SLIDE 1
I/I Reduction Planning In a Well Established Elgin Neighborhood - - PowerPoint PPT Presentation
I/I Reduction Planning In a Well Established Elgin Neighborhood - - PowerPoint PPT Presentation
I/I Reduction Planning In a Well Established Elgin Neighborhood Presented By: Colby J. Basham Public Works Utility Superintendent City of Elgin Jeffrey W. Freeman, P.E., CFM, LEED AP Vice President Engineering Enterprises, Inc. March 19,
SLIDE 2
SLIDE 3
Background Information
Study Area
SLIDE 4
Study Area Overview
- N. Commonwealth
& Murray Reference Point
SLIDE 5
Study Area Overview
SLIDE 6
Study Area Overview
SLIDE 7
Study Area Overview
City Has Invested Time & Money In The Storm & Sanitary Sewer Infrastructure Within This Area In the Past City Lined Sanitary Sewer Mainlines Within Area Several Years Ago City Conducted A Similar Study In 1998 Within This Area; Recommendations:
Line Storm Sewers To Prevent Exfiltration Repair Identified Inflow Sources Sanitary Sewer Hydraulic Improvements
July 24, 2010 Storm Event & McClure & Wilder Storm Manhole Failure August 2010 Neighborhood Meeting
SLIDE 8
Study Initiation
Information Gathering Work Items: Neighborhood Kick-Off Meeting On 1/19/11 Land Surveying & Manhole Assessments Within Basins 1 – 4 Resident Survey Distribution & Collation
SLIDE 9
Study Initiation
SLIDE 10
Study Initiation
SLIDE 11
Flow Monitoring
Flow Monitoring Overview: Flow & Rainfall Monitoring From April 5, 2011 – May 17, 2011 Total of 6.56 Inches of Rain During Monitoring Period; Two Storms In Excess of 0.75 inches
April 19: 1.10 Inches In 13 Hours (2-Month Recurrence Interval Storm) May 11: 1.49 Inches In 2 Hours (1-Year Recurrence Interval Storm)
SLIDE 12
Flow Monitoring
Basin I&I Summary: Basins With Excessive Continuous Infiltration: 2 Basins With Excessive Inflow & Rain-Induced Infiltration (RII): 2, 1, 3; 4 & 5 (Marginal)
SLIDE 13
SSES Fieldwork
SSES Field Work Items: Smoke Testing Summary Within Basins 1, 2 & 3 Sanitary Sewer Televising Within Basins No. 2 & 3 Dye Water Flooding At Five Intersections
SLIDE 14
SSES Fieldwork
Boring Locations
Estimated Drummer Soil Limits
SLIDE 15
SSES Fieldwork
Boring Logs
SLIDE 16
SSES Fieldwork
SLIDE 17
Storm & Sanitary Sewer Models
Storm Sewer Model Setup Computer Modeled Storm Sewer Network Within StormCAD Evaluated Existing Conveyance Capacity Under 2-Year, 5-Year & 10-Year Recurrence Interval Storms
SLIDE 18
Storm & Sanitary Sewer Models
Sanitary Sewer Model Setup Computer Modeled Sanitary Sewer Network Within SewerCAD Evaluated Existing Baseline Domestic Waste Conveyance Capacity All Sewers @ Less Than Or Equal To 22% Capacity Verified Model Replicates Field Measured Dry Weather Flow Conditions Verified Model Replicates Field Measured Wet Weather Flow Conditions Utilized Model to Analyze Existing Conditions & Rehabilitation Alternatives Under 1-Year, 2-Year, 10-Year & 25-Year Recurrence Interval Storms
SLIDE 19
Rehabilitation Analysis
Rehabilitation That Should Proceed No Matter What: Reroute Water Main Around Manhole 1130 Remove Private Defects Roof Leaders/Faulty Clean- Outs & Sump Pumps Manhole Lining Within Basins No. 2 & 3 Properly Abandon Extra Service Connections On Oakley Line Last Remaining Sewer Within Basin No. 2 Along Hamilton Fix Storm Sewer Direct & Indirect Cross Connections
SLIDE 20
Rehabilitation Analysis
Additional Rehabilitation Options Evaluated: Sanitary Service Connection Lining (T-Liner) Construct Outlet Storm Sewer To Convey 10-Year Storm Event Install Overhead Sewers In High Risk Homes Construct Relief Sanitary Sewer Along Murray To Clair To Crystal To Wilder To Interceptor Fix Sanitary Sewer Bottleneck @ McClure & Wing Street Upsize Sanitary Sewer Along Wing Street To Interceptor At State
SLIDE 21
Rehabilitation Analysis
Storm Sewer Outfall Alignment
SLIDE 22
Rehabilitation Analysis
Sanitary Sewer Capacity Analysis – Existing Conditions
1 Yr Storm Event 2 Yr Storm Event 10 Yr Storm Event 25 Yr Storm Event
SLIDE 23
Rehabilitation Analysis
Sanitary Sewer Capacity Analysis – Lateral Lining In Basin No. 2 Only
1 Yr Storm Event 2 Yr Storm Event 10 Yr Storm Event 25 Yr Storm Event
SLIDE 24
Rehabilitation Analysis
Sanitary Sewer Capacity Analysis – Lateral Lining In Basins No. 2 & 3
1 Yr Storm Event 2 Yr Storm Event 10 Yr Storm Event 25 Yr Storm Event
SLIDE 25
Rehabilitation Analysis
Sanitary Sewer Capacity Analysis – Lateral Lining & Storm Sewer Outfall
1 Yr Storm Event 2 Yr Storm Event 10 Yr Storm Event 25 Yr Storm Event
SLIDE 26
Rehabilitation Analysis
Existing Conditions
SLIDE 27
Rehabilitation Analysis
With Lateral Lining & Manhole Rehab.
SLIDE 28
Rehabilitation Analysis
With Lateral Lining, Manhole Rehab. & Add. Storm Sewer Outlet
SLIDE 29
Financial Review & Summary
Recommended I&I Reduction Investment Needed In Study Area:
Private Defect Remediation Resident Storm Sewer Cross Conn. Remed. City Crews Overhead Sewer Installation (W/N 3 Feet) $416,000 Manhole Lining Within Basins No. 2 & 3 $53,000 Hamilton Sanitary Sewer Lining $15,000 Basin No. 2 Service T-Liners $640,000 Basin No. 3 Service T-Liners $565,000 North Storm Sewer Additional Outlet $1,466,000 Total: $3,155,000 +
SLIDE 30
Financial Review & Summary
Funding Review: Sanitary Sewer Mainline & Manhole Rehabilitation Is Cost Of Maintaining System Per City Code, Residents Own Sanitary Sewer Service To Mainline; Therefore T-Liner Should Be Resident’s Cost City of Elgin Overhead Sewer Reimbursement Program Storm Sewer Installation Funding To Be Evaluated
SLIDE 31