Geotechnical Desktop Study Borings >100 feet deep Water Well - - PowerPoint PPT Presentation

geotechnical desktop study
SMART_READER_LITE
LIVE PREVIEW

Geotechnical Desktop Study Borings >100 feet deep Water Well - - PowerPoint PPT Presentation

Geotechnical Desktop Study Borings >100 feet deep Water Well Logs Regional Geology Fault Mapping & Behavior Geotechnical Desktop Study Borings Identified >100 Feet Deep Faulting Grain Size Distribution Comparison Inverted Siphon


slide-1
SLIDE 1
slide-2
SLIDE 2

Geotechnical Desktop Study

slide-3
SLIDE 3

Geotechnical Desktop Study

Borings >100 feet deep Water Well Logs Regional Geology Fault Mapping & Behavior

slide-4
SLIDE 4

Borings Identified >100 Feet Deep

slide-5
SLIDE 5

Faulting

slide-6
SLIDE 6

Grain Size Distribution Comparison

slide-7
SLIDE 7

Inverted Siphon Hydraulic Analysis

slide-8
SLIDE 8

Comparison Projects

Mill Creek Drainage Relief Tunnel

  • Dallas, Texas
  • Diameter: 30’ and 35’
  • Length: 26,385’ (~5 mi)
  • Discharge: ~20,000 cfs

Waller Creek Tunnel

  • Austin, Texas
  • Diameter: 20’, 22’ & 26’
  • Length: 5600’ (~1 mi)
  • Discharge: ~8,500 cfs

San Antonio River Tunnel

  • San Antonio, Texas
  • Diameter: ~24’
  • Length: ~16356’ (~3 mi)
  • Discharge: ~6,700 cfs
slide-9
SLIDE 9

Regional Topography

slide-10
SLIDE 10

HCFCD Inverted Siphon Concept

slide-11
SLIDE 11

Methodology

  • Spreadsheet solves for two parameters
  • Darcy-Weisbach equation – Head loss equation
  • Swamee-Jain equation – Darcy friction coefficient ( f )
  • Approximation of implicit Colebrook-White equation
  • VB programming used in excel for iteration
slide-12
SLIDE 12

Design Parameters

  • Roughness coefficient (ks) = 0.001 ft

Project Parameter Value Mill Creek Drainage Relief Tunnel (MCDRT) – Dallas, TX Manning’s Roughness Coefficient 0.011 Waller Creek Tunnel (WCT) – Austin, TX Roughness coefficient (ks; ft) 0.001 San Antonio River Tunnel (SART) – San Antonio, TX Roughness coefficient (ks; ft) 0.002

  • Minor (Inlet & Outlet Losses) = 0.2 + 1.0 = 1.2 ft
  • Bend Loss = 0.006 per bend
  • No. of Bends per mile (1,000-ft radius) = 2.5
  • Kinematic Viscosity = 1.023 x 10-5 ft2/s
  • Sediment Deposition Depth = 5% of Tunnel Diameter
slide-13
SLIDE 13

Scenarios Analyzed

Diameter (ft) Differential Head (ft) Tunnel Length (mi) 5 30 5 10 40 10 15 50 15 20 60 20 25 70 25 30 80 30 35 90

  • 40

100

  • Diameter: 5’ intervals
  • Heads : 10’ intervals
  • Length: 5 mi intervals
slide-14
SLIDE 14

Validation

Project Actual Rated Capacities (cfs) Spreadsheet (cfs) Mill Creek, Dallas 20,000 (approx.) 19,831 Waller Creek, Austin 8,500 (approx.) 8,486 San Antonio River Tunnel 6,700 (approx.) 6,720

slide-15
SLIDE 15

Flow Rates for 10-mile Tunnel

Flow rate (cfs) Diameter (ft) Head (ft) 30 40 50 5

70 81 90

10

423 489 547

15

1,205 1,394 1,560

20

2,527 2,922 3,270

25

4,477 5,176 5,792

30

7,132 8,244 9,224

35

10,557 12,202 13,651

40

14,810 17,117 19,149

*Additional results in Appendix B

slide-16
SLIDE 16

Results

5 10 15 20 25 30 35 40 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Tunnel Diameter (ft) Flow (cfs)

FLOW RATE AT 50' HEAD

L = 5 mi L = 10 mi L = 15 mi L = 20 mi L = 25 mi L = 30 mi 5 10 15 20 25 30 35 40 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Tunnel Diameter (ft) Flow (cfs)

FLOW RATE AT 60' HEAD

L = 5 mi L = 10 mi L = 15 mi L = 20 mi L = 25 mi L = 30 mi 5 10 15 20 25 30 35 40 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Tunnel Diameter (ft) Flow (cfs)

FLOW RATE AT 30' HEAD

L = 5 mi L = 10 mi L = 15 mi L = 20 mi L = 25 mi L = 30 mi 5 10 15 20 25 30 35 40 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Tunnel Diameter (ft) Flow (cfs)

FLOW RATE AT 40' HEAD

L = 5 mi L = 10 mi L = 15 mi L = 20 mi L = 25 mi L = 30 mi

slide-17
SLIDE 17

Sensitivity Analysis

Parameter Range Minimum Design Maximum Roughness coefficient (ft) 0.0005 0.001 0.002 Minor loss (Entrance & Exit Losses) 0.2 +1.0 = 1.2 1.0+1.0 = 2.0 Bend Loss 0.006 (smooth bend) 0.02 (mitered bend)

  • No. of Bends per mile (1,000-ft radius)

2.5 5 Kinematic Viscosity (x 10-5, ft2/s) 0.93 1.023 1.86 Sediment Deposition (% of Tunnel Diameter) 5 10

Takeaways:

  • Surface roughness has the highest influence on the tunnel flow rate.
  • Sediment depth has the second most influence on the tunnel flow rate.
  • Other parameters interchangeably rank higher to lower depending on the differential head,

tunnel diameter, and length.

slide-18
SLIDE 18

Tunnel Applicability

slide-19
SLIDE 19

Face Support Methods for Shields and TBMs

slide-20
SLIDE 20

Pre-cast Concrete Segmental Lining Schematic

slide-21
SLIDE 21

TBM Launch Site

  • Site size > 5 acres
  • Shaft size = 2 to 2.5 OD
  • Haul routes considered
  • Power = 20 MW +/-
  • Noise screening

Fencing with Noise Barrier

slide-22
SLIDE 22

Third-party Impacts

  • The construction of large diameter flood control tunnel(s) will have a

significant impact on traffic and noise in the area surrounding the shaft sites

  • Truck traffic for a 40-foot diameter tunnel construction will require hundreds of truck trips each

work day.

  • Time of day restrictions are sometimes placed at shaft site locations that are

in a residential area.

  • Typical time of day restrictions may be 7:00 AM to 7:00 PM.
  • Tunnel construction below ground is pursued essentially 24 hours a day, 7

days a week.

  • Above the tunnel it will be difficult to to even notice that tunnel construction is taking place
slide-23
SLIDE 23

Typical TBM Progress Rates

  • For this planned flood control tunnel, we would recommend assumed

progress rates for initial planning purposes as follows:

  • 25-foot Diameter Tunnel

75 ft/day

  • 40-foot Diameter Tunnel

50 ft/day

  • The Anacostia River Tunnel which is a 23 -foot diameter soft ground tunnel

was constructed with an average daily progress rate of 80 ft/day and a maximum daily progress of 120 ft/day.

slide-24
SLIDE 24

Construction Packaging and Schedule

  • A planned flood control tunnel may exceed 10 miles in length and 40 foot in

diameter.

  • A tunnel project of this size is often broken up into several construction contracts.
  • Each contract would have one or more TBMs with individual TBM runs typically

being a few miles in length.

  • From discussions with tunnel contractors for planning purposes, an upper limit on

mining length with a single TBM before major mechanical rehabilitation is required is between 5 and 7 miles. This distance may be appropriate for breaking up longer tunnels into segments.

slide-25
SLIDE 25

Cost Analysis

Don, Wotring, PE, Brierley Associates Brian Gettinger, PE

F O R C O N C E P T U A L T U N N E L A U G U S T 2 9 , 2 0 1 9

presented by

slide-26
SLIDE 26

AACE Class 5 Cost Estimate

Accuracy Range Includes Contingency Contingency = 50%

Estimate Class Maturity Level1 Typical Estimate Purpose Typical Estimating Method Expected Accuracy Range2 Class 5 0% to 2% Concept screening SF factoring, parametric models, judgement, or analogy L: -20% to -30% H: +30% to +50%

slide-27
SLIDE 27

Cost Estimate

Shafts and In/Outlet Structures Mobilization and Bonding Other Allowances Contingency

Tunnel 44% 32% 13.5% 6% 3%

1.5%

Payment Items 25-ft Diameter (2019 millions USD) 40-ft Diameter (2019 millions USD) Project Subtotal $678.1 (65%) $1,005 (66%) Contingency (50%) $332.1 (32%) $492.7 (32%) Allowances $31.7 (3%) $31.7 (2%) Total $1,041 $1,530

Appendix B – 25-ft Diameter Tunnel Appendix C – 40-ft Diameter Tunnel Appendix D – Payment Items (32)

slide-28
SLIDE 28

Historical Project Comparison

Northeast Boundary Tunnel

slide-29
SLIDE 29

Phase 1 Conclusions

slide-30
SLIDE 30
  • 1. Tunneling in Harris County is feasible based on the geotechnical

conditions and project experience in similar soils

  • 2. Tunnels can move a significant rate of stormwater operating entirely

by gravity as an inverted siphon

  • 3. Tunnel cost including a 50% contingency for a representative 10-mile-

long, 25- and 40-foot diameter tunnel are $1 billion and $1.5 billion respectively

Phase 1 Outcomes