Early Improvements Update 15 May 2018 Project Process 2 Candidate - - PowerPoint PPT Presentation
Early Improvements Update 15 May 2018 Project Process 2 Candidate - - PowerPoint PPT Presentation
Early Improvements Update 15 May 2018 Project Process 2 Candidate Early Improvements 107 interventions Considered to the stage where sufficient willingness and resource will enable delivery within three years Most still require
2
Project Process
3
Candidate Early Improvements
- 107 interventions
- Considered to the stage where sufficient willingness and
resource will enable delivery within three years
- Most still require definition, investigation and assessment
- Prioritised into 15 mostly geographic packages
- Identified potential candidates for showcase and trial
- Current estimate of cost is
- $M 40 – 60 capex (including 20 – 30 of cycling)
- $M 10 – 17 opex
4
Implementation Planning
107 interventions – if delivered under BAU
- WCC – 75
- NZTA – 31
- GWRC – 1
Legal advice confirms that WCC traffic resolution decisions cannot be delegated
- Any changes to parking or traffic restrictions on WCC roads
Therefore the delivery mechanism needs some thinking
5
Prioritisation
- Setting safer speeds first to prioritise safety
- Benefits realisation – seeking biggest benefit returns first
- Only a matter of months between different packages starting,
intention is to deliver as many as possible early in the programme
- Showcase and trial opportunities identified
6
Prioritisation
Package Description
Liveability Access Multimodal Safety Resilience
Prioritisation - weave these points into a story, it's only a matter of months between them and there's a bold desire to do it all Showcase Trial Setting Safer Speeds Reducing speed limits on selected roads in the CBD and sections of SH1 east of Mt Vic
2
- 1
1 3 5
Potential to significantly improve safety across the network Featherston St Corridor length improvements to walking and cycling priority, and provision of cycling facilities on Whitmore
2 1 2 1 6
Showcase project with good multi-modal benefits, and the potential to improve the last mile pedestrian trip from rail Golden Mile Bus priority enhancements, minor safety improvements, and trial restriction of general traffic on sections of northern Willis Street and Courtenay Place
2 1 2 1 6
Network wide PT benefits as a pre-cursor to lane drop on the Quays Basin Reserve Package of relatively low cost minor at-grade improvements to improve efficienct access
3 1 1 5
Improving a critical conflict point Hutt Road Public transport and cycling priority along the corridor with integrated pedestrian improvements
1 1 1 2 5
Improve PT and cycle trips from the north, begin to discourage private vehicle use as a pre-cursor to lane drop Isolated Minor Improvements Traffic signal and intersection enhancements, pedestrian crossing improvments and shelter and wayfinding enhancements, lengthening nine bus stops to meet minimum standard, further use of technology to improve management of on-street parking
1 1 1 1 1 5
Progress minor individual projects as possible Operational Improvements Improved signal operations, applying MaaS platform to Wellington context, improved incident management, enhancing existing TDM programmes
2 1 2 5
Progress minor individual projects as possible Willis/Victoria Corridor length improvements to walking and cycling priority
1 1 2 1 5
Large PT LoS gap, but not currently high numbers of buses
- r cyclists
Karo / Vivian Restrict parking on Vivian Street and minor efficiency improvements
2 1 1 4
Dixon Street Implementing cycling connections and pedestrian improvements
1 2 1 4
SH1 East of Mt Vic Pedestrian and cycle crossing signals on Cobham Drive, bus priority and minor intersection safety improvements (dependency with setting safer speeds)
1 1 2 4
Taranaki St Trial cycling and bus priority improvements in advance of final corridor form
1 1 1 1 4
Newtown Review bus lane priorities
1 2 3
The Terrace Pedestrian priority and crossing enhancements, Bowen Street bus lanes/clearways
1
- 1
2 1 3
Motorway Corridor Minor efficiency and safety improvements
1 1 2
Investment Objectives Sub-Total
7
Package Maps
DRAFT proposals for Setting Safer Speeds
Speed Limit Review
Liveability Access Multimodal Safety Resilience Capex 0.4-0.6 Opex 0.4-0.6
2
- 1
1 3
DRAFT proposals for Featherston Street
Optimise signals to favour pedestrians (consider LED strip lighting trial) Safety Improvements Add pedestrian crossing Provide Cycling Facility Widen footpath
Liveability Access Multimodal Safety Resilience Capex 2.5-4.1 Opex 0.3-0.6
2 1 2 1
DRAFT proposals for Golden Mile
Safety Improvements Remove Bus Stop PT Priority Upgrades Trial removal/ restriction of General Traffic Add pedestrian crossings/crosswalks Provide Cycling Facility Improved Laneway Second cycle minor phases Convert angle parking to parallel Pedestrian countdown timers
Liveability Access Multimodal Safety Resilience Capex 4.7-7.8 Opex 1.4-2.6
2 1 2 1
Potential shared space
DRAFT proposals for Basin Reserve
Close/restrict Ellice Street Remove/restrict parking Widen footpath At-grade access improvements Remove parking Southbound bus lane
Liveability Access Multimodal Safety Resilience Capex 5.8-9.3 Opex 0.5-0.9
3 1 1
DRAFT proposals for Hutt Road
Improved crossing
- pportunities
Improved Public Transport priority/HOV
Liveability Access Multimodal Safety Resilience Capex 2.2-3.5 Opex 0.2-0.4
1 1 1 2
Trial Cycling Facility Signalise pedestrian crossing
DRAFT proposals for Willis / Victoria
Provide Cycling Facility Improved Laneway Improved bus priority
Liveability Access Multimodal Safety Resilience Capex 1.5-2.4 Opex 0.3-0.5
1 1 2 1
Remove Parking
DRAFT proposals for Karo / Vivian
Restrict parking Restrict turns Optimise signals (queue conflict and PT delay) Second cycle right turn Remove Parking Second cycle Abel Smith (west) Second cycle right turn Second cycle Pirie Street
Liveability Access Multimodal Safety Resilience Capex 0.7-1.2 Opex 0.2-0.4
2 1 1
Change lane designations
DRAFT proposals for Dixon
Liveability Access Multimodal Safety Resilience Capex 1.5-2.5 Opex 0.1-0.2
1 2 1
Pedestrian Connection Provide Cycling Facility
DRAFT proposals for SH1 East of Mt Vic
Safety Improvements Add pedestrian and cycle crossing Pedestrian crossing
- pportunities
PT priority
Liveability Access Multimodal Safety Resilience Capex 4.8-7.7 Opex 0.4-0.8
1 1 2
DRAFT proposals for Taranaki Street
Trial cycling facility Add pedestrian crossings/ signalise zebra
Liveability Access Multimodal Safety Resilience Capex 3.4-5.5 Opex 0.3-0.5
1 1 1 1
PT priority improvements
DRAFT proposals for Newtown
Review bus lane times/ PT priority
Liveability Access Multimodal Safety Resilience Capex 0.1-0.5 Opex 0.0-0.0
1 2
DRAFT proposals for The Terrace
Improved right turn into Museum Street Improve pedestrian crossing
- pportunities
Improved pedestrian route Review clearway times/ PT priority
Liveability Access Multimodal Safety Resilience Capex 1.6-2.7 Opex 0.8-1.5
1
- 1
2 1
DRAFT proposals for Motorway Corridor
Increase off-ramp stacking capacity and optimise intersection Safety Improvements Test lane lights
Liveability Access Multimodal Safety Resilience Capex 1.8-3.0 Opex 0.3-0.6
1 1
Active queue warning sign
21
- Pedestrian wayfinding
- Additional countdown timers (traffic signals)
- Pedestrian sensors (traffic signals)
- Additional smart parking infrastructure
- Loading zone parking sensors
- Pedestrian shelter
- Widened footpaths (minor only)
- Airport travel choice VMS
- Additional CCTV for traffic operations monitoring
- Lengthen nine bus stops to minimum standard on 2018 core
routes
- Improved pedestrian lighting
- Cycle rumble strips on harbourside walkway
- Double right turn out of Hinemoa onto Waterloo Quay
- Remove two single car parks that affect intersection
capacity Tinakori Road
- Trial half cycle minor phases at traffic signals during peak
- peration
- Signalise zebra crossing on Tinakori Road
- Rationalise bus stops near Kilbirnie Aquatic Centre
- Improve pedestrian crossing on Molesworth near
Hawkestone
- Improve pedestrian crossing on Mulgrave at Thorndon Quay
Operational Improvements and Isolated Minor Improvements
- Improved Incident Response
- Applying MaaS platform to Wellington context
- Increased workplace and School travel planning
- Further encourage e-bike uptake
- Increase resource for operations