hwr for pxie proposed fabrication technology
play

HWR for PXIE: Proposed fabrication technology P.N. Ostroumov - PowerPoint PPT Presentation

HWR for PXIE: Proposed fabrication technology P.N. Ostroumov Physics Division October 26, 2011 Project X Collaboration Meeting, October 25-27, 2011 Content Recent activities of our Group Fabrication steps Purchase of Nb sheets and


  1. HWR for PXIE: Proposed fabrication technology P.N. Ostroumov Physics Division October 26, 2011 Project X Collaboration Meeting, October 25-27, 2011

  2. Content  Recent activities of our Group  Fabrication steps – Purchase of Nb sheets and bar stock – Nb forming – Brazed SS-Nb transition – Nb machining, wire EDM – BCP – EBW – SS vessel – Alignment fiducials  HWR for PXIE specs P.N. Ostroumov QWR&HWR Workshop, September 23-24, 2011 2 September 23, 2011

  3. Development and construction of a new 162.5 MHz HWR  EM Design - B. Mustapha  Mechanical design and engineering analysis – Z. Conway  Fabrication steps – Nb forming – Brazed SS-Nb transition – Nb machining, wire EDM – EBW – Frequency tuning – SS vessel – ASME pressure vessel code  Cavity Sub-systems: RF coupler, slow and fast tuners – M. Kelly, G. Zinkann  RF surface processing – M. Kelly  Cryomodule: assembly, alignment – Z. Conway and M. Kelly  Operational experience with SC ion linac – G. Zinkann

  4. Recent Experience of ANL Linac Development Group  In the past 26 months – Prototype 72.75 MHz QWR has been developed, built and tested – 6 production cavities have been built – Just finished construction of super-high gradient 72.75 MHz QW • Peak magnetic fields are expected to exceed 120 mT – New 322 MHz, β =0.285 HWR for the MSU/FRIB has been developed • Complete engineering and mechanical design – New super-high gradient 325 MHz HWR resonator has been developed • Being constructed, die forming of Nb parts is in progress • Will be completed in the summer of 2012 – Optimized EM design of SC cavities for several other applications • 162.5 MHz HWR for FNAL • Low- β (0.085) and high- β (0.15) 176 MHz HWRs for SARAF • Low- β (0.085) and high- β (0.15) 109 MHz QWRs for SARAF

  5. Overall design philosophy of SC cavities  Incorporate into the cavity design the following features and sub-systems – RF coupler – Slow tuner – Fast tuner – RF surface processing – Facilitate integration into the cryomodule • Cavity alignment  Fabrication is being done under close supervision of ANL experts – EBW by an ANL engineer – Wire EDM set up by an ANL engineer – Helium vessel work - under ANL engineer guidance  RF surface processing, assembly, testing – ANL experts P.N. Ostroumov QWR&HWR Workshop, September 23-24, 2011 5 September 23, 2011

  6. Example: 72.75 MHz QWR  Exploded view of Nb and SS parts  Nb purchase: 1/8” sheets and bar stocks  SS helium vessel  Nb-SS brazed joints

  7. HWR: exploded view (preliminary) 7

  8. Fabrication Steps: QWR Nb parts 30 cm 30 cm 30 cm P.N. Ostroumov QWR&HWR Workshop, September 23-24, 2011 8 September 23, 2011

  9. Niobium parts for production cavities, formed from flat sheets and machined from bar stocks Central conductor halves Toroids with gussets Bottom domes and extension tubes Cylinder housing Brazed Nb-SS transitions Tapered sections (coupling ports, beam ports) P.N. Ostroumov QWR&HWR Workshop, September 23-24, 2011 9 September 23, 2011

  10. Cavity Fabrication by Wire EDM  Essentially no possibility for inclusions Cavity Bottom Dome Center Conductor P.N. Ostroumov QWR&HWR Workshop, September 23-24, 2011 10 September 23, 2011

  11. Sinker EDM of the Toroid center conductor mating surface 11

  12. Wire EDM  Recast layer only 5 microns thick – Oxide of brass and niobium – Completely removed with a 5 minute BCP; not removed easily by EP

  13. BCP etch after Machining, EDM, 24 hours prior EBW

  14. Electron Beam Welding AFTER THE PARTS WELD SEAMS ARE EDMed OR MACHINED TO SIZE THEY RECEIVE A 5 MICRON BCP ETCH AND WITHIN 24 HOURS OF ETCH ARE WELDED. Cylindrical Housing Central Conductors 14

  15. Electron Beam Welding of multiple parts Tapered sections P.N. Ostroumov QWR&HWR IMP Workshop, September 23-24, 2011 15 September 23, 2011

  16. Welding of each part requires well-designed support fixturing 16

  17. Electron Beam Welding P.N. Ostroumov QWR&HWR IMP Workshop, September 23-24, 2011 17 September 23, 2011

  18. 18 Niobium welds completed

  19. Stainless steel jacket is assembled to complete cavity fabrication 19

  20. Stainless Steel LHe Vessel, TIG welding P.N. Ostroumov QWR&HWR Workshop, September 23-24, 2011 20 September 23, 2011

  21. Final Step: connect beam ports to the SS helium vessel using Electron Beam Welding P.N. Ostroumov QWR&HWR Workshop, September 23-24, 2011 21 September 23, 2011

  22. Fiducials for the cavity alignment

  23. Current status of the 162.5 MHz, β =0.11 HWR  EM design is nearly complete  Detailed procedures for the mechanical design and engineering analysis have been developed – is being started as I speak  Detailed fabrication procedure exists  Beam aperture – 33 mm  RF coupler will be capable either to transmit 10 kW RF power to the beam or withstand full reflection  Will be built in compliance with the ASME pressure vessel code

  24. First “Cold Test” of the new ATLAS Superconducting Quarter Wave Resonator, December 14, 2010

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend