i 90 mississippi river bridge interchange project
play

I-90 Mississippi River Bridge & Interchange Project Presentation - PowerPoint PPT Presentation

I-90 Mississippi River Bridge & Interchange Project Presentation Outline I. Background: Context & Need for Project II. Preferred Alternative Overview III. Project Development IV. Project Management Tools & Innovation V.


  1. I-90 Mississippi River Bridge & Interchange Project

  2. Presentation Outline I. Background: Context & Need for Project II. Preferred Alternative Overview III. Project Development IV. Project Management Tools & Innovation V. Questions & Answers

  3. Location: Interstate 90 crossing Mississippi. River near Dresbach, Minn.

  4. Need for Project – Key Issues: • Structural • Existing deck geometry is deficient • Fatigue Cracking in plate girders • Additional components in poor condition • Non-redundant design •No “back-up” for member failure •Effect of Ch. 152 Legislation (Mn 2008)

  5. Need for Project – Key Issues (cont.) • Capacity • WB I-90 to SB 61 movement •Traffic volumes heavy during PM commute • Excessive backups onto I90 off-ramp •Safety – higher than average crash rates •I90 Mainline Curve •NB 61 – EB90 On-ramp

  6. Issues Map

  7. Project Requirements : • Provide free-flow movements between I-90 and US 14/61 • Maintain I-90 WB access to/from Rest Area • Meet 70 mph design speed on I-90 • Provide new river bridge with 100-year design life & structural redundancy

  8. Additional Priorities: • Minimize long-term maintenance costs of river bridge • Allow for future Rest Area reconstruction • Minimize Environmental Impacts

  9. Bridge Aesthetics

  10. Project Elements: • 9 Bridges total: •2 Concrete Box Girder River Spans •2 curved steel bridges on I-90 •2 curved steel bridges @ interchange ramps •2 concrete spans to/from Rest Area •1 steel pedestrian bridge

  11. Project elements (cont.) • Realignment of I-90 Mainline • 70 mph design • Interchange modifications •Addition of “fly-under” •Added movements from Rest Area

  12. Project elements (cont.) • 15,000 lf. + retaining wall construction •Unique tiered wall systems • Storm sewer and Ponds • Rest Area reconstruction NOT included in project.

  13. Project Development • Process Overview • Preliminary Design • Final Design

  14. Project Management - Key Challenges • Early identification of – Current and future infrastructure needs – Environmental Constraints – Engineering Constraints – Community Needs

  15. Project Development – Key Challenges • Involvement of many participants & stakeholders • Decision-making (process, roles, and authority) • Consistent communications and documentation

  16. Key stakeholders- regulatory • Federal Highway Administration • Wisconsin Department of Transportation • Wisconsin Department of Natural Resources • U.S. Fish & Wildlife Service • U.S. Coast Guard • U.S. Army Corps of Engineers • Mn Department of Natural Resources • Mn Pollution Control Agency

  17. Key stakeholders - advisory • La Crosse Area Planning Commission • City of Onalaska • City of La Crosse • City of La Crescent • La Crosse Area Convention & Visitor Bureau • Winona County • La Crosse County

  18. MnDOT Stakeholders • Bridge Office • Rest Area/Site Development • Bike & Pedestrian Facilities • Geometric Design Services Unit • Investment Management • Land Management

  19. Project Development Committees • Project Advisory Committee (PAC) • Technical Advisory Committee (TAC)

  20. Project Status: • Environmental Document Approval Dec. 2010 • Final Design Initiating Nov. 2010 • 100% Plan turn-in by late Oct., 2011 • < 12 months for Final Plan Set delivery !!

  21. Project Development –Challenges Ahead 1. Aggressive Schedule 2. Complex Design & Constructability issues 3. Potential for unknowns to develop • How Best to manage/mitigate challenges?

  22. Challenge 1: Schedule • Pace of delivery requires large team •Final Design segmented into 2 portions •River Bridge •Interchange and approach roadways •Final Design plan production outsourced •Approaches/Interchange: SRF, Inc. •River Span: TBD

  23. Challenge 1: Schedule Project Management Tools to be incorporated: • Use of Oracle/Primavera P6 CPM •Task Management •Activities are cost & resource loaded • Frequent Plan Review Meetings •Bi-weekly OTS meetings •Video-conferencing as needed • Document Management System

  24. Challenge 2: Complex Constructability & Design Issues: • Independent design for: •River Span Bridge •Curved-steel girder approach bridges • Constructability Reviews •Included in Design Quality Reviews •Contract review one-on-ones

  25. Challenge 3: Potential for unknown issues to develop: • Conduct Risk Assessment Workshop shortly after Final Design is initiated

  26. Opportunities for Innovation • Performance-Based specifications •Maintenance of Traffic During Construction • Alternative Technical Concepts •Alternate retaining wall types

  27. Construction Phase: Bid Letting: February, 2012 Estimated Construction Cost: $164,000,000 • 70% Mn • 30% WI •Construction Begins: Spring 2012 •Construction Ends: Spring 2015 (anticipated)

  28. Questions? Jai Kalsy, P.E., Project Manager Minnesota Department of Transportation 2900 48 th Street NW Rochester, MN 55901 E-mail: jai.kalsy@state.mn.us

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend