I-90 Mississippi River Bridge & Interchange Project Presentation - - PowerPoint PPT Presentation

i 90 mississippi river bridge interchange project
SMART_READER_LITE
LIVE PREVIEW

I-90 Mississippi River Bridge & Interchange Project Presentation - - PowerPoint PPT Presentation

I-90 Mississippi River Bridge & Interchange Project Presentation Outline I. Background: Context & Need for Project II. Preferred Alternative Overview III. Project Development IV. Project Management Tools & Innovation V.


slide-1
SLIDE 1

I-90 Mississippi River Bridge & Interchange Project

slide-2
SLIDE 2

Presentation Outline

I. Background: Context & Need for Project II. Preferred Alternative Overview III. Project Development IV. Project Management Tools & Innovation V. Questions & Answers

slide-3
SLIDE 3

Location: Interstate 90 crossing Mississippi. River near Dresbach, Minn.

slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6

Need for Project – Key Issues:

  • Structural
  • Existing deck geometry is deficient
  • Fatigue Cracking in plate girders
  • Additional components in poor condition
  • Non-redundant design
  • No “back-up” for member failure
  • Effect of Ch. 152 Legislation (Mn 2008)
slide-7
SLIDE 7

Need for Project – Key Issues (cont.)

  • Capacity
  • WB I-90 to SB 61 movement
  • Traffic volumes heavy during PM commute
  • Excessive backups onto I90 off-ramp
  • Safety – higher than average crash rates
  • I90 Mainline Curve
  • NB 61 – EB90 On-ramp
slide-8
SLIDE 8

Issues Map

slide-9
SLIDE 9

Project Requirements :

  • Provide free-flow movements between I-90 and US 14/61
  • Maintain I-90 WB access to/from Rest Area
  • Meet 70 mph design speed on I-90
  • Provide new river bridge with 100-year design life & structural redundancy
slide-10
SLIDE 10

Additional Priorities:

  • Minimize long-term maintenance costs of river bridge
  • Allow for future Rest Area reconstruction
  • Minimize Environmental Impacts
slide-11
SLIDE 11
slide-12
SLIDE 12

Bridge Aesthetics

slide-13
SLIDE 13
slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17

Project Elements:

  • 9 Bridges total:
  • 2 Concrete Box Girder River Spans
  • 2 curved steel bridges on I-90
  • 2 curved steel bridges @ interchange ramps
  • 2 concrete spans to/from Rest Area
  • 1 steel pedestrian bridge
slide-18
SLIDE 18

Project elements (cont.)

  • Realignment of I-90 Mainline
  • 70 mph design
  • Interchange modifications
  • Addition of “fly-under”
  • Added movements from Rest Area
slide-19
SLIDE 19

Project elements (cont.)

  • 15,000 lf. + retaining wall construction
  • Unique tiered wall systems
  • Storm sewer and Ponds
  • Rest Area reconstruction NOT included in

project.

slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22

Project Development

  • Process Overview
  • Preliminary Design
  • Final Design
slide-23
SLIDE 23
slide-24
SLIDE 24

Project Management - Key Challenges

  • Early identification of

– Current and future infrastructure needs – Environmental Constraints – Engineering Constraints – Community Needs

slide-25
SLIDE 25

Project Development – Key Challenges

  • Involvement of many participants & stakeholders
  • Decision-making (process, roles, and authority)
  • Consistent communications and documentation
slide-26
SLIDE 26

Key stakeholders- regulatory

  • Federal Highway Administration
  • Wisconsin Department of Transportation
  • Wisconsin Department of Natural Resources
  • U.S. Fish & Wildlife Service
  • U.S. Coast Guard
  • U.S. Army Corps of Engineers
  • Mn Department of Natural Resources
  • Mn Pollution Control Agency
slide-27
SLIDE 27

Key stakeholders - advisory

  • La Crosse Area Planning Commission
  • City of Onalaska
  • City of La Crosse
  • City of La Crescent
  • La Crosse Area Convention & Visitor Bureau
  • Winona County
  • La Crosse County
slide-28
SLIDE 28

MnDOT Stakeholders

  • Bridge Office
  • Rest Area/Site Development
  • Bike & Pedestrian Facilities
  • Geometric Design Services Unit
  • Investment Management
  • Land Management
slide-29
SLIDE 29

Project Development Committees

  • Project Advisory Committee (PAC)
  • Technical Advisory Committee (TAC)
slide-30
SLIDE 30

Project Status:

  • Environmental Document

Approval Dec. 2010

  • Final Design Initiating Nov.

2010

  • 100% Plan turn-in by late

Oct., 2011

  • < 12 months for Final Plan Set

delivery !!

slide-31
SLIDE 31

Project Development –Challenges Ahead

  • 1. Aggressive Schedule
  • 2. Complex Design & Constructability issues
  • 3. Potential for unknowns to develop
  • How Best to manage/mitigate challenges?
slide-32
SLIDE 32

Challenge 1: Schedule

  • Pace of delivery requires large team
  • Final Design segmented into 2 portions
  • River Bridge
  • Interchange and approach roadways
  • Final Design plan production outsourced
  • Approaches/Interchange: SRF, Inc.
  • River Span: TBD
slide-33
SLIDE 33
slide-34
SLIDE 34

Challenge 1: Schedule Project Management Tools to be incorporated:

  • Use of Oracle/Primavera P6 CPM
  • Task Management
  • Activities are cost & resource loaded
  • Frequent Plan Review Meetings
  • Bi-weekly OTS meetings
  • Video-conferencing as needed
  • Document Management System
slide-35
SLIDE 35

Challenge 2: Complex Constructability & Design Issues:

  • Independent design for:
  • River Span Bridge
  • Curved-steel girder approach bridges
  • Constructability Reviews
  • Included in Design Quality Reviews
  • Contract review one-on-ones
slide-36
SLIDE 36

Challenge 3: Potential for unknown issues to develop:

  • Conduct Risk Assessment Workshop shortly after

Final Design is initiated

slide-37
SLIDE 37

Opportunities for Innovation

  • Performance-Based specifications
  • Maintenance of Traffic During Construction
  • Alternative Technical Concepts
  • Alternate retaining wall types
slide-38
SLIDE 38
slide-39
SLIDE 39
slide-40
SLIDE 40
slide-41
SLIDE 41
slide-42
SLIDE 42
slide-43
SLIDE 43

Construction Phase: Bid Letting: February, 2012 Estimated Construction Cost: $164,000,000

  • 70% Mn
  • 30% WI
  • Construction Begins: Spring 2012
  • Construction Ends: Spring 2015 (anticipated)
slide-44
SLIDE 44

Questions?

Jai Kalsy, P.E., Project Manager Minnesota Department of Transportation 2900 48th Street NW Rochester, MN 55901 E-mail: jai.kalsy@state.mn.us