Improvements Project Hopkinton-Westborough- Southborough December, - - PowerPoint PPT Presentation
Improvements Project Hopkinton-Westborough- Southborough December, - - PowerPoint PPT Presentation
I-90 / I-495 Interchange Improvements Project Hopkinton-Westborough- Southborough December, 2014 Introduction / Welcome Paul Matthews, Executive Director, 495 MetroWest Partnership Renata Welch, MassDOT Project Manager Jonathan
- Paul Matthews, Executive Director, 495 MetroWest
Partnership
- Renata Welch, MassDOT Project Manager
- Jonathan Gulliver, MassDOT District Highway Director
Introduction / Welcome
- Historic congestion at interchange associated with toll
plaza
- MassDOT planning study (2012-2013) identified
deficiencies and need for improvements
- Implementation of All Electronic Toll System (AETS)
July 15, 2016
- Subsequent elimination of toll plaza will not eliminate
congestion and safety issues Background
Project Area
Immediate Study Area
- Based upon 2035 Priority
Development Areas scenario
- Weekday AM and PM peak
hours
2035 Design Volumes
Previous Concept from Planning Study
Safety and Operational Issues
- Substandard geometry
- Magnitude of passenger vehicle traffic
- Magnitude of truck traffic
- Vehicle conflicts (weaving sections) within interchange
area Background
Advocacy
Advocacy
Advocacy
Advocacy
What Are We Trying to Do
- Eliminate Weaving Movement Conflicts
- Improve Interstate-to-Interstate Design
- Reduce Congestion and Travel Time
- Minimize Resource Impacts
Project Goals
Existing Conditions
Environmental Concerns
Environmental Concerns
Environmental Concerns
Environmental Concerns
Environmental Concerns
- MassDOT internal working group started with a blank
slate to envision new interchange configurations
- New interchange configurations were then modified
while still maintaining appropriate design speeds and geometry
- All design standards are met
- New ramp designs to provide direct connections and
eliminate weaves
Concept Development
DIRECTIONAL (60MPH)
Concept Development
FULL CLOVERLEAF
Concept Development
Design/Operations
- Eliminate weaves
- Direct connections
- Ramp geometry
- Reduce congestion
- Stormwater BMPs
Cost/Construction
- Construction cost
- Mitigation cost
- Bridge maintenance
- Phasing
- Maintaining traffic
Environmental
- Wetlands
- Flood zone
- Habitat
- ACEC
- Open space
- Riverfront area
- Historic /
Archaeological
- Hazardous materials
- Air quality
- Water quality
Socioeconomic
- Noise / distance
from residences
- Neighborhood
impacts
- Visual impacts
- Environmental justice
- ROW impacts
Regulatory
- Meets Purpose &
Need
- Permit requirements
- Mitigation needs
Screening Categories and Considerations
Initial Screening
Concept Development
- Concept 22-3
- Concept 14-5
- Concept 14-4
Eight Initial Concepts 30+ Variations of Initial Concepts
Concept 22-3
Existing Ramp to Remain (with Modifications)
Concept 22-3
Concept 14-5
Existing Ramps to Remain (with Modifications) Existing Ramp to Remain (with Modifications)
Concept 14-5
Concept 14-4
Existing Ramps to Remain (with Modifications) Existing Ramp to Remain (with Modifications) Existing Ramps to Remain (with Modifications)
Concept 14-4
- Based upon 2035 Priority
Development Areas scenario
- Baseline (No Build)
represents conditions with toll plazas removed
- Weekday AM and PM peak
hours analyzed
- All three concepts provide
acceptable operations and address weaving and congestion concerns
Preliminary Traffic Modeling
Insert video clip 2035 No Build PM
Future PM Peak Hour Conditions (2035) –No Build
Future PM Peak Hour Conditions (2035) – Concept 14-4
2035 Operational Benefits
Resource Impacts
- Concept 22-3 $285,400,000*
- Concept 14-5 $215,800,000*
- Concept 14-4 $162,000,000*
note: does not include engineering, mitigation or ROW costs
* 2014 Dollars
Conceptual Cost Estimates
- Project has historically been included in Central Mass
MPO / CMRPC Long Range Transportation Plan (LRTP) but not fully funded
- Project has been included by reference in Boston MPO
LRTP
- Need to continue efforts to include in both plans and
eventual Transportation Improvement Program (TIP)
- Funding expected to include Western Turnpike funds
Programming
- November 18th – initial discussion with FHWA
environmental and programming staff
- December 2nd – initial discussion with State and
Federal environmental agencies
- December 18th – initial discussion with 495 MetroWest
Partnership, local and regional officials and stakeholders
Outreach
Overall Project Schedule
1 2 3 4 5 6
Planning Study Feasibility Study/ Conceptual Design EA / EIR / 25% Design Final Design and Permitting Early Action Construction Construction Complete
Current Stage
Next Steps
- Continue to refine concepts and impact calculations
- Prepare ENF for Winter 2015 filing
- Work with MPOs (Boston, Central Mass) to include
project in Long Range Plans
- Procure consultant services for environmental
documentation / 25% / permitting
- Prepare Environmental Assessment / Environmental
Impact Report for NEPA and MEPA and obtain permits
- Design and Construction