hamilton wetland hamilton wetland
play

HAMILTON WETLAND HAMILTON WETLAND Steve Crooks Geomorphology - PDF document

Adaptive Restoration of the West Coast's Tidal Wetlands Tom Gandesbery Presentation Team Members HAMILTON WETLAND HAMILTON WETLAND Steve Crooks Geomorphology lead, Phil Williams RESTORATION RESTORATION and Associates Bruce


  1. Adaptive Restoration of the West Coast's Tidal Wetlands Tom Gandesbery Presentation Team Members HAMILTON WETLAND HAMILTON WETLAND • Steve Crooks – Geomorphology lead, Phil Williams RESTORATION RESTORATION and Associates • Bruce Pavlik - Botany and Ecology, Independent PROJECT PROJECT Consultant • Eric Jolliffe - Staff Biologist, USACOE ~~~ A Work In Progress • Jay Kinberger - Project Manager, USACOE • Edgar Salire - Soils Engineer, USACOE • Bill Rudolph - Soils Enginner, Consultant to SCC Tom Gandesbery • Eric Polson - Civil Engineer, Consultant to SCC State Coastal Conservancy • Bill Firth - Hydrologist, USACOE Sonoma Sonoma Baylands Baylands Hamilton Landscape level design Project is 3 Properties = Bel Marin Keys Homes 2600 acres BMK V 1600 ac - Owned by NAF ~200ac SCC Owned by SLC Airfield 622ac -Owned by SCC Coastal Training Program Elkhorn Slough and SF Bay National Estuarine Research Reserve January 12, 2006 1

  2. Adaptive Restoration of the West Coast's Tidal Wetlands Tom Gandesbery Presentation From the North LTMS ~ Hamilton Link Partners involved in: Pre-project planning (Since 1993) legislation (federal and state) Stakeholder Involvement (Local Gov and NGO) = Collaboration (Work between agencies) Maritime Interest groups Hamilton Partners: California Coastal Conservancy San Francisco Bay Conservation & Development Commission (BCDC) U.S. Army Corps of Engineers LTMS Strategy Multiple Objectives LTMS Program EIS/EIR (1994) and ROD (1999) Disposal and Reuse Goal of 40/40/20 1. Marsh Restoration using Dredged Sediment 20-Year Planning Horizon ( � LTMS) 40% Ocean Disposal 40% Reuse 2. Tidal Marsh Habitat benefiting Endangered Species 20% In-Bay How Will We Get There? How Will We Get There? � North Bay Restoration Initiative (see map) Transition Period Transition Period Habitat Linkages 8.0 Existing Disposal Limit Wet Year Millions of Cubic Yards/Year USFWS / DGS Refuge System 7.0 Existing Disposal Limit Dry Year 6.0 COE 5.0 Medium Small 4.0 3. Well Planned Reuse of Military Lands 3.0 2.0 � BRAC No-Cost Conveyance to SCC 1.0 0.0 (Hamilton) 1999-2001 2002-2004 2005-2007 2008-2010 After 2010 North Bay Project Potential Coastal Training Program Elkhorn Slough and SF Bay National Estuarine Research Reserve January 12, 2006 2

  3. Adaptive Restoration of the West Coast's Tidal Wetlands Tom Gandesbery Presentation Design Objectives Creation of 3 habitat types tidal wetlands seasonal wetlands uplands To benefit an array of species endangered (saltmarsh harvest mouse, clapper rail) shorebirds (e.g. greater yellowlegs, long-billed curlew) local wildlife (e.g. marsh hawk, voles, butterflies) With minimal long-term maintenance Hamilton Wetlands Restoration Total Project Conceptual Project Design • Scan pdf Authorized in WRDA 1999 - $55,200,000 • Purpose: Ecosystem and Wetlands Restoration • Restores approximately 990 acres of habitat including: – 570 Acres of Coastal Salt Marsh – 120 Acres of tidal channels and intertidal habitats • Accommodates approximately 10.6MCY of dredged material • 13 years of Adaptive Management Post Breach • Complete Restoration – 20 Years Regardless of the availability of dredged material, the bay ward levee breach would be completed no later than 8 years after initiation of site preparation to ensure that marsh establishment would not be delayed Baylands Before And After PS Marina in better days Coastal Training Program Elkhorn Slough and SF Bay National Estuarine Research Reserve January 12, 2006 3

  4. Adaptive Restoration of the West Coast's Tidal Wetlands Tom Gandesbery Presentation Habitat Types at Hamilton Hamilton Site Template Hamilton Site at 10 Years Hamilton Site at 50 Years Summary of Costs Total Project Conceptual Total Project Design • Scan pdf Total Combined Cost……….……$281,400,000 Federal ...………..…..$221,600,000 Project Share………..……..$128,200,000 O&M Share……………..……$76,900,000 Oakland -50’ Project Share….$16,500,000 Non-Federal..…………$59,800,000 Sponsor Share…………..…..$42,800,000 Non-Fed O&M Share………..$11,500,000 Oakland 50’ Project Share…...$5,500,000 Annual O&M (project life)……..$886,000 Coastal Training Program Elkhorn Slough and SF Bay National Estuarine Research Reserve January 12, 2006 4

  5. Adaptive Restoration of the West Coast's Tidal Wetlands Tom Gandesbery Presentation Regulatory Actions Progress 3 Major Phases • Final RAP for Airfield (DTSC and RWQCB) • For Airfield • Includes SEIR Comments (SCC) – Built 3 out of five levee segments • Site Cleanup Requirements to Army (RWQCB) – Seasonal Wetland Design ~50% complete • Waste Discharge Requirements (RWQCB) to Army and – Trail plan complete SCC Covers all aspects of wetlands project – DM placement cells for first phase compete • Section 7 ESA for Construction and Project (USFWS) • Section 7 ESA for Offloader (NMFS) – DM placement scheduled to start fall of 2006 • Consistency Determination includes Offloader (BCDC) – 2005 Permits that require monitoring Antenna Field Status BMKV Status 190 Acres Elements to Authorization of BMKV portion have been completed: ~ 30 Acres in southeast corner used for: � Supplemental EIS/EIR for Bel Marin Keys Unit V Shooting range � Completed December 2002. Antenna field � General Reevaluation Report (GRR) a revision to the FS Burn Pits (fire training, etc) � Draft Chief’ Report written Spot Removals completed in 1990s Clean-up Plans in a regulatory “process” � Revised Cost Estimates After remediation, restored as Phase II or III of the project Pending Corps Headquarters approval Toxics Remediation Public Access This is Another Workshop! This is another Workshop! • Done by Army / Navy BRAC • Trail will run western parameter of site • 1990s - BRAC work within Hamilton • To BMK Blvd North and connect to ? South • User –wildlife interaction • Contaminants typical of an large airport – Nesting birds most sensitive • $70 Million plus soil no groundwater • Sophisticated Trail Design (Mixture of cable fencing,moat, signage, elevation) • Cleanup complete this FY • Cleanup plan adopted 2003 Required monitoring • Low level (residual) DDT in soil – Methods? – Applicable to Adaptive Management • Coastal Training Program Elkhorn Slough and SF Bay National Estuarine Research Reserve January 12, 2006 5

  6. Adaptive Restoration of the West Coast's Tidal Wetlands Tom Gandesbery Presentation Site is subsided show cross The Project at HAAF sect Habitat Upland Tidal wetland Seasonal wetland Goal local wildlife endangered species shorebirds migratory species Physical corridor tidal action tidal inundation corollaries restricted access sedimentation ppt inputs escape terrain channel network/form high soil salinity Vegetation native overstory Salicornia open pannes, mixed understory stressed Salicornia, matrix of native wetland Challenges weeds design template design w/ man options inund/salinity regime weeds Uncertainty low low to moderate high Target salinity/inundation regime is narrow seasonal wetland target Seasonal Wetland Design stressed Salicornia Soil Salinity (dS/m) inundated exposed Salicornia brackish marsh freshwater marsh upland Inundation (months) Who performs Adaptive Management ? Adaptive Management Working Group (AMWG) composed of: scientists* - specialists in monitoring & restoration regulators - agency representatives private interests - local business & user groups stewards* - resource owners & managers *Technical Advisory Group (TAG) (regulatory mechanism) Coastal Training Program Elkhorn Slough and SF Bay National Estuarine Research Reserve January 12, 2006 6

  7. Adaptive Restoration of the West Coast's Tidal Wetlands Tom Gandesbery Presentation Hamilton AMMP High Priorities for Monitoring Physical We’re Working on it…… Placed sediment elevation ( No overfilling!) June? Levee erosion and stability (flood control) • 2002 SEIR and Draft ADMP Plan (Appendix K) Channel development • It outlines: Hydrology inside and outboard • Goals • Objectives Chemical Measures of Progress (“success”?) MeHg (Corps, Calfed) Physical Conventionals and sediment (e.g. redox) Chemical Biological Biological Other benefits Bird use > Public and community “ownership” of project Clapper rail and SMH Mouse > Further the scientific understanding of wetlands Fish use HAAF ADAPTIVE MANAGEMENT CYCLES Strategy y t i l a u Design Decision q Design e c r Adaptive Management: u o Monitoring specific s e to objectives, uncertainties r Evaluation Evaluation Implementation salinity, indundation, veg, birds Monitoring time Modified from Sit and Taylor 1998 Allowable under Corps CW Rules Monitoring Feasibility • Methods and approach must be cost effective, • What can $ be spent on? comparable and generally accepted within the scientific community – Corps will carryout AMM for 13 years after completion of each seperable unit (breach) • Project funding vs. Science – Terminology important to Federal Gov’t – Process requires that the Corps give the sponsor an • Better when tied to regional efforts O&M manual. – Methodology, timing and funding – Role of NGO or other third party? – PM need control of deliverables – Federal contracting rules >>> look back at early partners and funders Coastal Training Program Elkhorn Slough and SF Bay National Estuarine Research Reserve January 12, 2006 7

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend