Delivery
Scott Kennelly Senior Project Manager Asset Delivery Services
June 2010
Delivery Scott Kennelly Senior Project Manager Asset Delivery - - PowerPoint PPT Presentation
June 2010 Delivery Scott Kennelly Senior Project Manager Asset Delivery Services Project Delivery Delivery by a two stream approach Early & Enabling Works Operator Franchise Works The Early & Enabling Works is carried
June 2010
17
that have access / time constraints
rail lines, rollingstock, stations and depot
18
The EEW consist of three main packages:
And minor works.
19
20
21
22
Design RFP ECI Phase Tender Construction July 2010 Award Late 2011
23
24
25
Typical services / products:
signals, pavement markings etc
26
Design RFP ECI Phase Tender Construction July 2010 Award Late 2011 September 2010 October 2010
27
shortlisted to build Stage One
players in this field are vying to build this project
for local business and trade to partner to deliver the project
2010, the proponents will participate in a ‘Request for Proposal’ process
Typical activities
30
Expression of Interest
Interactive Phase Design & Construction June 2010 June 2011 Evaluate & Award November 2010 2014 Operations
31
Typical services / products:
Power lines etc
etc
security, personnel services etc
32
33
component of the contractor’s performance
Design RFP ECI Phase Tender Construction Award
Contractor commitment and assessment criteria Progressive reporting Incentive Provide local industry register to contractors