HWR Handling in CMTF C. Baffes HWR Transportation Review 24 July - - PowerPoint PPT Presentation

hwr handling in cmtf
SMART_READER_LITE
LIVE PREVIEW

HWR Handling in CMTF C. Baffes HWR Transportation Review 24 July - - PowerPoint PPT Presentation

HWR Handling in CMTF C. Baffes HWR Transportation Review 24 July 2018 Outline Truck pulls into dock Handoff from truck to crane Crane to staging position, downstream end of PIP2IT cave Post-transport reassembly as specified


slide-1
SLIDE 1

HWR Handling in CMTF

  • C. Baffes

HWR Transportation Review 24 July 2018

slide-2
SLIDE 2

Outline

  • Truck pulls into dock
  • Handoff from truck to crane
  • Crane to staging position, downstream end of PIP2IT cave
  • Post-transport reassembly as specified by ANL team
  • Crane to final position in PIP2IT cave
  • Handoff to stand

7/18/2018

  • C. Baffes | HWR Handling in CMTF

2

slide-3
SLIDE 3

Outline

  • Truck pulls into dock
  • Handoff from truck to crane
  • Crane to staging position, downstream end of PIP2IT cave
  • Post-transport reassembly as specified by ANL team
  • Crane to final position in PIP2IT cave
  • Handoff to stand

7/18/2018

  • C. Baffes | HWR Handling in CMTF

3

slide-4
SLIDE 4
  • Plan – just back in
  • Constraints

– Roll-up door is 16’ wide – Usable area of dock is ~12’ X 58’ – Tail end of trailer must be unobstructed - if we use a roll-tite trailer, it must roll towards the cab – If significant on-trailer work is needed, we may want a short trailer so that the roll- up door can be closed if weather is bad

Truck Pulls Into Dock

7/18/2018

  • C. Baffes | HWR Handling in CMTF

4

N

CMTF dock Crane bridge fully south

slide-5
SLIDE 5

Outline

  • Truck pulls into dock
  • Handoff from truck to crane
  • Crane to staging position, downstream end of PIP2IT cave
  • Post-transport reassembly as specified by ANL team
  • Crane to final position in PIP2IT cave
  • Handoff to stand

7/18/2018

  • C. Baffes | HWR Handling in CMTF

5

slide-6
SLIDE 6
  • Plan

– Rig HWR under crane – Take slack out of slings – Free HWR from trailer – Lift

  • Constraints

– Structure to be cleared on trailer cannot exceed 10.5’ cave height – Not much room to work around the trailer – 20T crane capacity

Handoff from Truck to Crane

7/18/2018

  • C. Baffes | HWR Handling in CMTF

6

LCLS2 pCM @ CMTF dock

slide-7
SLIDE 7
  • Hoist points on HWR lid
  • Simple 4-sling rigging arrangement
  • Same rigging to be used at ANL

Rigging layout

7/18/2018

  • C. Baffes | HWR Handling in CMTF

7

~6’ 10.3’ ~6’ <45

° across diagonal Worst case load in single sling = .707*W = 13,200lb (teeter-totter case)

slide-8
SLIDE 8
  • Compatible spreader bar is available
  • Trade-off: Spreader bar offers better geometry (lower

profile, lower sling angles), but requires handling over HWR Alternate Rigging layout

7/18/2018

  • C. Baffes | HWR Handling in CMTF

8

slide-9
SLIDE 9

Outline

  • Truck pulls into dock
  • Handoff from truck to crane
  • Crane to staging position, downstream end of PIP2IT cave
  • Post-transport reassembly as specified by ANL team
  • Crane to final position in PIP2IT cave
  • Handoff to stand

7/18/2018

  • C. Baffes | HWR Handling in CMTF

9

slide-10
SLIDE 10
  • Plan

– Crane over south cave wall – Tag lines to control rotation – Land on blocks in PIP2IT cave, downstream of final position – Idea is to provide good access all the way around the module

  • Constraints

– 10.5’ south cave wall height

Crane into staging position

7/18/2018

  • C. Baffes | HWR Handling in CMTF

10

Cave south wall These two blocks get removed Staging area

slide-11
SLIDE 11

Rigging Layout – strong constraint on height

7/18/2018

  • C. Baffes | HWR Handling in CMTF

11

Cave wall (roof removed) 10.5’ Elev. 24’ Elev. ~1’ ~6’ 10.3’ ~6’

slide-12
SLIDE 12

Crane into staging position

7/18/2018

  • C. Baffes | HWR Handling in CMTF

12

13.5’ elevation, 3’ higher than PIP2IT Comparable operation at CMTS

slide-13
SLIDE 13

Outline

  • Truck pulls into dock
  • Handoff from truck to crane
  • Crane to staging position, downstream end of PIP2IT cave
  • Post-transport reassembly as specified by ANL team
  • Crane to final position in PIP2IT cave
  • Handoff to stand

7/18/2018

  • C. Baffes | HWR Handling in CMTF

13

slide-14
SLIDE 14
  • Plan

– Work specified by ANL, not covered in this presentation

  • Constraints

– May not have continuous crane coverage due to schedule interactions with CMTS1 work (LCLS2)

Post-transport Reassembly

7/18/2018

  • C. Baffes | HWR Handling in CMTF

14

slide-15
SLIDE 15

Outline

  • Truck pulls into dock
  • Handoff from truck to crane
  • Crane to staging position, downstream end of PIP2IT cave
  • Post-transport reassembly as specified by ANL team
  • Crane to final position in PIP2IT cave
  • Handoff to stand

7/18/2018

  • C. Baffes | HWR Handling in CMTF

15

slide-16
SLIDE 16
  • Plan

– Lift and translate upstream in PIP2IT cave – Land on cribbing within 25mm of nominal position

  • Constraints

– Less stringent vertical constraints than other craning operations – Typically, we are able to set with ~10mm accuracy at CMTS

Crane into final position

7/18/2018

  • C. Baffes | HWR Handling in CMTF

16

slide-17
SLIDE 17

Outline

  • Truck pulls into dock
  • Handoff from truck to crane
  • Crane to staging position, downstream end of PIP2IT cave
  • Post-transport reassembly as specified by ANL team
  • Crane to final position in PIP2IT cave
  • Handoff to stand

7/18/2018

  • C. Baffes | HWR Handling in CMTF

17

slide-18
SLIDE 18
  • Plan

– With HWR sitting rigidly on cribbing, interface adjustment struts – Use adjustment struts to transfer load – Remove cribbing – Rough align HWR

  • Constraints – cribbing needs to avoid couplers

Handoff to stand

18

Cribbing on gussets

slide-19
SLIDE 19
  • Questions/Discussion

End

7/18/2018

  • C. Baffes | HWR Handling in CMTF

19