geotechnical aspects of the twin ports interchange tpi
play

Geotechnical Aspects of the Twin Ports Interchange (TPI) Duluth, - PowerPoint PPT Presentation

Geotechnical Aspects of the Twin Ports Interchange (TPI) Duluth, Minnesota Rich Lamb, P.E. 2019 Midwest Geotechnical Engineering Conference September 16-19, Columbus, OH mndot.gov Sorry, Wisconsin Project Location Duluth, Minnesota 2


  1. Geotechnical Aspects of the Twin Ports Interchange (TPI) Duluth, Minnesota Rich Lamb, P.E. 2019 Midwest Geotechnical Engineering Conference September 16-19, Columbus, OH mndot.gov

  2. Sorry, Wisconsin

  3. Project Location Duluth, Minnesota 2 Lake 1 Superior 3 Port of Duluth-Superior Superior, Wisconsin

  4. Current Interchange • Known locally as the “Can of Worms” • 3 rd highest crash rate statewide for interchanges • 33 aging bridges (built in late ‘60’s), mainline interstate on land bridge • 16 bridges weight restricted 7 non- redundant • Problem for over-sized and over-weight traffic coming from port and getting on Interstate 4

  5. Routes of Diverted OSOW Traffic 5

  6. Current Main Interchange Historic Neighborhood I535 Lake Superior 6

  7. Trestle Bridges (mainline I35 and all ramps) 7

  8. US53 8

  9. Garfield Interchange I535 9

  10. Twin Ports Interchange (TPI) Project Goals • Enhance safety by eliminating blind merges and left exits • Replace aging infrastructure • Reduce maintenance and closures • Reduce bridge structure • Improve freight mobility • Allow oversize/overweight freight on the Interstate by reconstruct/rehab substandard bridges 10

  11. Project Overview • Alternate Deliver Method - Construction Manager/General Contractor (CMGC) • Currently nearing 60% design status • Consultant design for both roadway and bridges • Construction scheduled for 2020-2022 ($250- 300M) • Driven Pile Load testing and Column Test Project (Rigid Inclusions) currently underway 11

  12. Construction Manager/General Contractor (CMGC) • Contractor hired at start of design under professional/technical consultant contract • Contractor responsibilities • Constructability Reviews • Maintenance of Traffic, Construction Staging Reviews • Work will be let in two Work Packages • Three cost estimates (EE, Contractor, ICE) must be close for Contractor to do work 12

  13. Current Design Layout • 14 New Bridges, 4 Bridge Rehabs • ~600,000 sq. ft. of Column Supported Embankments • Fill heights up to 38 ft. • 40% reduction in bridge deck area • 8,000 L.F. Retaining Walls • Cast-in-Place Concrete Cantilever • MSE 13

  14. Geotechnical Design Team • Subsurface Investigations, Ret Wall Geotechnical Reports, Roadway Soils • Ground Improvement Design, Modeling • Supplemental Subsurface Investigations • Early work on TH 53 Embankments • Lateral Pile Stability mndot.gov/

  15. Column Supported Embankment Design • Designed by consultants (Barr Engineering and Itasca Engineering) • Most economical column is full displacement grouted column • Diameters 16-18 in. • Column Spacing 8-10 ft. • Rough Unit Cost ~ $40/sq. ft. • Includes wall cost 15

  16. Subsurface Investigations • 120 Historic Borings from 1960’s (poorly located, ±50 ft.) • 150 Cone Penetration Test (CPT) soundings • 250 Modern SPT Foundation Borings • Dozen or so Test Pits 16

  17. General Subsurface Conditions US 53 Garfield Interchange Main Intersection Sand fill Sand fill Clay 10-55 ft. Org Silty Stiff Silt and thick Clay Clay Dense Sand Very Dense Sand Dense Sand >150 ft. Clay 40-60 ft Var. Bedrock Vert Dense Sand/Silt 100 ft. Bedrock 150 ft. 9/24/2019 mndot.gov 17

  18. Soil Variability 9/24/2019 mndot.gov 18

  19. Soil Variability Bridge 69902 West Abut Miller Creek Culvert Inlet 54 ft. 41 ft. 107 ft. 35 ft. 9/24/2019 mndot.gov 19

  20. Sloping Bedrock 500 ft. Miller/Coffee Creek Culvet 90 ft. Bedrock 9/24/2019 mndot.gov 20

  21. 3D Soil Model 21

  22. High Ground Water Table Existing Grade ~606 Lake Superior 603.5 MSL 22

  23. Lake Tides • Strong North Wind = 1-2 “tide” 23

  24. Soil Contamination 24

  25. Soil Contamination • Petroleum, lead, arsenic, PAH, Asbestos 25

  26. Big Geotechnical Challenges • Avoiding any excavation to limit cost of treating contaminated soil and groundwater • Possible Steel Corrosion from contaminated soil • Construction Staging does not allow for embankment settlement wait periods • High groundwater • Urban fill 26

  27. Bigger Geotechnical Challenges • Interaction of CSE foundation elements with bridge/wall driven piles • Ground heave/lateral displacement from “forest” of full displacement columns • Low fill ground improvement • Building bridge/walls/embankments over in- place utilities • Reviewing designs using finite difference method 27

  28. Low Embankments • No excavation • No settlement wait periods 4-6 ft. fill • 1 inch of long term allowable settlement Weak Soils, highly contaminated 30-60 ft. Dense Soils 9/24/2019 mndot.gov 28 28

  29. Low Embankment Foundation Design • Columns Supported Embankment • Driven piles or grouted 4-6 ft. fill columns LTP • 10 ft. center spacing • 1 ft. thick reinforced concrete LTP Dense Soils 9/24/2019 mndot.gov 29 29

  30. Interaction of CSE columns and bridge piles 30

  31. Ground Heave/Lateral Displacement Problem Full Displacement Columns Driven Piles 9/24/2019 mndot.gov 31

  32. Column Test Project • 63 CMC column 18 in. dia. 65 ft. • Wick drains ½ area • Driven 16 in. pipe pile • Two Static Load Tests on columns • Instruments 9/24/2019 mndot.gov 32

  33. Column Test Layout 33

  34. Test Area Soils 65 ft. 9/24/2019 mndot.gov 34

  35. Column Test Embankment 9/24/2019 mndot.gov 35

  36. Instrumentation • 63 total gages • Piezometers • Survey targets • Extensometers • ShapeAccelArray • Vertical and horizontal • Strain Gages 9/24/2019 mndot.gov 36

  37. Initial Instrumentation Results 37

  38. Current Instrumentation Results • Lateral Deflections ~4 inches near columns (3 ft), but only ½ inch 10 ft. away • Heave – 1 inch • Pore Pressures – dissipates quickly 38

  39. Vertical SAA 39

  40. If Ground Movement is Problem • Use non-displacement columns or H pile in “buffer zones” Full Auger Cast Displacement or H Pile Columns 2 3 1 9/24/2019 mndot.gov 40

  41. Sanitary Lift Station 41

  42. 42

  43. 43

  44. Cross Section 44

  45. Options • Remove building • Fill-in basement and drill foundations through floor • Span over 45

  46. Bridge Piling Adjustments 46

  47. Reviewing CSE Designs • How to check 2d, 2.5d and 3d Finite Difference Method models 47

  48. Thank you Rich Lamb rich.lamb@state.mn.us 651-366-5595 9/24/2019 mndot.gov 48

  49. 49

  50. Column Supported Embankments 101 Embankment Load Transfer Platform Rigid Inclusions Weak Soils (columns/piles) (70-95% of embankment load) Dense Soils 9/24/2019 mndot.gov 50

  51. Rigid Inclusions (Columns or Piles) • Full Displacement Grout Columns $12-$20 / LF • Non-displacement Grout Columns • Driven piles • H sections $30-$40 / LF • Pipe sections • Typical Spacing 5-10 ft. centers • Pile Caps typically used 9/24/2019 mndot.gov 51

  52. 52

  53. CSE with misc Structures/Utilities OH Sign Exit 535 EB Light Tower Embankment CIP Wall MSE Wall Storm Sewer 9/24/2019 mndot.gov 53

  54. Archaeological Concerns • I-535 and Garfield Avenue • Brown’s Trading Post • North side of Piedmont Avenue • Known Native Cemetery • Some graves relocated in 1870 to Railyard • Coffee Creek Banks • Culvert built over stream and filled • Beneath the structure • Old Lakeshore • Drilling in these areas suspended 54

  55. Load Transfer Platform Design • Acts as a pile cap – evenly distributes load to columns • Select well graded granular fill (94-98% compaction) (MnDOT Class 5) • Minimum of three horizontal biaxial geosynthetic reinforcement layers with vertical spacing of 8-18 in. • LTP thickness (½ the clear span between columns) 9/24/2019 mndot.gov 55

  56. Full Displacement Columns • “Drilled Displacement Piles” • Very few spoils, low noise, vibration • Reverse flight Augers push soils down and away from column • May displace soils laterally – problem for adjacent structures • Diameters of 12-24 inches, and typical lengths of 65-85 ft. • Difficult to penetrate dense soil layers 9/24/2019 mndot.gov 56

  57. Menard – Controlled Modulus Column 9/24/2019 mndot.gov 57

  58. Non Displacement Columns • “Auger Cast Pile” or “Continuous Flight Auger Pile” • Diameters of 12-24 in. • Depths of 100 ft. or more • Low noise, vibration • Spoils much greater than FDC 9/24/2019 mndot.gov 58

  59. Displacement Piles 9/24/2019 mndot.gov 59

  60. Non-Displacement Piles • “Pile Supported Embankment” 9/24/2019 mndot.gov 60

  61. Questions or Comments?

  62. Geology • What has shaped the subsurface conditions the project site? • Volcanoes (igneous bedrock) • Glaciers (dense soils) • Lake Sediments (organics and soft clay) • Erosion from stream flow (variability) • Land use (surface fill material, contaminants) mndot.gov/

  63. Subsurface Investigations • 120 Historical Borings (1960s) (bridges) • 100 Modern Borings (AET) (bridges) • 150 Cone Penetration Test (CPT) Soundings 75-100’ (embankments) • 150 Future holes 9/24/2019 mndot.gov 63

  64. 64

  65. 65

  66. 66

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend