Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 1
HCAL Status HCAL Status HCAL Status CMS HCAL Status Jim Freeman - - PowerPoint PPT Presentation
HCAL Status HCAL Status HCAL Status CMS HCAL Status Jim Freeman - - PowerPoint PPT Presentation
HCAL Status HCAL Status HCAL Status CMS HCAL Status Jim Freeman Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 20, 2002 1 Outline Outline Outline Absorber Optics Status at CERN HPDs Front End Electronics
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 2
Outline Outline Outline
- Absorber
- Optics
- Status at CERN
- HPDs
- Front End Electronics
- Higher Level readout
- Radioactive Source Test Milestone
- HF
- Summer 2002 Testbeam
- Longer Term Schedule
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 3
HB wedge design HB wedge design HB wedge design
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 4
Absorber Absorber Absorber
HB- at SX5 at CERN
- 17 HB+ wedges at CERN in
Building 186. (Wedge 16 being repaired)
- Optics installed, QC Testing
in progress
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 5
HB Wedges at Bldg 186 HB Wedges at Bldg 186 HB Wedges at Bldg 186
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 6
HB- wedge 16 Damage HB HB-
- wedge 16 Damage
wedge 16 Damage
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 7
HE + at Minsk HE + at Minsk HE + at Minsk
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 8
Megatile design, top view Megatile Megatile design, top view design, top view
Components are the machined scintillator plates, cover plates, fiber assembly (WLS spliced to clear fiber, optical connector) pigtails
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 9
Megatile cross-sectional view Megatile Megatile cross cross-
- sectional
sectional view view
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 10
Protvino - Pig Tail QC Protvino Protvino -
- Pig Tail QC
Pig Tail QC
RMS of the light yield transmission is less than 5%.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 11
Megatile Manufacture -HE Megatile Megatile Manufacture Manufacture -
- HE
HE
10 megatiles/day at Protvino
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 12
HB Megatile Production HB Megatile Production HB Megatile Production
CMS HCAL Production
18 36 54 72 90 108 126 144 162 180 198 216 234 252 270 288 306 324 342 360 378 396 414 432 450 468 486 504 522 540 558 576 594 612 630
week of
Mega tiles
Scintillator "Goal" Final Assy. "Goal" Covers "Goal" Scintillator Machined Covers Machined Completed Megatiles
18 megatiles per layer 17 layers per wedge 18 wedges per HB 2 HB's
80% 490 tiles 90% 551 tiles 100% 612 tiles
P r e pa r e d by: T odd Ne be lweek ending 09/30/01
( HB+ / HB-) HB- left Scint=576 94% (1 00% / 88%) 1 2% left Co ver=61 2 1 00% (1 00% / 1 00%) 0% left Tile=573 94% (1 00% / 88%) 1 2% left
L09 Delay for Quartz fiber
Scheduled to be completed end of 01. Total labor estimate ~ 1.8 M$
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 13
Installation at CERN Installation at CERN Installation at CERN
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 14
Optics Factory at FNAL Optics Factory at FNAL Optics Factory at FNAL
- HB Optics factory in final phase. Will be
finished in 2 weeks.
- Reduce staffing from 13 to 5.
- Factory will redirect to work on
components for RBX’s, HV, LV, electronics components.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 15
HPD Delivery Schedule HPD Delivery Schedule HPD Delivery Schedule
Letter of Intent received by DEP Oct 12, 01 Spare Tubes (20) Dec 20, 01 Spare Tubes (30) Mar 1, 02 HB- (72) May 12, 02 HE- (72) Aug 23, 02 HB+ (72) Nov 3, 02 HE+ (72) Jan 28, 03 HO (146) Jun 23, 03 So far, 20 at Minnesota. ~ on schedule First Production HPD
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 16
HPD Anti-Reflective Coating HPD Anti HPD Anti-
- Reflective Coating
Reflective Coating
3 layer coating on top of HPD Diode.
100 nm A l A l A l kapton
Aluminum with no anti-reflective coating New Diode Structure
Bias Voltage
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 17
RBX Status RBX Status RBX Status
- HB RBX in production (Mississippi).
Should be complete by April 02.
- ODU’s for HB complete (Notre Dame) 2-
3% rms.
- HE RBX in design. Design should be
complete by April 02
- Production of HE RBXs late spring
- HE ODUs to be built in ND factory in
summer.
- Design HO RBX. Build over summer
- HO ODUs in fall (ND)
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 18
HB RBX Assembly HB RBX Assembly HB RBX Assembly
Full RBX with 19 ch RMs RBX Interior -- HV distributor and backplane
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 19
Readout Module (RM) Overview Readout Module (RM) Readout Module (RM) Overview Overview
I N T E R F A C E B O A R D
H P D
ODU
FIBERS In
6 CHANNEL FRONT END READOUT CARD
12 COAX HV CABLE 12 COAX 12 COAX
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 20
RBX Readout Module RBX Readout Module RBX Readout Module
Interface Card HPD Mount
- The readout module (RM) integrates the HPD, front end electronics,
and digital optical drivers.
Electronics cards HV Optical Sorter ODU
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 21
ODU production at Notre Dame ODU production at Notre ODU production at Notre Dame Dame
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 22
ODU QC ODU QC ODU QC
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 23
FE/DAQ Readout FE/DAQ Readout FE/DAQ Readout
QIE QIE QIE QIE QIE QIE CCA CCA CCA TX TX
Shield Wall
C P U D C C H T R H T R H T R H T R H T R H T R LEVEL 1 TRIGGER TTC DDU/FED HPD
CONTROL MODULE FE READOUT MODULE
VR 1600 Mbit/s
L1 Accept
1 Gbit/s 16 1600Mbit/s fiber per HTR
18 HTRs per HCAL Readout Crate
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 24
FE Channels FE Channels FE Channels
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 25
FE Status FE Status FE Status
Past 6 months
- Tested proto CCA Asic – looks good
- Tested proto QIE Asic
- Does not run at 40MHz (easy fix)
- Noise levels under study
- 3000e- rms with soldered coax connections btw HPD
and QIE
- HB Backplane layout complete
- Proto GOL (serializer) tested - OK
- Gigabit Ethernet protocol
- 1600 Mbits/s
- Proto VCSEL and custom package tested – ok
- Rad qualified “glue” logic parts
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 26
CMS QIE Status CMS QIE Status CMS QIE Status
Full chip submitted 3/13/01 Received 5 wafers 6/1/01 Testing shows chip fully functional
- Chip does not run at 40 MHz
- Noise as a function of input capacitance being
studied
- Noise of 3000e- rms achieved with soldered
coax connections btw HPD and QIE
Goal is to submit production part by April ‘02
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 27
CCA Status CCA Status CCA Status
CCA submitted June 25, 2001 25 parts back Oct 11, 2001 Chips under test
- Problem with reads/writes to internal registers
- Problem with writes fixed with repair on chip
(jumped out inverter)
- Problem with reads under study
- Other than reads, the CCA appears to be fully
functional
Engineering run chip submitted on Feb
- 11. Due back April 8.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 28
CCA ASIC Repair CCA ASIC Repair CCA ASIC Repair
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 29
Radioactive Source Vertical Slice Radioactive Source Vertical Radioactive Source Vertical Slice Slice
- Exercise a single channel of HCAL readout
from scintillator to computer
- Radioactive Source
- Scintillator
- Optical Fiber
- HPD
- QIE
- Digital optical readout
- HTR
- DCC
- Computer
- First complete ~40Mhz readout of HCAL
Channel
- Successful demonstration of radioactive
source measurement for calibration.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 30
QIE under test QIE under test QIE under test
QIE
Test
Board
TTCrx
Clock distributor
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 31
DAQ System DAQ System DAQ System
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 32
Radioactive Source Test Radioactive Source Test Radioactive Source Test
Shift of 180 electrons
Response as source is removed from scintillator
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 33
HF Status HF Status HF Status
- 10 HF absorber wedges finished. 5 at
CERN
- Fiber ordered. First delivery to CERN
- Phototubes ordered.
- Expect first complete wedge (fibers,
pmts) at CERN in early June 02.
- Expect to test in H2 test beam this
summer.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 34
First Production HF Wedge First Production HF Wedge First Production HF Wedge
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 35
Idea to use HO for muon trigger, vertical slice trigger Idea to use HO for Idea to use HO for muon muon trigger, vertical slice trigger trigger, vertical slice trigger
Expect ~ 2 p.e.
- f noise and ~ 8
p.e. of signal for a single muon at normal incidence.
Toy montecralo with 5000 e- noise, 8 pe/mip in HO
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 36
Testbeam Motivation Testbeam Testbeam Motivation Motivation
- HB- assembled in September 01
- HB+ will be assembled in September 02
- Only chance for testing production
wedges with fast (engineering run ASICS) electronics is Summer 02.
- Desire to test 2 to 4 production wedges
from HB+.
- Get absolute calibrations to carry from
H2 to UX5.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 37
Testbeam Goals Testbeam Testbeam Goals Goals
- Prepare test beam DAQ to read out prototype
HTR cards.
- Electronics will be 6-channel RBX cards,
using first run QIE and engineering run CCA. GOL and fiber-optic readout.
- Rochester ECAL module on table, with new
motion mechanism.
- Take ~ 4 production wedges into beam.
- Measure radioactive source fingerprints.
- Scan with pions as function of eta and phi.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 38
Testbeam Responsibilities Testbeam Testbeam Responsibilities Responsibilities
- H2 Test beam beamline, DAQ – Laza
- RBX FE cards – Terri Shaw
- RBX mechanics, optics – Randy Ruchti
- Check out / test RBX’s – Anatoly Ronzhin
- System integration FE card to HTR – Jim
Rohlf
- Radioactive source system – Virgil
- Calibration System --Vasken, Sergey Los
- Refurbish table – George Ginther
- ECAL Module, new motion – Pawel
- HV System – Sergey Los
- HPD checkout and setup – Arjan Heering
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 39
Testbeam Conclusions Testbeam Testbeam Conclusions Conclusions
- Test Beam 2002 very important goal for
HB group.
- Only chance to test production wedges
- Important step in system integration in
preparation for SX5 activities in late 02, early 03.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, 2002 40
Conclusions Conclusions Conclusions
- HCAL absorber and optics making good
progress
- Front end and Higher level electronics
progressing
- Finished with absorber, optics.
- HPDs under control
- ASICs under control
- HF fibers and pmts ordered.
- Looking forward to test beams in summer 02
- Install electronics Spring 03
- Vertical Slice Tests in SX5 in 03