Geotechnical Aspects of the Twin Ports Interchange (TPI) Duluth, - - PowerPoint PPT Presentation

geotechnical aspects of the twin ports interchange tpi
SMART_READER_LITE
LIVE PREVIEW

Geotechnical Aspects of the Twin Ports Interchange (TPI) Duluth, - - PowerPoint PPT Presentation

Geotechnical Aspects of the Twin Ports Interchange (TPI) Duluth, Minnesota Rich Lamb, P.E. 2019 Midwest Geotechnical Engineering Conference September 16-19, Columbus, OH mndot.gov Sorry, Wisconsin Project Location Duluth, Minnesota 2


slide-1
SLIDE 1

Geotechnical Aspects of the Twin Ports Interchange (TPI) Duluth, Minnesota

Rich Lamb, P.E. 2019 Midwest Geotechnical Engineering Conference September 16-19, Columbus, OH

mndot.gov

slide-2
SLIDE 2

Sorry, Wisconsin

slide-3
SLIDE 3

Project Location

Lake Superior Duluth, Minnesota Superior, Wisconsin Port of Duluth-Superior 1 3 2

slide-4
SLIDE 4

Current Interchange

  • Known locally as the “Can of Worms”
  • 3rd highest crash rate statewide for

interchanges

  • 33 aging bridges (built in late ‘60’s),

mainline interstate on land bridge

  • 16 bridges weight restricted 7 non-

redundant

  • Problem for over-sized and over-weight

traffic coming from port and getting on Interstate

4

slide-5
SLIDE 5

Routes of Diverted OSOW Traffic

5

slide-6
SLIDE 6

Current Main Interchange

6

I535 Lake Superior Historic Neighborhood

slide-7
SLIDE 7

Trestle Bridges (mainline I35 and all ramps)

7

slide-8
SLIDE 8

US53

8

slide-9
SLIDE 9

Garfield Interchange I535

9

slide-10
SLIDE 10

Twin Ports Interchange (TPI) Project Goals

  • Enhance safety by eliminating blind merges and

left exits

  • Replace aging infrastructure
  • Reduce maintenance and closures
  • Reduce bridge structure
  • Improve freight mobility
  • Allow oversize/overweight freight on the Interstate

by reconstruct/rehab substandard bridges

10

slide-11
SLIDE 11

Project Overview

  • Alternate Deliver Method - Construction

Manager/General Contractor (CMGC)

  • Currently nearing 60% design status
  • Consultant design for both roadway and bridges
  • Construction scheduled for 2020-2022 ($250-

300M)

  • Driven Pile Load testing and Column Test

Project (Rigid Inclusions) currently underway

11

slide-12
SLIDE 12

Construction Manager/General Contractor (CMGC)

  • Contractor hired at start of design under

professional/technical consultant contract

  • Contractor responsibilities
  • Constructability Reviews
  • Maintenance of Traffic, Construction Staging

Reviews

  • Work will be let in two Work Packages
  • Three cost estimates (EE, Contractor, ICE) must

be close for Contractor to do work

12

slide-13
SLIDE 13

Current Design Layout

  • 14 New Bridges, 4 Bridge Rehabs
  • ~600,000 sq. ft. of Column

Supported Embankments

  • Fill heights up to 38 ft.
  • 40% reduction in bridge deck area
  • 8,000 L.F. Retaining Walls
  • Cast-in-Place Concrete Cantilever
  • MSE

13

slide-14
SLIDE 14

Geotechnical Design Team

  • Subsurface Investigations, Ret Wall

Geotechnical Reports, Roadway Soils

  • Ground Improvement Design, Modeling
  • Supplemental Subsurface Investigations
  • Early work on TH 53 Embankments
  • Lateral Pile Stability

mndot.gov/

slide-15
SLIDE 15

Column Supported Embankment Design

  • Designed by consultants (Barr

Engineering and Itasca Engineering)

  • Most economical column is full

displacement grouted column

  • Diameters 16-18 in.
  • Column Spacing 8-10 ft.
  • Rough Unit Cost ~ $40/sq. ft.
  • Includes wall cost

15

slide-16
SLIDE 16

Subsurface Investigations

  • 120 Historic Borings from 1960’s (poorly located, ±50 ft.)
  • 150 Cone Penetration Test (CPT) soundings
  • 250 Modern SPT Foundation Borings
  • Dozen or so Test Pits

16

slide-17
SLIDE 17

General Subsurface Conditions

9/24/2019 mndot.gov 17

Main Intersection US 53 Garfield Interchange

Very Dense Sand >150 ft. Bedrock Dense Sand Org Silty Clay Sand fill Bedrock

Vert Dense Sand/Silt

Clay

Stiff Silt and Clay

Sand fill Dense Sand

40-60 ft 100 ft. 150 ft. 10-55 ft. thick

Clay

Var.

slide-18
SLIDE 18

Soil Variability

9/24/2019 mndot.gov 18

slide-19
SLIDE 19

Soil Variability

9/24/2019 mndot.gov 19

107 ft. 54 ft. 41 ft. Miller Creek Culvert Inlet Bridge 69902 West Abut 35 ft.

slide-20
SLIDE 20

Sloping Bedrock

9/24/2019 mndot.gov 20

90 ft. 500 ft. Bedrock Miller/Coffee Creek Culvet

slide-21
SLIDE 21

3D Soil Model

21

slide-22
SLIDE 22

High Ground Water Table

22

Lake Superior 603.5 MSL Existing Grade ~606

slide-23
SLIDE 23

Lake Tides

  • Strong North Wind = 1-2 “tide”

23

slide-24
SLIDE 24

Soil Contamination

24

slide-25
SLIDE 25

Soil Contamination

  • Petroleum, lead, arsenic, PAH, Asbestos

25

slide-26
SLIDE 26

Big Geotechnical Challenges

  • Avoiding any excavation to limit cost of treating

contaminated soil and groundwater

  • Possible Steel Corrosion from contaminated soil
  • Construction Staging does not allow for

embankment settlement wait periods

  • High groundwater
  • Urban fill

26

slide-27
SLIDE 27

Bigger Geotechnical Challenges

  • Interaction of CSE foundation elements with

bridge/wall driven piles

  • Ground heave/lateral displacement from

“forest” of full displacement columns

  • Low fill ground improvement
  • Building bridge/walls/embankments over in-

place utilities

  • Reviewing designs using finite difference

method

27

slide-28
SLIDE 28

Low Embankments

  • No excavation
  • No settlement wait periods
  • 1 inch of long term

allowable settlement

28 9/24/2019 mndot.gov 28

4-6 ft. fill Weak Soils, highly contaminated 30-60 ft. Dense Soils

slide-29
SLIDE 29

Low Embankment Foundation Design

  • Columns Supported

Embankment

  • Driven piles or grouted

columns

  • 10 ft. center spacing
  • 1 ft. thick reinforced

concrete LTP

29 9/24/2019 mndot.gov 29

LTP Dense Soils 4-6 ft. fill

slide-30
SLIDE 30

Interaction of CSE columns and bridge piles

30

slide-31
SLIDE 31

Ground Heave/Lateral Displacement Problem

9/24/2019 mndot.gov 31

Driven Piles Full Displacement Columns

slide-32
SLIDE 32

Column Test Project

  • 63 CMC

column 18

  • in. dia. 65 ft.
  • Wick drains

½ area

  • Driven 16 in.

pipe pile

  • Two Static

Load Tests

  • n columns
  • Instruments

9/24/2019 mndot.gov 32

slide-33
SLIDE 33

Column Test Layout

33

slide-34
SLIDE 34

Test Area Soils

9/24/2019 mndot.gov 34

65 ft.

slide-35
SLIDE 35

Column Test Embankment

9/24/2019 mndot.gov 35

slide-36
SLIDE 36

Instrumentation

  • 63 total gages
  • Piezometers
  • Survey targets
  • Extensometers
  • ShapeAccelArray
  • Vertical and horizontal
  • Strain Gages

9/24/2019 mndot.gov 36

slide-37
SLIDE 37

Initial Instrumentation Results

37

slide-38
SLIDE 38

Current Instrumentation Results

  • Lateral Deflections ~4 inches near columns (3 ft), but only

½ inch 10 ft. away

  • Heave – 1 inch
  • Pore Pressures – dissipates quickly

38

slide-39
SLIDE 39

Vertical SAA

39

slide-40
SLIDE 40

If Ground Movement is Problem

  • Use non-displacement columns or H pile

in “buffer zones”

9/24/2019 mndot.gov 40

Auger Cast

  • r H Pile

Full Displacement Columns

1 2

3

slide-41
SLIDE 41

Sanitary Lift Station

41

slide-42
SLIDE 42

42

slide-43
SLIDE 43

43

slide-44
SLIDE 44

Cross Section

44

slide-45
SLIDE 45

Options

  • Remove building
  • Fill-in basement and drill

foundations through floor

  • Span over

45

slide-46
SLIDE 46

Bridge Piling Adjustments

46

slide-47
SLIDE 47

Reviewing CSE Designs

  • How to check 2d, 2.5d and 3d Finite Difference

Method models

47

slide-48
SLIDE 48

Thank you

Rich Lamb

rich.lamb@state.mn.us 651-366-5595

9/24/2019 mndot.gov 48

slide-49
SLIDE 49

49

slide-50
SLIDE 50

Column Supported Embankments 101

9/24/2019 mndot.gov 50

Embankment Load Transfer Platform Weak Soils Dense Soils Rigid Inclusions (columns/piles)

(70-95% of embankment load)

slide-51
SLIDE 51

Rigid Inclusions (Columns or Piles)

  • Full Displacement Grout Columns
  • Non-displacement Grout Columns
  • Driven piles
  • H sections
  • Pipe sections
  • Typical Spacing 5-10 ft. centers
  • Pile Caps typically used

9/24/2019 mndot.gov 51

$12-$20 / LF $30-$40 / LF

slide-52
SLIDE 52

52

slide-53
SLIDE 53

CSE with misc Structures/Utilities

9/24/2019 mndot.gov 53

Embankment MSE Wall CIP Wall Storm Sewer

Exit 535 EB

OH Sign Light Tower

slide-54
SLIDE 54

Archaeological Concerns

  • I-535 and Garfield Avenue
  • Brown’s Trading Post
  • North side of Piedmont Avenue
  • Known Native Cemetery
  • Some graves relocated in 1870 to Railyard
  • Coffee Creek Banks
  • Culvert built over stream and filled
  • Beneath the structure
  • Old Lakeshore
  • Drilling in these areas suspended

54

slide-55
SLIDE 55

9/24/2019 mndot.gov 55

Load Transfer Platform Design

  • Acts as a pile cap – evenly distributes load to columns
  • Select well graded granular fill (94-98% compaction) (MnDOT Class 5)
  • Minimum of three horizontal biaxial geosynthetic reinforcement

layers with vertical spacing of 8-18 in.

  • LTP thickness (½ the clear span between columns)
slide-56
SLIDE 56

Full Displacement Columns

  • “Drilled Displacement Piles”
  • Very few spoils, low noise, vibration
  • Reverse flight Augers push soils down

and away from column

  • May displace soils laterally – problem

for adjacent structures

  • Diameters of 12-24 inches, and

typical lengths of 65-85 ft.

  • Difficult to penetrate dense soil

layers

9/24/2019 mndot.gov 56

slide-57
SLIDE 57

Menard – Controlled Modulus Column

9/24/2019 mndot.gov 57

slide-58
SLIDE 58

Non Displacement Columns

  • “Auger Cast Pile” or

“Continuous Flight Auger Pile”

  • Diameters of 12-24 in.
  • Depths of 100 ft. or more
  • Low noise, vibration
  • Spoils much greater than FDC

9/24/2019 mndot.gov 58

slide-59
SLIDE 59

Displacement Piles

9/24/2019 mndot.gov 59

slide-60
SLIDE 60

Non-Displacement Piles

  • “Pile Supported Embankment”

9/24/2019 mndot.gov 60

slide-61
SLIDE 61

Questions or Comments?

slide-62
SLIDE 62

Geology

  • What has shaped the subsurface conditions the project

site?

  • Volcanoes (igneous bedrock)
  • Glaciers (dense soils)
  • Lake Sediments (organics and soft clay)
  • Erosion from stream flow (variability)
  • Land use (surface fill material, contaminants)

mndot.gov/

slide-63
SLIDE 63

Subsurface Investigations

  • 120 Historical Borings (1960s)

(bridges)

  • 100 Modern Borings (AET)

(bridges)

  • 150 Cone Penetration Test

(CPT) Soundings (embankments)

  • 150 Future holes

9/24/2019 mndot.gov 63

75-100’

slide-64
SLIDE 64

64

slide-65
SLIDE 65

65

slide-66
SLIDE 66

66

slide-67
SLIDE 67

Tall Embankments

67 9/24/2019 mndot.gov 67

Embankment 20-40 ft. Weak Soils 30-60 ft. Dense Soils

slide-68
SLIDE 68

Tall Embankments

68 9/24/2019 mndot.gov 68

Embankment 20-40 ft. Weak Soils 30-60 ft. Dense Soils

slide-69
SLIDE 69

Typical Section I35 and Ramps

69

slide-70
SLIDE 70

70

slide-71
SLIDE 71

Org Chart - CMGC

71

slide-72
SLIDE 72

Typical Section for CSE

72

slide-73
SLIDE 73

Typical Section for CSE

73

slide-74
SLIDE 74

Perched Abutments

74

Weak Soils, highly contaminated 30-60 ft. MSE Wall Dense Soils

slide-75
SLIDE 75

Main Interchange

75

slide-76
SLIDE 76

US 53 Bridges

76

slide-77
SLIDE 77

Garfield Interchange

77