HWR Handling in CMTF C. Baffes HWR Transportation Review 24 July - PowerPoint PPT Presentation

HWR Handling in CMTF C. Baffes HWR Transportation Review 24 July 2018 Outline Truck pulls into dock Handoff from truck to crane Crane to staging position, downstream end of PIP2IT cave Post-transport reassembly as specified


  1. HWR Handling in CMTF C. Baffes HWR Transportation Review 24 July 2018

  2. Outline • Truck pulls into dock • Handoff from truck to crane • Crane to staging position, downstream end of PIP2IT cave • Post-transport reassembly as specified by ANL team • Crane to final position in PIP2IT cave • Handoff to stand 2 C. Baffes | HWR Handling in CMTF 7/18/2018

  3. Outline • Truck pulls into dock • Handoff from truck to crane • Crane to staging position, downstream end of PIP2IT cave • Post-transport reassembly as specified by ANL team • Crane to final position in PIP2IT cave • Handoff to stand 3 C. Baffes | HWR Handling in CMTF 7/18/2018

  4. Truck Pulls Into Dock • Plan – just back in • Constraints – Roll-up door is 16’ wide – Usable area of dock is ~12’ X 58’ – Tail end of trailer must be unobstructed - if we use a roll-tite trailer, it must roll towards the cab – If significant on-trailer work is needed, we may want a short trailer so that the roll- N up door can be closed if CMTF dock weather is bad Crane bridge fully south 4 C. Baffes | HWR Handling in CMTF 7/18/2018

  5. Outline • Truck pulls into dock • Handoff from truck to crane • Crane to staging position, downstream end of PIP2IT cave • Post-transport reassembly as specified by ANL team • Crane to final position in PIP2IT cave • Handoff to stand 5 C. Baffes | HWR Handling in CMTF 7/18/2018

  6. Handoff from Truck to Crane • Plan – Rig HWR under crane – Take slack out of slings – Free HWR from trailer – Lift • Constraints – Structure to be cleared on trailer cannot exceed 10.5’ cave height – Not much room to work around the trailer – 20T crane capacity LCLS2 pCM @ CMTF dock 6 C. Baffes | HWR Handling in CMTF 7/18/2018

  7. Rigging layout • Hoist points on HWR lid • Simple 4-sling rigging arrangement • Same rigging to be used at ANL ° < 45 across diagonal Worst case load in single sling = .707*W = 13,200lb ~6’ (teeter-totter case) 10.3’ ~6’ 7 C. Baffes | HWR Handling in CMTF 7/18/2018

  8. Alternate Rigging layout • Compatible spreader bar is available • Trade-off: Spreader bar offers better geometry (lower profile, lower sling angles), but requires handling over HWR 8 C. Baffes | HWR Handling in CMTF 7/18/2018

  9. Outline • Truck pulls into dock • Handoff from truck to crane • Crane to staging position, downstream end of PIP2IT cave • Post-transport reassembly as specified by ANL team • Crane to final position in PIP2IT cave • Handoff to stand 9 C. Baffes | HWR Handling in CMTF 7/18/2018

  10. These two Crane into staging position blocks get • Plan removed – Crane over south cave wall – Tag lines to control rotation – Land on blocks in PIP2IT cave, downstream of final position – Idea is to provide good access all the way around the module • Constraints – 10.5’ south cave wall height Staging area Cave south wall 10 C. Baffes | HWR Handling in CMTF 7/18/2018

  11. Rigging Layout – strong constraint on height 24’ Elev. ~6’ 10.3’ ~6’ 10.5’ ~1’ Elev. Cave wall (roof removed) 11 C. Baffes | HWR Handling in CMTF 7/18/2018

  12. Crane into staging position Comparable operation at CMTS 13.5’ elevation, 3’ higher than PIP2IT 12 C. Baffes | HWR Handling in CMTF 7/18/2018

  13. Outline • Truck pulls into dock • Handoff from truck to crane • Crane to staging position, downstream end of PIP2IT cave • Post-transport reassembly as specified by ANL team • Crane to final position in PIP2IT cave • Handoff to stand 13 C. Baffes | HWR Handling in CMTF 7/18/2018

  14. Post-transport Reassembly • Plan – Work specified by ANL, not covered in this presentation • Constraints – May not have continuous crane coverage due to schedule interactions with CMTS1 work (LCLS2) 14 C. Baffes | HWR Handling in CMTF 7/18/2018

  15. Outline • Truck pulls into dock • Handoff from truck to crane • Crane to staging position, downstream end of PIP2IT cave • Post-transport reassembly as specified by ANL team • Crane to final position in PIP2IT cave • Handoff to stand 15 C. Baffes | HWR Handling in CMTF 7/18/2018

  16. Crane into final position • Plan – Lift and translate upstream in PIP2IT cave – Land on cribbing within 25mm of nominal position • Constraints – Less stringent vertical constraints than other craning operations – Typically, we are able to set with ~10mm accuracy at CMTS 16 C. Baffes | HWR Handling in CMTF 7/18/2018

  17. Outline • Truck pulls into dock • Handoff from truck to crane • Crane to staging position, downstream end of PIP2IT cave • Post-transport reassembly as specified by ANL team • Crane to final position in PIP2IT cave • Handoff to stand 17 C. Baffes | HWR Handling in CMTF 7/18/2018

  18. Handoff to stand • Plan – With HWR sitting rigidly on cribbing, interface adjustment struts – Use adjustment struts to transfer load – Remove cribbing – Rough align HWR • Constraints – cribbing needs to avoid couplers Cribbing on gussets 18

  19. End • Questions/Discussion 19 C. Baffes | HWR Handling in CMTF 7/18/2018

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.