Geotechnical Desktop Study Borings >100 feet deep Water Well - - PowerPoint PPT Presentation
Geotechnical Desktop Study Borings >100 feet deep Water Well - - PowerPoint PPT Presentation
Geotechnical Desktop Study Borings >100 feet deep Water Well Logs Regional Geology Fault Mapping & Behavior Geotechnical Desktop Study Borings Identified >100 Feet Deep Faulting Grain Size Distribution Comparison Inverted Siphon
Geotechnical Desktop Study
Geotechnical Desktop Study
Borings >100 feet deep Water Well Logs Regional Geology Fault Mapping & Behavior
Borings Identified >100 Feet Deep
Faulting
Grain Size Distribution Comparison
Inverted Siphon Hydraulic Analysis
Comparison Projects
Mill Creek Drainage Relief Tunnel
- Dallas, Texas
- Diameter: 30’ and 35’
- Length: 26,385’ (~5 mi)
- Discharge: ~20,000 cfs
Waller Creek Tunnel
- Austin, Texas
- Diameter: 20’, 22’ & 26’
- Length: 5600’ (~1 mi)
- Discharge: ~8,500 cfs
San Antonio River Tunnel
- San Antonio, Texas
- Diameter: ~24’
- Length: ~16356’ (~3 mi)
- Discharge: ~6,700 cfs
Regional Topography
HCFCD Inverted Siphon Concept
Methodology
- Spreadsheet solves for two parameters
- Darcy-Weisbach equation – Head loss equation
- Swamee-Jain equation – Darcy friction coefficient ( f )
- Approximation of implicit Colebrook-White equation
- VB programming used in excel for iteration
Design Parameters
- Roughness coefficient (ks) = 0.001 ft
Project Parameter Value Mill Creek Drainage Relief Tunnel (MCDRT) – Dallas, TX Manning’s Roughness Coefficient 0.011 Waller Creek Tunnel (WCT) – Austin, TX Roughness coefficient (ks; ft) 0.001 San Antonio River Tunnel (SART) – San Antonio, TX Roughness coefficient (ks; ft) 0.002
- Minor (Inlet & Outlet Losses) = 0.2 + 1.0 = 1.2 ft
- Bend Loss = 0.006 per bend
- No. of Bends per mile (1,000-ft radius) = 2.5
- Kinematic Viscosity = 1.023 x 10-5 ft2/s
- Sediment Deposition Depth = 5% of Tunnel Diameter
Scenarios Analyzed
Diameter (ft) Differential Head (ft) Tunnel Length (mi) 5 30 5 10 40 10 15 50 15 20 60 20 25 70 25 30 80 30 35 90
- 40
100
- Diameter: 5’ intervals
- Heads : 10’ intervals
- Length: 5 mi intervals
Validation
Project Actual Rated Capacities (cfs) Spreadsheet (cfs) Mill Creek, Dallas 20,000 (approx.) 19,831 Waller Creek, Austin 8,500 (approx.) 8,486 San Antonio River Tunnel 6,700 (approx.) 6,720
Flow Rates for 10-mile Tunnel
Flow rate (cfs) Diameter (ft) Head (ft) 30 40 50 5
70 81 90
10
423 489 547
15
1,205 1,394 1,560
20
2,527 2,922 3,270
25
4,477 5,176 5,792
30
7,132 8,244 9,224
35
10,557 12,202 13,651
40
14,810 17,117 19,149
*Additional results in Appendix B
Results
5 10 15 20 25 30 35 40 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Tunnel Diameter (ft) Flow (cfs)
FLOW RATE AT 50' HEAD
L = 5 mi L = 10 mi L = 15 mi L = 20 mi L = 25 mi L = 30 mi 5 10 15 20 25 30 35 40 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Tunnel Diameter (ft) Flow (cfs)
FLOW RATE AT 60' HEAD
L = 5 mi L = 10 mi L = 15 mi L = 20 mi L = 25 mi L = 30 mi 5 10 15 20 25 30 35 40 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Tunnel Diameter (ft) Flow (cfs)
FLOW RATE AT 30' HEAD
L = 5 mi L = 10 mi L = 15 mi L = 20 mi L = 25 mi L = 30 mi 5 10 15 20 25 30 35 40 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 Tunnel Diameter (ft) Flow (cfs)
FLOW RATE AT 40' HEAD
L = 5 mi L = 10 mi L = 15 mi L = 20 mi L = 25 mi L = 30 mi
Sensitivity Analysis
Parameter Range Minimum Design Maximum Roughness coefficient (ft) 0.0005 0.001 0.002 Minor loss (Entrance & Exit Losses) 0.2 +1.0 = 1.2 1.0+1.0 = 2.0 Bend Loss 0.006 (smooth bend) 0.02 (mitered bend)
- No. of Bends per mile (1,000-ft radius)
2.5 5 Kinematic Viscosity (x 10-5, ft2/s) 0.93 1.023 1.86 Sediment Deposition (% of Tunnel Diameter) 5 10
Takeaways:
- Surface roughness has the highest influence on the tunnel flow rate.
- Sediment depth has the second most influence on the tunnel flow rate.
- Other parameters interchangeably rank higher to lower depending on the differential head,
tunnel diameter, and length.
Tunnel Applicability
Face Support Methods for Shields and TBMs
Pre-cast Concrete Segmental Lining Schematic
TBM Launch Site
- Site size > 5 acres
- Shaft size = 2 to 2.5 OD
- Haul routes considered
- Power = 20 MW +/-
- Noise screening
Fencing with Noise Barrier
Third-party Impacts
- The construction of large diameter flood control tunnel(s) will have a
significant impact on traffic and noise in the area surrounding the shaft sites
- Truck traffic for a 40-foot diameter tunnel construction will require hundreds of truck trips each
work day.
- Time of day restrictions are sometimes placed at shaft site locations that are
in a residential area.
- Typical time of day restrictions may be 7:00 AM to 7:00 PM.
- Tunnel construction below ground is pursued essentially 24 hours a day, 7
days a week.
- Above the tunnel it will be difficult to to even notice that tunnel construction is taking place
Typical TBM Progress Rates
- For this planned flood control tunnel, we would recommend assumed
progress rates for initial planning purposes as follows:
- 25-foot Diameter Tunnel
75 ft/day
- 40-foot Diameter Tunnel
50 ft/day
- The Anacostia River Tunnel which is a 23 -foot diameter soft ground tunnel
was constructed with an average daily progress rate of 80 ft/day and a maximum daily progress of 120 ft/day.
Construction Packaging and Schedule
- A planned flood control tunnel may exceed 10 miles in length and 40 foot in
diameter.
- A tunnel project of this size is often broken up into several construction contracts.
- Each contract would have one or more TBMs with individual TBM runs typically
being a few miles in length.
- From discussions with tunnel contractors for planning purposes, an upper limit on
mining length with a single TBM before major mechanical rehabilitation is required is between 5 and 7 miles. This distance may be appropriate for breaking up longer tunnels into segments.
Cost Analysis
Don, Wotring, PE, Brierley Associates Brian Gettinger, PE
F O R C O N C E P T U A L T U N N E L A U G U S T 2 9 , 2 0 1 9
presented by
AACE Class 5 Cost Estimate
Accuracy Range Includes Contingency Contingency = 50%
Estimate Class Maturity Level1 Typical Estimate Purpose Typical Estimating Method Expected Accuracy Range2 Class 5 0% to 2% Concept screening SF factoring, parametric models, judgement, or analogy L: -20% to -30% H: +30% to +50%
Cost Estimate
Shafts and In/Outlet Structures Mobilization and Bonding Other Allowances Contingency
Tunnel 44% 32% 13.5% 6% 3%
1.5%
Payment Items 25-ft Diameter (2019 millions USD) 40-ft Diameter (2019 millions USD) Project Subtotal $678.1 (65%) $1,005 (66%) Contingency (50%) $332.1 (32%) $492.7 (32%) Allowances $31.7 (3%) $31.7 (2%) Total $1,041 $1,530
Appendix B – 25-ft Diameter Tunnel Appendix C – 40-ft Diameter Tunnel Appendix D – Payment Items (32)
Historical Project Comparison
Northeast Boundary Tunnel
Phase 1 Conclusions
- 1. Tunneling in Harris County is feasible based on the geotechnical
conditions and project experience in similar soils
- 2. Tunnels can move a significant rate of stormwater operating entirely
by gravity as an inverted siphon
- 3. Tunnel cost including a 50% contingency for a representative 10-mile-
long, 25- and 40-foot diameter tunnel are $1 billion and $1.5 billion respectively
Phase 1 Outcomes