Local Advisory Committee Meeting #2 May 4, 2016 Presentation - - PowerPoint PPT Presentation

local advisory committee
SMART_READER_LITE
LIVE PREVIEW

Local Advisory Committee Meeting #2 May 4, 2016 Presentation - - PowerPoint PPT Presentation

GTA East Local Advisory Committee Meeting #2 May 4, 2016 Presentation Outline Review of items from the last meeting Capacity Needs in GTA East Status of Restoration Analysis Pickering-Ajax-Whitby IRRP - What you can expect


slide-1
SLIDE 1

GTA East Local Advisory Committee Meeting #2

May 4, 2016

slide-2
SLIDE 2
  • Review of items from the last meeting – Capacity

Needs in GTA East

  • Status of Restoration Analysis
  • Pickering-Ajax-Whitby IRRP - What you can expect

in the near-term portion of the Plan

  • Discussion of Priorities for the Mid and Long Term

Presentation Outline

2

slide-3
SLIDE 3
  • The Region is broken down into two sub-regions:

– Oshawa-Clarington – Pickering-Ajax-Whitby

  • Oshawa-Clarington:

– A new transformer station is recommended for the area to address near-term capacity needs

  • Pickering-Ajax-Whitby:

– Additional transformer capacity required to be in-service by 2018 to support urban and greenfield growth in Pickering – Rationale for meeting restoration criteria for rare failure events to be investigated

Review of Needs in GTA East

3

slide-4
SLIDE 4

Review - Needs in GTA East

4

Approximate site of new transformer station

slide-5
SLIDE 5

5

230 kV Circuits from Cherrywood Transformer Station (H24/26C & M29/B23C)

slide-6
SLIDE 6

Single Line Diagram of the Study Area

6

Wilson TS Thornton TS Oshawa GM CTS Whitby TS Cherrywood TS

500kV 230kV 750MVA 500kV/230kV Autotransformers

Atlantic Packaging CTS Whitby CGS Gerdau CTS Clarington TS

500kV 230kV 750MVA 500kV/230kV Autotransformers

Bowmanville SS To Lennox TS

C28C H24C H26C M29C B23C

To Otonabee TS To Otonabee TS To Havelock TS To Almonte TS To BellevilleTS To Pickering SS (8 circuits)

slide-7
SLIDE 7
  • How much load can be “restored” in a certain

amount of time after an outage.

Restoration - What does it mean?

7

slide-8
SLIDE 8
  • LDCs generally have some amount of load transfer capability
  • available. This capability can include:

– Moving load to adjacent stations – Loading up feeders to their maximum ratings – Other actions

  • Direct connect customers account for 153 MW of load along the

H24C/H26C load pocket that cannot be restored via LDCs

  • After taking into consideration the load transfer capability of LDCs

in the area, two of the restoration timelines are currently not met: 30 minute and 4 hour timelines and consideration should be given to solutions

Restoration Status

8

slide-9
SLIDE 9
  • 1. Do Nothing

– The value of lost load is less than the cost of a system upgrade

  • 2. Increase Distribution Transfer Capability

– Provide additional load transfer capability between stations at the feeder level

  • 3. Installation of Motorized Disconnect Switches

– Segregate line sections to reduce the overall effect and probability of an outage

  • 4. A combination of 2 & 3

Overview of Restoration Options

9

slide-10
SLIDE 10
  • Considerations when comparing the costs of options:
  • The probability of an outage occurring
  • The location of an outage on the various segments
  • Risk introduced by the switches / solution
  • Other LDC operational value provided by low voltage transfers
  • Cost to customers of a long interruption

– Risk calculations indicate there is value in conducting detailed analysis of solutions

Options considerations

10

slide-11
SLIDE 11
  • There could be benefit in distribution or transmission

level infrastructure solutions

  • A comparison between these four options requires

detailed study between the transmission and distribution companies

  • Refinement of the restoration analysis and related

solution recommendations to be determined as part of the Regional Infrastructure Plan lead by Hydro One

Next Steps for the Restoration Analysis

11

slide-12
SLIDE 12
  • IRRP for the Pickering-Ajax-Whitby area is to be

completed by end of June 2016 according to regulatory timelines

– A near-term need for transformation capacity has been identified and a new station is recommended – Refinement of the restoration analysis and related solution recommendations will be determined in the Regional Infrastructure Plan for the Region to be led by Hydro One and expected to be complete in Q1 2017

Timeline and the near-term portion of the IRRP

12

slide-13
SLIDE 13

13

MID- AND LONG- TERM PRIORITIES

slide-14
SLIDE 14

LAC members are asked to provide feedback on the following questions to help shape the mid- and long-term priorities of the plan:

  • 1. Where are the key future growth areas in your communities, along with

the scope of the growth and timing, both residential and non-residential?

  • 2. What are your energy goals and objectives and is there a plan to achieve

them? For the communities, does your community have a community energy plan or other plan to address greenhouse gas emissions, climate change and extreme weather events?

  • 3. Can you share information on your policies and initiatives that will impact

energy use (i.e. electrification of transit etc.)?

LAC Member Discussion

14

slide-15
SLIDE 15

15

QUESTIONS