GTA East Local Advisory Committee Introductory Meeting
March 10, 2016
GTA East Local Advisory Committee Introductory Meeting March 10, - - PowerPoint PPT Presentation
GTA East Local Advisory Committee Introductory Meeting March 10, 2016 Presentation Outline Role of the Local Advisory Committee Regional Electricity Planning Process Summary of Findings from Regional Planning Activities in GTA
March 10, 2016
Activities in GTA East
Strategy for the Region
2
3
3
(economic development, downtown intensification, community energy plans, etc. ) in the GTA East Regional area
related to regional electricity planning
Ajax Whitby Area Working Group
between regional planning cycles for the region
6 Scoping Assessment IESO (90 days to complete) Start IRRP Pickering
Whitby Municipal Meetings Establish LAC for Region First LAC Meeting Second LAC Meeting IRRP Posted Continue work on planning for long- term needs Needs Screening Hydro One (60 days to complete)
7
8
9
Ontario Energy Board
Ontario Electricity System and its Customers
Regulation Generation Distribution Transmission System Operation, Planning and Procurement
Hydro One, Great Lakes Power Transmission, Five Nations and others Local Distribution Companies (LDCs), Hydro One Distribution and other distribution customers Ontario Power Generation (OPG) and other generators Ministry of Energy
distribution system planning (led by LDCs)
– Applies the IESO’s reliability standards – Aligns with provincial/municipal planning policies, and where possible, with local interests
and other innovative solutions) led by the IESO, for studies with more expansive needs; or for studies with “wires only” solutions, led by Hydro One or other Transmitters.
10
12
Process Outcomes Planning
Implementation
Decision Making Community Engagement
solutions
near-term needs Dialog with community members on options to address longer-term needs Working group recommendations based on planning criteria and consideration of community input
and/or IRRP
needs and options A plan consisting of wires project(s) and/or non-wires alternatives Input on preferences for longer-term electricity supply
wires projects
wires alternatives Solutions are in place in time to meet the Region’s electricity needs
13
The primary power system facilities serving this region are Pickering NGS and four 500 / 230 kV transformers at Cherrywood TS. Load in south Durham Region is almost 900 MW, growing at about 1% to 1.5% per year.
15
Transformation relief required for Cherrywood TS once Pickering NGS retires. Local supply reliability in the area also needs improvement. Transformation relief required for Cherrywood TS once Pickering NGS retires. Local supply reliability in the area also needs improvement.
16
Clarington TS relieves overloads at Cherrywood TS and also provides local reliability improvements. Clarington TS relieves overloads at Cherrywood TS and also provides local reliability improvements.
17
primarily by Pickering NGS and four 500/230 kV transformers at Cherrywood TS
include: – Renewable FIT and microFIT – CHP, EFW
for the region was about 770 MW (summer peaking) in 2015
to continue developing as targets for the greater golden horseshoe are pursued
in the GTA East Region since 2014.This group consists of the Independent Electricity System Operator (IESO), Hydro One Networks (Transmission and Distribution), Veridian Connections Inc, Whitby Hydro Electric Corporation and Oshawa PUC Networks Inc.
and Oshawa-Clarington based on the types of needs identified:
– Needs in the Oshawa-Clarington sub-region were assessed by a Hydro One led Local Planning Working Group in 2015. This report is now complete and can be found on Hydro One’s website – An Integrated Regional Resource Plan (IRRP) for the Pickering-Ajax-Whitby Area is currently underway. This plan will assess the needs and recommend integrated solutions to meet the identified needs.
the foundation for continued planning to address future needs as they arise.
18
19
this sub-region was completed by Hydro One in May 2015
is recommended for the area to address near- term capacity needs
Oshawa Hydro, Hydro One Distribution and Hydro One Transmission is under development for this transformer station.
Near-Term Needs
transformer capacity required to be in-service by 2018 to support urban and Greenfield growth in Pickering
for meeting restoration criteria for rare failure events
20
Options Considered for Meeting Capacity Needs 1. A new transformer station near the community of Seaton and reinforcement of existing line 2. New 27.6 kV distribution feeders from other transformer stations 3. A combination of the above
21
22
23
24
Details of Option 1-Reinforcement of Existing Circuits
Existing tower type: single circuit Approximate portions of circuit to be reinforced (dependent on the preferred site)
Options Considered for Restoration 1. Do Nothing, because the risk does not justify the cost. 2. Establish distribution infrastructure and process for transferring load between distribution stations during these unlikely failure events. 3. Install remote control motorized switches on the 230 kV circuits to isolate the faults from the rest of the Region’s system.
25
Status of Near-Term Needs and Options
– Economic analysis comparing the three different options is complete, and a new 230/27.6 kV transformer station which is
– Given the near-term nature of the need, implementation of the recommendation is under development
– Economic analysis is underway to compare the cost and benefits
transfers – Results of this analysis to be shared at the next LAC meeting
26
27
generation initiatives
stations in the Pickering-Ajax-Whitby and Oshawa-Clarington areas
planners, other communities and stakeholders to establish long terms needs and local preferences on options to supply longer term electrical demand.
IRRP
28
Conservation & Small-Scale, Distributed Resources Larger, Localized Generation Wires
Deliver Provincial Resources Community Self-Sufficiency
Final plan may have elements from each
Centralized Local Resources
appliances
management based on customer preferences (Intelligent thermostats, smart plugs, smart charging for electric vehicles…)
more user friendly and timely information and tips relating to energy management
than TOU to promote customer behaviour modification
29
District Energy
renewables and storage -> Residential and commercial solar+storage solutions
> Microgrids could enable more local demand reduction and local generation options
30
demand in the Region. The plan will also need to consider the community’s interests and goals in supplying future electricity demand. Some factors that could impact electricity demand in the mid to long-term in the Region:
lands
Are there other items that should be considered? – strategic growth plans, community energy plans, economic development discussions, update to Official Plans?
31