • Neighborhood • Ramp geometry • Habitat impacts • Reduce congestion • ACEC • Visual impacts • Stormwater BMPs • Open space • Environmental justice • Riverfront area Cost/Construction • ROW impacts • Historic / • Construction cost Regulatory Archaeological • Mitigation cost • Hazardous materials • Meets Purpose & • Bridge maintenance • Air quality Need • Phasing • Permit requirements • Water quality • Maintaining traffic • Mitigation needs

  24. Concept Development Initial Screening • Concept 22-3 30+ Variations of Eight Initial • Concept 14-5 Initial Concepts Concepts • Concept 14-4

  25. Concept 22-3 Existing Ramp to Remain (with Modifications)

  26. Concept 22-3

  27. Concept 14-5 Existing Ramps to Remain (with Modifications) Existing Ramp to Remain (with Modifications)

  28. Concept 14-5

  29. Concept 14-4 Existing Ramps to Remain (with Modifications) Existing Ramps to Remain (with Modifications) Existing Ramp to Remain (with Modifications)

  30. Concept 14-4

  31. Preliminary Traffic Modeling • Based upon 2035 Priority Development Areas scenario • Baseline (No Build) represents conditions with toll plazas removed • Weekday AM and PM peak hours analyzed • All three concepts provide acceptable operations and address weaving and congestion concerns

  32. Future PM Peak Hour Conditions (2035) – No Build Insert video clip 2035 No Build PM

  33. Future PM Peak Hour Conditions (2035) – Concept 14-4

  34. 2035 Operational Benefits

  35. Resource Impacts

  36. Conceptual Cost Estimates • Concept 22-3 $285,400,000* • Concept 14-5 $215,800,000* • Concept 14-4 $162,000,000* note: does not include engineering, mitigation or ROW costs * 2014 Dollars

  37. Programming • Project has historically been included in Central Mass MPO / CMRPC Long Range Transportation Plan (LRTP) but not fully funded • Project has been included by reference in Boston MPO LRTP • Need to continue efforts to include in both plans and eventual Transportation Improvement Program (TIP) • Funding expected to include Western Turnpike funds

  38. Outreach • November 18 th – initial discussion with FHWA environmental and programming staff • December 2 nd – initial discussion with State and Federal environmental agencies • December 18 th – initial discussion with 495 MetroWest Partnership, local and regional officials and stakeholders

  39. Overall Project Schedule 1 Planning Study 2 Feasibility Study/ Conceptual Design 3 EA / EIR / 25% Design 4 Final Design and Permitting 5 Early Action Construction 6 Construction Complete Current Stage

  40. Next Steps • Continue to refine concepts and impact calculations • Prepare ENF for Winter 2015 filing • Work with MPOs (Boston, Central Mass) to include project in Long Range Plans • Procure consultant services for environmental documentation / 25% / permitting • Prepare Environmental Assessment / Environmental Impact Report for NEPA and MEPA and obtain permits • Design and Construction

  41. QUESTIONS AND COMMENTS

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend