Delivery Scott Kennelly Senior Project Manager Asset Delivery - - PowerPoint PPT Presentation

delivery
SMART_READER_LITE
LIVE PREVIEW

Delivery Scott Kennelly Senior Project Manager Asset Delivery - - PowerPoint PPT Presentation

June 2010 Delivery Scott Kennelly Senior Project Manager Asset Delivery Services Project Delivery Delivery by a two stream approach Early & Enabling Works Operator Franchise Works The Early & Enabling Works is carried


slide-1
SLIDE 1

Delivery

Scott Kennelly Senior Project Manager Asset Delivery Services

June 2010

slide-2
SLIDE 2

17

Project Delivery

  • Delivery by a two stream approach
  • Early & Enabling Works
  • Operator Franchise Works
  • The Early & Enabling Works is carried out in selected areas

that have access / time constraints

  • The Operator Franchise Works is the remaining roadworks,

rail lines, rollingstock, stations and depot

slide-3
SLIDE 3

18

Early & Enabling Works

The EEW consist of three main packages:

  • 1. Gold Coast University Hospital Station shell
  • 2. Roadworks North
  • 3. Roadworks South

And minor works.

slide-4
SLIDE 4

19

GCUH Station shell Roadworks North Roadworks South

slide-5
SLIDE 5

20

Gold Coast University Hospital Station shell

slide-6
SLIDE 6

21

Gold Coast University Hospital Station shell

slide-7
SLIDE 7

22

Gold Coast University Hospital Station shell

Design RFP ECI Phase Tender Construction July 2010 Award Late 2011

slide-8
SLIDE 8

23

Roadworks North Roadworks South

slide-9
SLIDE 9

24

Roadworks

slide-10
SLIDE 10

25

Roadworks North & South

Typical services / products:

  • Earthworks: excavation/compaction equipment, backfill material etc
  • Drainage: concrete pipes, pvc pipes, drainage pipes, geotechnical fabric etc
  • Service relocation: trenching, ducting, backfill etc
  • Paving: supply and/or placement of gravel, concrete, bitumen, asphalt etc
  • Concreting: kerb and channel, footpaths, medians etc
  • Roadside furniture: guardrails, noise barriers, signs, street lighting, traffic

signals, pavement markings etc

  • Built environment: fencing, landscaping etc
slide-11
SLIDE 11

26

Roadworks North & South

Design RFP ECI Phase Tender Construction July 2010 Award Late 2011 September 2010 October 2010

slide-12
SLIDE 12

27

Roadworks – Minor Works

  • Croquet club fields
  • Building modifications eg tennis club
  • Building demolitions
  • Fencing and retaining walls
  • Landscaping
slide-13
SLIDE 13

Operator Franchise

  • Three proponents

shortlisted to build Stage One

  • Some of the biggest global

players in this field are vying to build this project

  • Proponents will be looking

for local business and trade to partner to deliver the project

  • Between now and late

2010, the proponents will participate in a ‘Request for Proposal’ process

slide-14
SLIDE 14

Operator Franchise scope

Typical activities

  • Road works
  • Drainage works and service relocation
  • Bridge works
  • Earth works
  • Concreting (structural, footpaths, curb and channel)
  • Building and construction around stations and depot
  • Electrical works
  • Street furniture
  • Maintenance of the system and rolling stock
  • Cleaning
  • Security
  • Recruitment and HR Management
  • Traffic signal upgrades
  • Systems
  • Landscaping
slide-15
SLIDE 15

30

Operator Franchise

Expression of Interest

Interactive Phase Design & Construction June 2010 June 2011 Evaluate & Award November 2010 2014 Operations

slide-16
SLIDE 16

31

Operator Franchise

Typical services / products:

  • As for the roadworks projects
  • Stations: foundations, structures, painting, electrical, etc
  • Carparks: paving materials, excavation/ compaction equipment, landscaping etc
  • Rail: track slab, kerb and channel, fencing, pavement markings, Overhead

Power lines etc

  • Communications: equipment, electrical installation, conduits, manholes, signals

etc

  • Accommodation works: driveways, fences, retaining walls etc
  • Operations: office accommodation, telecommunications, office supplies,

security, personnel services etc

slide-17
SLIDE 17

32

Local Industry Participation

  • Understand the challenge to get involved in large projects
  • Acknowledge Government protocols for large projects
  • GCRT commitment to maximise opportunity for local industry
  • Enable open two-way communications and increase awareness
  • f local suppliers and contractor contacts
slide-18
SLIDE 18

33

Local Industry Participation

  • GCRT on-line industry register on GCRT website
  • Strong weighting in tenders for local involvement
  • During construction, LIP implementation is measured as a

component of the contractor’s performance

slide-19
SLIDE 19

Local Industry Participation

Design RFP ECI Phase Tender Construction Award

Contractor commitment and assessment criteria Progressive reporting Incentive Provide local industry register to contractors