HELCOM PLUS project
Project Status Updates
Sriram Sethuraman ( Project Manager ) Marco Manzi (SYKE) Pekka Kotilainen (PLC Data Manager), Liisa Tuominen-Roto (SYKE)
HELCOM PLUS project Project Status Updates Sriram Sethuraman ( - - PowerPoint PPT Presentation
HELCOM PLUS project Project Status Updates Sriram Sethuraman ( Project Manager ) Marco Manzi (SYKE) Pekka Kotilainen (PLC Data Manager), Liisa Tuominen-Roto (SYKE) Project Updates Work Package # 1 Overview Expected completion timeline -
Sriram Sethuraman ( Project Manager ) Marco Manzi (SYKE) Pekka Kotilainen (PLC Data Manager), Liisa Tuominen-Roto (SYKE)
– Expected completion timeline - April 2014 – Overall – 75 % complete
– Data Model Finalization :- 90 % complete . Updated towards comments received during PLUS 5/2014 – QA Process Diagram – 100 % complete
comments received during PLUS 5/2014. Parts related to QA and certain other requirements will be updated during WP3 and WP4, when additional inputs are received from Contracting Parties.
QA Process Diagram
Work Package # 2 Preliminary activities for Migration
Main Migration Activities - Yet to start List of Activities
Work Package # 3 To be started after the completion of Work Package # 2 Activities
screens
upload
Schedule of WP1 and WP2 Tasks for HELCOM PLUS
Attachment 1 Updated Roadmap for implementation of HELCOM PLUS project (last updated 03.03.2014)
related to WP 3 and WP 4 ( QA)
will start during March 2014.