How to start and achieve the BIM Project effectively Date 01/01/2014 - - PowerPoint PPT Presentation

how to start and achieve the bim project effectively
SMART_READER_LITE
LIVE PREVIEW

How to start and achieve the BIM Project effectively Date 01/01/2014 - - PowerPoint PPT Presentation

How to start and achieve the BIM Project effectively Date 01/01/2014 What is BIM? Geometry Data and Information Define the Project BIM Goals Before the actual BIM project begins Identify the project. Identify the importance of


slide-1
SLIDE 1

How to start and achieve the BIM Project effectively

Date – 01/01/2014

slide-2
SLIDE 2

What is BIM?

 Geometry  Data and Information

slide-3
SLIDE 3

Define the Project BIM Goals

Before the actual BIM project begins

  • Identify the project.
  • Identify the importance of using BIM from Client’s perspective.
  • Define the goals for future use of the BIM data.
  • Identify the role of owner, consultant, contractor and subcontractor.
slide-4
SLIDE 4

Select the right tool for Client’s perspective and Project

Building Civil Plant

Data Exchange Analysis Modeling Tools: Revit Bentley Digital Project Archi CAD Analysis: Structural Energy People movement Daylight Tools: AutoCAD Civil 3D Analysis: Alignments Surface condition Simulation Tools: Auto Plant Smart Plant Plant 3D PMDS Analysis: Pipe Stress Hydraulic Process Flow

slide-5
SLIDE 5

Identify the future use of BIM

= Integrated Project Delivery

slide-6
SLIDE 6

BIM Process

BIM Handover and Closeout

IFC & Validation of Basis of Design Planning

Model Development BIM System Finalization Build and Commission OWNER Design Review 3D Coordination Record Model Maintenance Scheduling & System Analysis

slide-7
SLIDE 7

IFC & Validation of Basis of Design:

 Confirm Subcontractors if ability to deliver BIM.  Existing Conditions Modeling  Provide IFC Design Documents from Architect or consultant.  Issue Direction to Initial RFIs.  Validate Project BIM Setup.  Consolidate Initial BIM RFIs and Change Recommendations.  Provide Basis of Design BIM based on IFC Document Set.  Document Initial RFIs.

BIM PLAN

slide-8
SLIDE 8

Common Questions:

  • How detailed should my model be?
  • How much information should I include in my model?
  • Who is responsible for modeling?
  • Should this be considered an additional service?

IFC & Validation of Basis of Design:

slide-9
SLIDE 9

Identify Project Information flow

IFC & Validation of Basis of Design: Owner Architect Management Consultant Contractor Subcontractor Subcontractor Subcontractor Facility Manager

slide-10
SLIDE 10

Who is the Author for each model element?

  • Party responsible for model elements:
  • Architect
  • Consultant
  • Contractor
  • Subcontractor

IFC & Validation of Basis of Design:

slide-11
SLIDE 11

How detailed should my model be?

  • LOD: 100 Conceptual Geometry
  • LOD: 200 Approximate Geometry
  • LOD: 300 Precise Geometry
  • LOD: 400 Fabrication
  • LOD: 500 AS-Built
  • Architect
  • Architect, Consultants
  • Architect, Consultants
  • Contractor, Sub-cons
  • Contractor, Sub-cons

IFC & Validation of Basis of Design:

= LOD (Level of Development)

slide-12
SLIDE 12

Select the right team (Staffing)

Project Phase

BIM Engineer:

  • Most experienced BIM users on TEAM
  • Initial Development of Model

BIM Modeler:

  • Less experienced BIM user on TEAM

BIM Manager:

  • Responsible for Database
  • Specifications

MODEL DEVELOPMENT:

slide-13
SLIDE 13

Assign the Task to BIM Team

Experienced BIM engineer is developing a majority of the model. Less Experienced BIM modeler can be added to the team to assist BIM engineer and complete the construction document BIM Manager Manages the implementation of supporting software and ensure that standards are kept high, and that work is being completed on time. MODEL DEVELOPMENT:

slide-14
SLIDE 14

Data exchange

Industry Foundation Classes (IFC) is an open standard for building data exchange developed by buildingSMART (formerly the IAI). IFC File Format MODEL DEVELOPMENT:

slide-15
SLIDE 15

Model development :C :Clash Detection

MODEL DEVELOPMENT:

slide-16
SLIDE 16

QA/Q /QC Process

  • When do we have to start QA/QC for BIM project?
  • Or export data for QA/QC?
  • Process of exporting to the right format to all parties at the end of the day/week or when needed.
  • What kind of tool is available for QA/QC?
  • Autodesk Design Review
  • Blue Beam
  • NavisWorks

EDUCATING STAFF ON QUALITY CONTROL :While it is always best to have a single individual responsible for the quality control of the models and that person should have a clear understanding of how the model should be developed, the standard of care and level of detail associated with the library, and the intent of the models that are being created. MODEL DEVELOPMENT:

slide-17
SLIDE 17

Conducting BIM Coordination Meeting

 Run Clash Detection Review results by subcontractors  Subcontractors conduct weekly meeting. Send the official document to consultant if they can’t resolve.  Consultant receives list of clashes that need to be resolved.  Repeat meeting as needed. ( or Virtual weekly meeting)

MODEL DEVELOPMENT:

slide-18
SLIDE 18

BIM System Finalization:

 Provide Project-Level Clash Detection and Recommend Solutions.  Validate Incorporation of Approved Changes.  Review/Approve Finalized Systems.  Monitor Final BIM Progress  Pull Final Shop Drawings & Reports from BIM as basis for submittals.

Finalize BIM Modeling & Shop Drawings Generation

slide-19
SLIDE 19

3D Tagging : Assets of Importance

  • Tagged with ID Number linked with Data (linked to from i-models)

BIM System Finalization:

slide-20
SLIDE 20

System Finalization:

Shop Drawings Generation

slide-21
SLIDE 21

Build and Commission:

 Define Systems to Pre-Fabricate.  Manage Supply Chain.  Manage Work Orders.  Validate Commissioning of Systems.  Pull System Fabrication from BIM.  Validate incorporation of Approved Changes.  Pull Performance Specifications from Model.  Incorporate Approved Changes.  Validate Commissioning of Systems.

BIM to Construction

slide-22
SLIDE 22

Handover and Closeout:

Final Deliverables  Provide Record As-Built Project Model.  Validate completeness of As-Built System Models.  Provide As-Built System Models for Facility Management.

slide-23
SLIDE 23
  • 1. Identify the Project Phases
  • 2. Determine the BIM uses
  • 3. Select Software
  • 4. Pick the People
  • 5. Develop BIM Model
  • 6. Coordination Meeting
  • 7. Shop Drawings Generation
  • 8. Final Documentation of BIM Model Deliverables

Summary :

Eight step process of BIM Project

slide-24
SLIDE 24