BIM and Project Controls: An overview of 5D BIM Ian Levers Agenda - PowerPoint PPT Presentation
BIM and Project Controls: An overview of 5D BIM Ian Levers Agenda An introduction to 5D BIM The 5D BIM Workflow Barriers and enablers to successful 5D BIM What next? The 5D BIM Workflow What is 5D BIM? An introduction to 5D
BIM and Project Controls: An overview of 5D BIM – Ian Levers
Agenda � An introduction to 5D BIM � The 5D BIM Workflow � Barriers and enablers to successful 5D BIM � What next?
The 5D BIM Workflow What is 5D BIM?
An introduction to 5D BIM Line Object Time - Cost – Drawings Models Schedules Plans /Estimates 3D 5D 2D 4D Automated Quantity Take-off
An introduction to 5D BIM What are the efficiencies? 1. Clarifies the design 2. Simplify & speed up take-off 3. Visual record of measurement 4. Risk reduction 5. Focus on value adding: not take-off 6. Early & improved value engineering
An introduction to 5D BIM � Where does this leave our role? � What’s the reality?
The 5D BIM Workflow The 5D BIM Workflow
The Information Delivery Cycle Source BSI: PAS 1192 Part 2 Employer Decision Points
The 5D BIM Workflow � EIRs (Employer Information Requirements) informs the… � BEP (BIM Execution Plan) tells us……… � Who authors the BIM � Who manages the process � Who detects clashes � How information is exchanged � LoD = ‘Level of Detail’ (or development/ definition) � Software implementation strategy
Why use Specialist 5D Software? Why not add a cost parameter to each 3D object in the authoring tool?
From the BIM we are able to……….
How is Information Exchanged � CDE (Common Data Environment) such as Project Wise � Native file format (dwfx, rvt, dgn, i.dgn etc. etc.).. or IFC? � 5D BIM Protocol – Using scheduling from C3D etc… � What data is exchanged? � Non-geometrical � Geometrical
Non-geometrical Data Exchange
Geometrical Data Exchange
QA, QA and more QA
………OK, maybe just a little bit more QA
Standardised Libraries WBS, CBS, Method of Measurement
Parametric Link – isolated view Published data, 3D View and CESMM
Parametric Link – highlighted view This link enables speedy VE
Outputs – To support EDPs Cost Plans, Estimates, PTEs, BoQs
Example Projects
Example Projects
Example Projects
Example Projects
Barriers and Enablers to 5D BIM � Barriers � Incomplete EIRs � Poor data, naming conventions etc. � Software interoperability � Modelling standards � Enablers � A robust BEP including…… � Robust 5D protocols (modelling for 5D) � Enthusiasm � Basic modelling knowledge � Trial and Error
What’s Next? � 4D • Why not let the quantities drive the programme? � 6D+ • Carbon, • Embodied Water, • LCC � Earned Value using the real time “As-Built” model?