GTA East Local Advisory Committee Introductory Meeting March 10, - - PowerPoint PPT Presentation

gta east
SMART_READER_LITE
LIVE PREVIEW

GTA East Local Advisory Committee Introductory Meeting March 10, - - PowerPoint PPT Presentation

GTA East Local Advisory Committee Introductory Meeting March 10, 2016 Presentation Outline Role of the Local Advisory Committee Regional Electricity Planning Process Summary of Findings from Regional Planning Activities in GTA


slide-1
SLIDE 1

GTA East Local Advisory Committee Introductory Meeting

March 10, 2016

slide-2
SLIDE 2
  • Role of the Local Advisory Committee
  • Regional Electricity Planning Process
  • Summary of Findings from Regional Planning

Activities in GTA East

  • Engaging the Community on a Long-Term Electricity

Strategy for the Region

  • Discussion

Presentation Outline

2

slide-3
SLIDE 3

3

ROLE OF THE LOCAL ADVISORY COMMITTEE

3

slide-4
SLIDE 4
  • Provide input on planning initiatives and priorities

(economic development, downtown intensification, community energy plans, etc. ) in the GTA East Regional area

  • Share information on local electricity supply preferences
  • Provide input in the design of engagement approaches

related to regional electricity planning

Role of the Local Advisory Committee

slide-5
SLIDE 5

Meetings are a Forum for Information Sharing

  • Updates on progress and results from the Pickering

Ajax Whitby Area Working Group

  • A venue for a broader energy dialogue and a bridge

between regional planning cycles for the region

slide-6
SLIDE 6

Planning and Engagement – Timeline

6 Scoping Assessment IESO (90 days to complete) Start IRRP Pickering

  • Ajax-

Whitby Municipal Meetings Establish LAC for Region First LAC Meeting Second LAC Meeting IRRP Posted Continue work on planning for long- term needs Needs Screening Hydro One (60 days to complete)

slide-7
SLIDE 7

REGIONAL ELECTRICITY PLANNING PROCESS

7

slide-8
SLIDE 8

A Typical Electric Power System

8

slide-9
SLIDE 9

Key Participants in Ontario’s Electricity Sector

9

Ontario Energy Board

Ontario Electricity System and its Customers

Regulation Generation Distribution Transmission System Operation, Planning and Procurement

Hydro One, Great Lakes Power Transmission, Five Nations and others Local Distribution Companies (LDCs), Hydro One Distribution and other distribution customers Ontario Power Generation (OPG) and other generators Ministry of Energy

slide-10
SLIDE 10
  • A process for identifying and addressing local electricity needs
  • Link between provincial bulk system planning (led by the IESO) and local

distribution system planning (led by LDCs)

  • Objective of maintaining a safe, reliable and economic electricity supply
  • Operates in the context of existing criteria and frameworks

– Applies the IESO’s reliability standards – Aligns with provincial/municipal planning policies, and where possible, with local interests

  • Either an integrated approach (considers conservation, generation, wires

and other innovative solutions) led by the IESO, for studies with more expansive needs; or for studies with “wires only” solutions, led by Hydro One or other Transmitters.

What is Regional Electricity Planning?

10

slide-11
SLIDE 11

Context for Regional Electricity Planning

slide-12
SLIDE 12

Overview of the Electricity Planning Process

12

Process Outcomes Planning

Implementation

Decision Making Community Engagement

  • Data gathering
  • Technical studies
  • Options for integrated

solutions

  • Trigger projects to address

near-term needs Dialog with community members on options to address longer-term needs Working group recommendations based on planning criteria and consideration of community input

  • Needs Screening,

and/or IRRP

  • Identification of

needs and options A plan consisting of wires project(s) and/or non-wires alternatives Input on preferences for longer-term electricity supply

  • ptions
  • Regulatory approvals for

wires projects

  • Programs, procurement or
  • ther mechanisms for non-

wires alternatives Solutions are in place in time to meet the Region’s electricity needs

slide-13
SLIDE 13

GTA East Region

13

slide-14
SLIDE 14

The primary power system facilities serving this region are Pickering NGS and four 500 / 230 kV transformers at Cherrywood TS. Load in south Durham Region is almost 900 MW, growing at about 1% to 1.5% per year.

slide-15
SLIDE 15

15

Transformation relief required for Cherrywood TS once Pickering NGS retires. Local supply reliability in the area also needs improvement. Transformation relief required for Cherrywood TS once Pickering NGS retires. Local supply reliability in the area also needs improvement.

slide-16
SLIDE 16

16

Clarington TS relieves overloads at Cherrywood TS and also provides local reliability improvements. Clarington TS relieves overloads at Cherrywood TS and also provides local reliability improvements.

slide-17
SLIDE 17

The GTA East Region

17

  • This Area is supplied

primarily by Pickering NGS and four 500/230 kV transformers at Cherrywood TS

  • Sources of local supply

include: – Renewable FIT and microFIT – CHP, EFW

  • Peak electricity demand

for the region was about 770 MW (summer peaking) in 2015

  • This region is expected

to continue developing as targets for the greater golden horseshoe are pursued

slide-18
SLIDE 18

Background

  • The Regional Participants have been examining the electrical needs

in the GTA East Region since 2014.This group consists of the Independent Electricity System Operator (IESO), Hydro One Networks (Transmission and Distribution), Veridian Connections Inc, Whitby Hydro Electric Corporation and Oshawa PUC Networks Inc.

  • The Region was divided into two sub-regions: Pickering-Ajax-Whitby

and Oshawa-Clarington based on the types of needs identified:

– Needs in the Oshawa-Clarington sub-region were assessed by a Hydro One led Local Planning Working Group in 2015. This report is now complete and can be found on Hydro One’s website – An Integrated Regional Resource Plan (IRRP) for the Pickering-Ajax-Whitby Area is currently underway. This plan will assess the needs and recommend integrated solutions to meet the identified needs.

  • The recommendations resulting from these planning processes lay

the foundation for continued planning to address future needs as they arise.

18

slide-19
SLIDE 19

Local Planning for the Oshawa-Clarington sub-region

19

  • Local Planning Report for

this sub-region was completed by Hydro One in May 2015

  • A new transformer station

is recommended for the area to address near- term capacity needs

  • An agreement between

Oshawa Hydro, Hydro One Distribution and Hydro One Transmission is under development for this transformer station.

slide-20
SLIDE 20

Integrated Planning for the Pickering-Ajax- Whitby Area

Near-Term Needs

  • CAPACITY: Additional

transformer capacity required to be in-service by 2018 to support urban and Greenfield growth in Pickering

  • RESTORATION: Rationale

for meeting restoration criteria for rare failure events

20

slide-21
SLIDE 21

Integrated Planning for the Pickering-Ajax- Whitby Area

Options Considered for Meeting Capacity Needs 1. A new transformer station near the community of Seaton and reinforcement of existing line 2. New 27.6 kV distribution feeders from other transformer stations 3. A combination of the above

21

slide-22
SLIDE 22

22

slide-23
SLIDE 23

23

slide-24
SLIDE 24

24

Integrated Planning for the Pickering-Ajax- Whitby Area

Details of Option 1-Reinforcement of Existing Circuits

Existing tower type: single circuit Approximate portions of circuit to be reinforced (dependent on the preferred site)

slide-25
SLIDE 25

Integrated Planning for the Pickering-Ajax- Whitby Area

Options Considered for Restoration 1. Do Nothing, because the risk does not justify the cost. 2. Establish distribution infrastructure and process for transferring load between distribution stations during these unlikely failure events. 3. Install remote control motorized switches on the 230 kV circuits to isolate the faults from the rest of the Region’s system.

25

slide-26
SLIDE 26

Integrated Planning for the Pickering-Ajax- Whitby Area

Status of Near-Term Needs and Options

  • Capacity:

– Economic analysis comparing the three different options is complete, and a new 230/27.6 kV transformer station which is

  • ption 1 is recommended

– Given the near-term nature of the need, implementation of the recommendation is under development

  • Restoration:

– Economic analysis is underway to compare the cost and benefits

  • f the status quo versus motorized switches or distribution load

transfers – Results of this analysis to be shared at the next LAC meeting

26

slide-27
SLIDE 27

The GTA East Region - Plan for Meeting Near term Growth

27

  • Continued implementation of conservation and distributed

generation initiatives

  • Implementation of the near-term solutions for new transformer

stations in the Pickering-Ajax-Whitby and Oshawa-Clarington areas

  • The regional participants will work with the LAC, municipal

planners, other communities and stakeholders to establish long terms needs and local preferences on options to supply longer term electrical demand.

  • This input will help shape the mid and long term elements of this

IRRP

slide-28
SLIDE 28

Approaches to Addressing Longer-Term Needs

28

Conservation & Small-Scale, Distributed Resources Larger, Localized Generation Wires

Deliver Provincial Resources Community Self-Sufficiency

Final plan may have elements from each

  • f the approaches

Centralized Local Resources

slide-29
SLIDE 29
  • Energy Efficiency: switching to more efficient lights and

appliances

  • Automation: Increasing use of technology to automate energy

management based on customer preferences (Intelligent thermostats, smart plugs, smart charging for electric vehicles…)

  • More user friendly and timely reporting: Customers expecting

more user friendly and timely information and tips relating to energy management

  • Behaviour Modification: Exploring pricing rate structure other

than TOU to promote customer behaviour modification

Community Self Sufficiency: Conservation and Demand Management

29

slide-30
SLIDE 30
  • Combined Heat and Power/

District Energy

  • Rapidly reducing costs of

renewables and storage -> Residential and commercial solar+storage solutions

  • Technological innovations -

> Microgrids could enable more local demand reduction and local generation options

Community Self Sufficiency: Distributed Energy Resources

30

slide-31
SLIDE 31

Considerations for the mid to longer-term

  • The IRRP must consider factors that could impact the future electricity

demand in the Region. The plan will also need to consider the community’s interests and goals in supplying future electricity demand. Some factors that could impact electricity demand in the mid to long-term in the Region:

  • Continued intensification and development of industrial and Greenfield

lands

  • Electrification of mass transit
  • Retirement of Pickering GS

Are there other items that should be considered? – strategic growth plans, community energy plans, economic development discussions, update to Official Plans?

31