HELCOM PLUS project

Project Status Updates

Sriram Sethuraman ( Project Manager ) Marco Manzi (SYKE) Pekka Kotilainen (PLC Data Manager), Liisa Tuominen-Roto (SYKE)

slide-2
SLIDE 2

Overview

Project Updates

  • Work Package # 1

– Expected completion timeline - April 2014 – Overall – 75 % complete

  • Key Activities

– Data Model Finalization :- 90 % complete . Updated towards comments received during PLUS 5/2014 – QA Process Diagram – 100 % complete

  • Database Design Document:- 80 % complete . Updated towards

comments received during PLUS 5/2014. Parts related to QA and certain other requirements will be updated during WP3 and WP4, when additional inputs are received from Contracting Parties.

slide-3
SLIDE 3

QA Process Diagram

slide-4
SLIDE 4

Work Package # 2 Preliminary activities for Migration

  • Creation of database copy in MS-SQL – completed
  • Table dependency and Migration order finalization – 80 %

Main Migration Activities - Yet to start List of Activities

  • Migration Strategy document
  • Migration testing approach
  • Overall migration and testing of the data base
  • Finalization of Database schema post migration
slide-5
SLIDE 5

Work Package # 3 To be started after the completion of Work Package # 2 Activities

  • Revision of Data Format Specifications
  • Reporting Form Creation
  • Identification of items to be reported as per new structure
  • Creation of optimal reporting template as per needs.
  • User requirement specification document including mock up

screens

  • Web Application Development for testing of Reporting Form

upload

  • Testing approach and testing of Reporting form Upload
slide-6
SLIDE 6

Schedule of WP1 and WP2 Tasks for HELCOM PLUS

slide-7
SLIDE 7

Attachment 1 Updated Roadmap for implementation of HELCOM PLUS project (last updated 03.03.2014)

slide-8
SLIDE 8

3) Open questions Other Items and Actions required

  • Data Model to be commented and approved by Contracting Parties
  • Functional Requirement Specifications has been updated, except for specific functionalities

related to WP 3 and WP 4 ( QA)

  • KT discussions between SYKE and BNI including involvment in PLUS development activities

will start during March 2014.

slide-9
SLIDE 9