helcom plus project
play

HELCOM PLUS project Project Status Updates Sriram Sethuraman ( - PowerPoint PPT Presentation

HELCOM PLUS project Project Status Updates Sriram Sethuraman ( Project Manager ) Marco Manzi (SYKE) Pekka Kotilainen (PLC Data Manager), Liisa Tuominen-Roto (SYKE) Project Updates Work Package # 1 Overview Expected completion timeline -


  1. HELCOM PLUS project Project Status Updates Sriram Sethuraman ( Project Manager ) Marco Manzi (SYKE) Pekka Kotilainen (PLC Data Manager), Liisa Tuominen-Roto (SYKE)

  2. Project Updates • Work Package # 1 Overview – Expected completion timeline - April 2014 – Overall – 75 % complete • Key Activities – Data Model Finalization :- 90 % complete . Updated towards comments received during PLUS 5/2014 – QA Process Diagram – 100 % complete Database Design Document:- 80 % complete . Updated towards • comments received during PLUS 5/2014. Parts related to QA and certain other requirements will be updated during WP3 and WP4, when additional inputs are received from Contracting Parties.

  3. QA Process Diagram

  4. Work Package # 2 Preliminary activities for Migration Creation of database copy in MS-SQL – completed • Table dependency and Migration order finalization – 80 % • Main Migration Activities - Yet to start List of Activities Migration Strategy document • Migration testing approach • Overall migration and testing of the data base • Finalization of Database schema post migration •

  5. Work Package # 3 To be started after the completion of Work Package # 2 Activities Revision of Data Format Specifications • Reporting Form Creation • Identification of items to be reported as per new structure • Creation of optimal reporting template as per needs. • User requirement specification document including mock up • screens Web Application Development for testing of Reporting Form • upload Testing approach and testing of Reporting form Upload •

  6. Schedule of WP1 and WP2 Tasks for HELCOM PLUS

  7. Attachment 1 Updated Roadmap for implementation of HELCOM PLUS project (last updated 03.03.2014)

  8. Other Items and Actions required 3) Open questions Data Model to be commented and approved by Contracting Parties • Functional Requirement Specifications has been updated, except for specific functionalities • related to WP 3 and WP 4 ( QA) KT discussions between SYKE and BNI including involvment in PLUS development activities • will start during March 2014.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend