fy 19 20 1 st quarter project delivery report
play

FY 19-20 1 st Quarter Project Delivery Report by Michael D. Keever - PowerPoint PPT Presentation

Tab 64 FY 19-20 1 st Quarter Project Delivery Report by Michael D. Keever Division of Project December 4 & 5, 2019 Management Phases of Project Development Capital Outlay Support (COS) COS Closeout Planning Program Allocatio


  1. Tab 64 FY 19-20 1 st Quarter Project Delivery Report by Michael D. Keever Division of Project December 4 & 5, 2019 Management

  2. Phases of Project Development Capital Outlay Support (COS) COS Closeout Planning Program Allocatio Construction PS&E (Design) Need & n Programming Priority PA&ED PID Allocation & Allocation Identified Right of Way Programme 20% Known Hig 80% Unknown h Complete PA&ED Construction Complete Risk and Uncertainty d Design Complete Closeout Complete 80% Known 20% Unknown Low Preliminary Engineering (15¢) Construction (85¢)

  3. FY 19-20 1 st Quarter Project Delivery Performance Measures Year-End Annual Completion Last Five Fiscal Measure Completion Projection (%) Commitment (%) Year Average (%) Draft Environmental 109 7 6 89 79 Documents Project Approval, Environmental 268 41 15 97 90 Documents Projects Certified by 304 34 11 97 97 Right of Way Projects Designed and 313 27 9 100 98 Ready for Construction Capital Value Ready for $4,947 M $216 M 4 98 98 Allocation Projects Constructed 184 46 25 95 88

  4. FY 19-20 1 st Quarter Project Delivery Performance Measures  Project Costs at End of Construction 1 Last Five Fiscal Year Measure Expended Budget Savings % Average (%) Costs for 4 Completed STIP $749 M $726 M -$23 M 103% 95% Projects Costs for 48 Completed $413 M $451 M $38 M 92% 91% SHOPP Projects 1 Construction costs are calculated 6 months after the end of construction 4

  5. FY 19-20 1 st Quarter Project Watch List  Construction Capital Budget Risks Managed by Caltrans Total Budget Total Risk Status Projects 1 (Millions) (Millions) Seeking Allocation 15 $31 $30 Advertising 2 $12 $3 Construction 20 $788 $53 Closeout 8 $181 $12 Total 45 $1,012 $98 1 853 Projects under construction with construction budget of $9.9 billion, as of September 2019. 5

  6. Appendix E of the Project Delivery Report Construction Capital Closeout 1 Summary, SHOPP Projects 2 $350 FY 2019-20, Q1, Year-to-Date $324 ($Millions) $314 $313 $291 $300 $250 $200 $150 $100 $50 $12 $6 -$7 $0 -$50 Con Cap Programmed Allocations G12s to Award Other G12s Total Suplementals Allocations plus G-12s Con Cap Expended plus Supplementals 1 Project closeout reflects projects where construction contract was complete two quarters ago. 2 Appendix B, 48 SHOPP Completed Projects at Closeout. 6

  7. Thank You! 7

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.