Team IPD/BIM Thesis BIM ception 2010-2011 Pfund Russell sell - PowerPoint PPT Presentation

The Millennium Science Complex Team IPD/BIM Thesis BIM ception 2010-2011 Pfund Russell sell Stough Villaca acamp mpa BIM ception Introduction Stephen Pfund Structural Christopher Russell Lighting/Electrical BIM ception is


  1. PCM Façade Assembly Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2 ” Face Brick Conclusions Plenum Investigation • 3” Concrete Panel Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  2. PCM Façade Assembly Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2 ” Face Brick Conclusions Plenum Investigation • 3” Concrete Panel Cantilever Plaza • 3.5” Air Space IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  3. PCM Façade Assembly Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2 ” Face Brick Conclusions Plenum Investigation • 3” Concrete Panel Cantilever Plaza • 3.5” Air Space IPD/BIM Reflection • 3” Rigid Insulation Pfund Russell sell Stough Villaca acamp mpa

  4. PCM Façade Assembly Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2 ” Face Brick Conclusions Plenum Investigation • 3” Concrete Panel Cantilever Plaza • 3.5” Air Space IPD/BIM Reflection • 3” Rigid Insulation • 3 ” PCM Panel Pfund Russell sell Stough Villaca acamp mpa

  5. Façade energy Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  6. Façade energy Analysis Building Info Annual Operating Costs Façade Investigation Overview $59,799 Wall Composition $70,000 $59,356 $60,254 Annual Operating Costs $59,855 Window To Wall Ratio Shade Analysis $60,000 $49,700 $48,208 Lighting Design Conclusions $50,000 $43,547 $44,764 $42,491 $43,770 Plenum Investigation $40,000 $39,111 Cantilever Plaza $38,526 IPD/BIM Reflection $30,000 Existing PCM Panel Design 3 Pane Redesign PCM & 3 Glazing Pane Purchased Steam (therms) Redesign Redesign Purchased Chilled Water (therms) Electricity (kWh) Pfund Russell sell Stough Villaca acamp mpa

  7. PCM Façade Rejection Building Info Annual Operating Costs Façade Investigation Overview • Minimal Energy Savings $59,799 Wall Composition $70,000 $59,356 $60,254 Annual Operating Costs $59,855 Window To Wall Ratio • Transportation/ Erection Shade Analysis $60,000 $49,700 $48,208 Lighting Design • Structural Thickness Conclusions $50,000 $43,547 $44,764 $42,491 $43,770 Limitations Plenum Investigation $40,000 $39,111 Cantilever Plaza • $38,526 Cost of Additional Materials IPD/BIM Reflection $30,000 Existing PCM Panel Design 3 Pane Redesign PCM & 3 Glazing Pane Purchased Steam (therms) Redesign Redesign Purchased Chilled Water (therms) Electricity (kWh) Pfund Russell sell Stough Villaca acamp mpa

  8. Final Assembly Selection Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  9. Final Assembly Selection Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  10. Final Assembly Selection Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  11. Final Assembly Selection Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2” Face Brick Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  12. Final Assembly Selection Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2” Face Brick Conclusions Plenum Investigation • 6” C-Panel Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  13. Final Assembly Selection Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2” Face Brick Conclusions Plenum Investigation • 6” C -Panel Cantilever Plaza • 3 ” Rigid Insulation IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  14. Final Assembly Selection Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2” Face Brick Conclusions Plenum Investigation • 6” C-Panel Cantilever Plaza • 3 ” Rigid Insulation IPD/BIM Reflection • Bearing Connections Relocated to Top Return Pfund Russell sell Stough Villaca acamp mpa

  15. Final Assembly Selection Building Info Façade Investigation Overview • Triple Pane Low-e Glazing Wall Composition Window To Wall Ratio • 16” Overhang and Shelf Shade Analysis Lighting Design • 2” Face Brick Conclusions Plenum Investigation • 6” C-Panel Cantilever Plaza • 3 ” Rigid Insulation IPD/BIM Reflection • Bearing Connections Relocated to Top Return Pfund Russell sell Stough Villaca acamp mpa

  16. Life Cycle Cost Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Third Floor, Existing Panels Shade Analysis Length of Panel 2-Pane Glass Assembly 3-Pane Glass Assembly Lighting Design 22ft $1,496,443 $1,587,963 Conclusions 14ft $41,091 $43,331 Plenum Investigation 31ft $78,510 $83,470 Cantilever Plaza Total $1,616,044 $1,714,764 Increased Cost of 3-Pane $98,720 IPD/BIM Reflection $98,720 more for 3-Pane Glazing Pfund Russell sell Stough Villaca acamp mpa

  17. Life Cycle Cost Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Existing Triple Pane Savings Third Floor, Existing Panels Glazing Shade Analysis Length of Panel 2-Pane Glass Assembly 3-Pane Glass Assembly Total Yearly Lighting Design 22ft $1,496,443 $1,587,963 $154,262 $142,912 $11,350 Operating Costs Conclusions 14ft $41,091 $43,331 Installation Plenum Investigation 31ft $78,510 $83,470 $1,616,044 $1,714,764 $-98,720 Costs Cantilever Plaza Total $1,616,044 $1,714,764 30 yr Life Cycle $5,591,498 $5,397,713 $193,785 Increased Cost of 3-Pane $98,720 Cost IPD/BIM Reflection $98,720 more for 3-Pane Glazing Includes fuel escalation and inflation Pfund Russell sell Stough Villaca acamp mpa

  18. Life Cycle Cost Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Existing Triple Pane Savings Third Floor, Existing Panels Glazing Shade Analysis Length of Panel 2-Pane Glass Assembly 3-Pane Glass Assembly Total Yearly Lighting Design 22ft $1,496,443 $1,587,963 $154,262 $142,912 $11,350 Operating Costs Conclusions 14ft $41,091 $43,331 Installation Plenum Investigation 31ft $78,510 $83,470 $1,616,044 $1,714,764 $-98,720 Costs Cantilever Plaza Total $1,616,044 $1,714,764 30 yr Life Cycle $5,591,498 $5,397,713 $193,785 Increased Cost of 3-Pane $98,720 Cost IPD/BIM Reflection 8.7 Year Simple Payback $98,720 more for 3-Pane Glazing Includes fuel escalation and inflation Pfund Russell sell Stough Villaca acamp mpa

  19. Existing Conditions Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio • WWR =70% Shade Analysis Lighting Design • Transmittance = 72% Conclusions Plenum Investigation • U-Value = 0.41 Cantilever Plaza • SHGC = 0.37 IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  20. Useful Illuminance Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Existing Conditions Pfund Russell sell Stough Villaca acamp mpa

  21. Useful Illuminance Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Existing Conditions 60% WWR Pfund Russell sell Stough Villaca acamp mpa

  22. Useful Illuminance Building Info Façade Investigation Window to Wall Ratio Selection Overview Wall Composition 0 Window To Wall Ratio -1 Shade Analysis Percent of Floor Area Useful Illuminance -2 Lighting Design Conclusions -3 Plenum Investigation -4 Cantilever Plaza -5 IPD/BIM Reflection -6 -7 -8 50 60 70 80 90 Percent Glass in Room Cavity Lighting 60% WWR Pfund Russell sell Stough Villaca acamp mpa

  23. Percent Energy Savings Building Info Façade Investigation Energy Intensity (kbtu/sf yr) Overview Energy Intensity (kbtu/sf yr) Wall Composition 162.3 Window To Wall Ratio 156.8 160 154.1 151.6 146.9 142.9 Shade Analysis Lighting Design 134.8 136.9 139.5 141.0 140 145.8 142.5 Conclusions Plenum Investigation 120 Cantilever Plaza IPD/BIM Reflection 100 50% 60% 70% 75% 80% 90% Percent Glass in Room Cavity 3 Pane Façade Existing Façade Pfund Russell sell Stough Villaca acamp mpa

  24. Percent Energy Savings Building Info Façade Investigation Energy Intensity (kbtu/sf yr) Window to Wall Ratio Selection Overview Energy Intensity (kbtu/sf yr) Wall Composition 162.3 Window To Wall Ratio 156.8 160 154.1 151.6 146.9 14 Percent Energy Savings 142.9 Shade Analysis Lighting Design 12 134.8 136.9 139.5 141.0 140 145.8 142.5 Conclusions 10 Plenum Investigation 120 Cantilever Plaza 8 IPD/BIM Reflection 100 6 50% 60% 4 70% 75% 50 60 70 80 90 80% Percent Glass in Room Cavity 90% Percent Glass in Room Cavity Mechanical 3 Pane Façade Existing Façade Pfund Russell sell Stough Villaca acamp mpa

  25. Minimum Concrete Thickness Building Info Façade Investigation Wu Overview • Flexure - Self Weight Wall Composition Window To Wall Ratio • 6” Practical for reinforcing Shade Analysis Lighting Design conditions Conclusions Plenum Investigation Cantilever Plaza M cap (lb- Ratio (%) Minimum Thickness (in) M sw (lb-ft) M wind (lb-ft) IPD/BIM Reflection ft) 50 6 2864 2819 1081 60 5.5 2406 2152 883 70 4.5 1611 1477 706 80 4 1273 1058 550 Pfund Russell sell Stough Villaca acamp mpa

  26. Construction Cost Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Third Floor, Redesigned Panel Shade Analysis Length of Panel 70% 60% Lighting Design 22ft $1,530,763 $1,539,322 Conclusions 14ft $41,131 $41,331 Plenum Investigation 31ft $81,270 $81,733 Cantilever Plaza Total $1,653,164 $1,662,387 IPD/BIM Reflection Increased Cost of 60% $9,223 $9,223 more for 60% Glass Ratio Pfund Russell sell Stough Villaca acamp mpa

  27. Window To Wall Ratio Selection Building Info Façade Investigation Window to Wall Ratio Selection Overview $1,662,387 $1,653,164! Wall Composition 0 Window To Wall Ratio Third Floor, Redesigned Panel 14 Percent Energy Savings -1 Shade Analysis Percent of Floor Area Useful Illuminance Length of Panel 70% 60% Lighting Design -2 12 22ft $1,530,763 $1,539,322 Conclusions -3 14ft $41,131 $41,331 10 Plenum Investigation -4 31ft $81,270 $81,733 Cantilever Plaza -5 8 Total $1,653,164 $1,662,387 IPD/BIM Reflection Increased Cost of 60% $9,223 -6 6 $9,223 more for 60% Glass Ratio -7 4 -8 50 60 70 80 90 Percent Glass in Room Cavity Mechanical Lighting Pfund Russell sell Stough Villaca acamp mpa

  28. Life Cycle Cost Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Third Floor, Redesigned Panel 70 % Glass 60 % Glass Savings Shade Analysis Length of Panel 70% 60% Lighting Design Total Yearly 22ft $1,530,763 $1,539,322 $142,912 $139,338 $3,574 Operating Costs Conclusions 14ft $41,131 $41,331 Installation Plenum Investigation $1,653,164 $1,662,387 $-9,223 31ft $81,270 $81,733 Costs Cantilever Plaza Total $1,653,164 $1,662,387 30 yr Life Cycle $5,336,113 $5,253,245 $82,868 IPD/BIM Reflection Cost Increased Cost of 60% $9,223 $9,223 more for 60% Glass Ratio Pfund Russell sell Stough Villaca acamp mpa

  29. Life Cycle Cost Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Third Floor, Redesigned Panel 70 % Glass 60 % Glass Savings Shade Analysis Length of Panel 70% 60% Lighting Design Total Yearly 22ft $1,530,763 $1,539,322 $142,912 $139,338 $3,574 Operating Costs Conclusions 14ft $41,131 $41,331 Installation Plenum Investigation $1,653,164 $1,662,387 $-9,223 31ft $81,270 $81,733 Costs Cantilever Plaza Total $1,653,164 $1,662,387 30 yr Life Cycle $5,336,113 $5,253,245 $82,868 IPD/BIM Reflection Cost Increased Cost of 60% $9,223 2.6 Year Simple Payback $9,223 more for 60% Glass Ratio Pfund Russell sell Stough Villaca acamp mpa

  30. Precast Panel Erection Building Info Façade Investigation Overview Wall Composition • Existing Schedule Window To Wall Ratio Shade Analysis • Start: November 16, 2009 Lighting Design Conclusions • Finish: May 17, 2010 Plenum Investigation Cantilever Plaza IPD/BIM Reflection • New Schedule • Start: December 7, 2009 • Finish: March 4, 2010 Precast Erection Plan Pfund Russell sell Stough Villaca acamp mpa

  31. Precast Panel Erection Building Info Façade Investigation Overview Wall Composition • Existing Schedule Window To Wall Ratio Shade Analysis • Start: November 16, 2009 Lighting Design Conclusions • Finish: May 17, 2010 Plenum Investigation Cantilever Plaza IPD/BIM Reflection • New Schedule • Start: December 7, 2009 • Finish: March 4, 2010 Precast Erection Plan Pfund Russell sell Stough Villaca acamp mpa

  32. Precast Panel Erection Building Info Façade Investigation Overview Wall Composition • Existing Schedule Window To Wall Ratio Shade Analysis • Start: November 16, 2009 Lighting Design Conclusions • Finish: May 17, 2010 Plenum Investigation Cantilever Plaza IPD/BIM Reflection • New Schedule • Start: December 7, 2009 • Finish: March 4, 2010 Precast Erection Plan Pfund Russell sell Stough Villaca acamp mpa

  33. Precast Panel Erection Building Info Façade Investigation Overview Wall Composition • Existing Schedule Window To Wall Ratio Shade Analysis • Start: November 16, 2009 Lighting Design Conclusions • Finish: May 17, 2010 Plenum Investigation Cantilever Plaza IPD/BIM Reflection • New Schedule • Start: December 7, 2009 • Finish: March 4, 2010 Precast Erection Plan Pfund Russell sell Stough Villaca acamp mpa

  34. Precast Panel Erection Building Info Façade Investigation Overview Wall Composition • Existing Schedule Window To Wall Ratio Shade Analysis • Start: November 16, 2009 Lighting Design Conclusions • Finish: May 17, 2010 Plenum Investigation Cantilever Plaza IPD/BIM Reflection • New Schedule • Start: December 7, 2009 • Finish: March 4, 2010 Precast Erection Plan Pfund Russell sell Stough Villaca acamp mpa

  35. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  36. Exterior Shade Analysis Building Info Façade Investigation Overview 160,000 • Analyze Effects of Solar Radiation Wall Composition (BTU/SF) Window To Wall Ratio 100,000 • Reduce External Building Loading Shade Analysis Lighting Design 45,000 Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Cumulative Yearly Incident Solar Radiation (BTU/SF) Pfund Russell sell Stough Villaca acamp mpa

  37. Percent Consumption Relative to Exterior Shade Analysis Shelf Mounting Height Building Info 102% Façade Investigation 99.99% 99.98% Overview 99.99% 160,000 100% 100.00% Existing 100.02% 100.03% Wall Composition 98% (BTU/SF) Window To Wall Ratio 100,000 5’6” 6’0” 6’6” Shade Analysis 7’0” 7’6” 8’0” Shade Mounting Hieght Lighting Design 45,000 Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Cumulative Yearly Incident Solar Radiation (BTU/SF) Pfund Russell sell Stough Villaca acamp mpa

  38. Percent Consumption Relative to Exterior Shade Analysis Shelf Mounting Height Building Info 102% Façade Investigation 99.99% 99.98% Overview 99.99% 160,000 100% 100.00% Existing 100.02% 100.03% Wall Composition 98% (BTU/SF) Window To Wall Ratio 100,000 5’6” 6’0” 6’6” Shade Analysis 7’0” 7’6” 8’0” Shade Mounting Hieght Lighting Design 45,000 Conclusions Plenum Investigation Overhang and Shelf Projection Cantilever Plaza Percent Consumption Relative to Length 100.0% IPD/BIM Reflection 100.00% No Shade Condition 98.5% 98.0% 98.00% 97.5% 96.5% 96.00% Cumulative Yearly Incident 94.00% Solar Radiation (BTU/SF) 0” 12" 18” 24” 36” Shade Projection Length Pfund Russell sell Stough Villaca acamp mpa

  39. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  40. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  41. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  42. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  43. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  44. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  45. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  46. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  47. Shade Analysis Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  48. Lighting Design Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  49. Lighting Design Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  50. Lighting Design Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  51. Lighting Design Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  52. Lighting Design Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  53. Lighting Design Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  54. Lighting Design Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Student Area Pseudo Color Pfund Russell sell Stough Villaca acamp mpa

  55. Lighting Design Building Info Façade Investigation Overview Wall Composition IESNA Illumination Recommendations for Student Area Window To Wall Ratio Avg. Horizontal Illuminance Shade Analysis Area Target Design Lighting Design Student Area Desk 30 fc 34 fc Conclusions Corridor 5 fc 21.7 fc Plenum Investigation Cantilever Plaza IPD/BIM Reflection ASHRAE Power Density Requirements Area Allowable Design Student Area 1.2 W / SF 0.86 W / SF Corridor 0.5 W / SF 0.40 W / SF Pfund Russell sell Stough Villaca acamp mpa

  56. Daysim Control Study Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Student Area Da con 322.8 lux Pfund Russell sell Stough Villaca acamp mpa

  57. Daysim Control Study Building Info Façade Investigation Overview Percent of Yearly Peak Lighting Load Wall Composition Percent of Peak Lighting Load Window To Wall Ratio 100.0 Shade Analysis Lighting Design 80.0 Conclusions 60.0 Plenum Investigation 40.0 Cantilever Plaza 20.0 IPD/BIM Reflection 0.0 Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec North Student Area Month South Student Area Student Area Da con 322.8 lux Pfund Russell sell Stough Villaca acamp mpa

  58. Lighting Energy Analysis Building Info Façade Investigation Overview Percent of Yearly Peak Lighting Load Wall Composition Percent of Peak Lighting Load Window To Wall Ratio 100.0 Shade Analysis Existing Design Lighting Redesign Savings Lighting Design 80.0 Conclusions Total Yearly $140,379 $137,859 $2,520 60.0 Operating Costs Plenum Investigation 40.0 Cantilever Plaza Installation $42,016 $34,695 $7,321 20.0 IPD/BIM Reflection Costs 0.0 30 yr Life Cycle $3,659,698 $3,587,427 $72,271 Jan Feb Mar Apr May Jun Cost Jul Aug Sept Oct Nov Dec North Student Area Month South Student Area Pfund Russell sell Stough Villaca acamp mpa

  59. Lighting Energy Analysis Building Info Façade Investigation Overview Percent of Yearly Peak Lighting Load Wall Composition Percent of Peak Lighting Load Window To Wall Ratio 100.0 Shade Analysis Existing Design Lighting Redesign Savings Lighting Design 80.0 Conclusions Total Yearly $140,379 $137,859 $2,520 60.0 Operating Costs Plenum Investigation 40.0 Cantilever Plaza Installation $42,016 $34,695 $7,321 20.0 IPD/BIM Reflection Costs 0.0 30 yr Life Cycle $3,659,698 $3,587,427 $72,271 Jan Feb Mar Apr May Jun Cost Jul Aug Sept Oct Immediate Return on Investment Nov Dec North Student Area Month South Student Area Pfund Russell sell Stough Villaca acamp mpa

  60. Façade Conclusions Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Existing Façade Conclusions Façade Redesign Plenum Investigation Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  61. Façade Conclusions Building Info Façade Investigation Overview Wall Composition Window To Wall Ratio Shade Analysis Lighting Design Conclusions Plenum Investigation Cantilever Plaza IPD/BIM Reflection Existing Design Façade Redesign Pfund Russell sell Stough Villaca acamp mpa

  62. Plenum Investigation Building Info Façade Investigation Plenum Investigation Overview Floor System Duct System Coordination Logistics/Schedule 4D Modeling Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  63. Plenum Analyses Building Info Façade Investigation Plenum Investigation • Floor System redesign/ Vibration Overview Floor System Analysis Duct System Coordination Logistics/Schedule 4D Modeling Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  64. Plenum Analyses Building Info Façade Investigation Plenum Investigation • Floor System redesign/ Vibration Overview Floor System Analysis Duct System • Duct System Redesign Coordination Logistics/Schedule 4D Modeling Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  65. Plenum Analyses Building Info Façade Investigation Plenum Investigation • Floor System redesign/ Vibration Overview Floor System Analysis Duct System • Duct System Redesign Coordination Logistics/Schedule • Structural/Mechanical Coordination 4D Modeling Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  66. Plenum Analyses Building Info Façade Investigation Plenum Investigation • Floor System redesign/ Vibration Overview Floor System Analysis Duct System • Duct System Redesign Coordination Logistics/Schedule • Structural/Mechanical Coordination 4D Modeling Cantilever Plaza • 4D Modeling IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  67. Existing Floor System Building Info Façade Investigation Plenum Investigation • One-way composite steel beams Overview Floor System • 22ft square bays Duct System Coordination • 11ft Beam spacing Logistics/Schedule 4D Modeling • 6.25” LWC slab, 3” 18ga Deck Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  68. Existing Floor System Building Info Façade Investigation Plenum Investigation • One-way composite steel beams Overview Floor System • 22ft square bays Duct System Coordination • 11ft Beam spacing Logistics/Schedule 4D Modeling • 6.25” LWC slab, 3” 18ga Deck Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  69. Existing Vibration Analysis Building Info Façade Investigation Uv(lb/sec2) Δ p (in/100kip) Span/Location Weight T(sec) Velocity(ui/sec) Plenum Investigation A 27.7 5500 1.115 0.0639 3916 • AISC Design Guide 11- Floor Overview B 27.2 5500 1.004 0.0601 3317 Floor System Vibration Due to Human Activity C 26.8 5500 1.138 0.0649 4063 Duct System • SAP2000 model – AE597A Coordination Logistics/Schedule • Point Load – Deflection Analysis 4D Modeling Cantilever Plaza • Period of vibration calculation using IPD/BIM Reflection Rayleigh method • Life Science Wing – 4000ui/s Pfund Russell sell Stough Villaca acamp mpa

  70. Floor System Alternatives Building Info Façade Investigation Plenum Investigation • Typical Gravity System within Wings Overview Floor System • Save vertical plenum space Duct System Coordination • Concrete typically thinner profile Logistics/Schedule 4D Modeling Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  71. Three Building Mixed System Building Info Façade Investigation Plenum Investigation • Seamless Integration at intersection Overview Floor System • Waffle Slab/ One-Way Pan Joist Duct System Coordination • Vibrations will determine required Logistics/Schedule stiffness 4D Modeling Cantilever Plaza IPD/BIM Reflection Pfund Russell sell Stough Villaca acamp mpa

  72. One-Way Pan-Joist Design Building Info Façade Investigation Plenum Investigation • Designed For Strength Overview Floor System • ACI318-08, Flexural/ Shear Design Duct System Coordination • 3ft Module: 30”pans, 6” ribs Logistics/Schedule 4D Modeling • 10” deep pans – Table 9.5a Cantilever Plaza • 18” Interior Beams on column lines IPD/BIM Reflection • 36” Wide Girders • 18” square columns Pfund Russell sell Stough Villaca acamp mpa

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.