St. Bede School & Parish STREAM Renovation & Strategic Facility Improvements Information Session 02/13/18 Introduction & Agenda Deacon Rick Tucek Committee Chair, Deacon Administrator Parish Project Team Committee Structure
Introduction & Agenda
Deacon Rick Tucek Committee Chair, Deacon Administrator
Parish Project Team Committee Structure
Deacon Rick Tucek, Chair
- Fr. Bryce, Co-chair
- Design & Construction
- Kevin McNulty, Parish Property, Plant &
Equipment Committee
- Tim Steitz, Parish Property, Plant & Equipment
Committee
- Fundraising & Development
- Holly Sommer, Parish Finance Council, PTG
Treasurer
- Angie Maher, Chair, Parish Finance Council
- Curriculum
- Becky Page, Principal
- Emily Noel, Assistant Principal
- STREAM Academic Committee Teachers
- Marketing
- Joe Perozich, Business Manager
- Christine Honan, Parishioner Volunteer
- PTG
- Rachel Mollen, PTG Co-president
- Kristie Steitz, PTG Co-president
Agenda Overview
- 1. Project Background
- 2. STREAM Project Progress Update & Timeline
- 3. Fundraising Update
- 4. East End School Regionalization
- 5. STREAM Curriculum Development
- 6. Marketing Strategy
- 7. Master Plan
- 8. Q&A
STREAM Project Background
Angie Maher Chair, Parish Finance Council
The Case for STREAM & Improvements
- 1. Provide students the best learning experience possible
- 2. Support our teachers as they implement new
methodologies and teaching techniques
- 3. Part of STREAM implementation throughout the Diocese
- 4. Increase Enrollment
- 5. Maintain financially sustainable operations of the school
without excessive support from the parish
How did we get here?
- 2012: PTG Survey of Parents showed STRONG
interest in STREAM curriculum and facilities
- 2017: Major donor interested in contributing to a
STREAM Renovation Project
- THINK BIGGER!!!
STREAM Project Update & Timeline
Kevin McNulty Parish Property, Plant & Equipment Committee
STREAM Renovation Schedule
- Design 90% complete
- Final paperwork being processed by the Diocese
- Solicitation of subcontractors starting in February
- Construction Schedule:
- Begin immediately after the last day of classes (June 12, 2018 tentatively)
- Complete before teachers return in August
- Classes to begin as scheduled in the Fall
Current Cost Estimate
Current Cost Estimate
Hard Construction Costs: $472,000 Design Fees (including master planning): $40,000 Furniture & Equipment: $47,000 Contingency & Misc. Soft Costs: $49,000 TOTAL ESTIMATE PROJECT COST: $608,000
Estimate subject to change pending final design and selection of furniture and equipment.
Fundraising Update
Angie Maher Chair, Parish Finance Council
How is the project to be funded?
- Private donations specifically earmarked for this
project
- Fundraising goal: $610,000
- Making good progress, but we are not there yet!
How much money has been raised?
Funding Sources Expected Response Dates Funding Requested Funds Expected Before 4/1/18
- St. Bede PTG
$65,000 $65,000 Keefe Ellis Memorial Fund $10,000 $10,000 Major Donors $400,000 $400,000 Other Donors $100,000 ? Grants 3/1 – 5/1/18 $368,000 ? Naming Opportunities TBD ? Parishioners $10,500 In-Kind ? TOTALS $943,000 $485,500
Eastern District School Regionalization
Deacon Rick Tucek Committee Chair, Deacon Administrator
Eastern District School Regionalization
- Regional Advisory Board has been established
- Board and regional vicars reviewing schools and
will make recommendations to the diocese
- Regionalization is expected to be implemented in
Fall 2018
- St. Bede is awaiting final details from the Diocese
Curriculum Update
Becky Page Principal
17 PowerPoint Timesaver
What is STREAM?
Science Technology Religion Engineering Art Math
Four Pillars of STREAM:
- 1. Inquiry-based Learning
- 2. Integrated teaching of different
subjects
- 3. Project-based group learning
- 4. Career Readiness
STREAM Curriculum Development
- Carnegie Science Center Program
- STEAM Makers Author Jacie Maslyk working with
teachers
- Focus on Best Practices for STREAM education
- Facilitate instruction to student’s individual learning
styles
Marketing Campaign
Joe Perozich Parish Business Manager
Marketing Campaign
- How are we marketing
STREAM Renovation & Strategic Improvements?
- Revamped Website
- Direct Mailings
- Presentations to Parishioners & Parents
- Printed marketing materials
- Bulletin Advertisements
- Our efforts are gaining
traction - Open House was very successful – Over 30 families attended
- Developing Database of
Alumni Network
- Strategic Marketing Plan
Parish & School Facilities Master Planning
Kevin McNulty Parish Property, Plant & Equipment Committee
Master Planning - Context & Background
- Completed many deferred maintenance projects over the
past four years to reach a “steady state”
- Money was allocated for repairs and maintenance
generally but projects were executed REACTIVELY
- Planning must be done to pursue projects PROACTIVELY
and avoid unexpected expenses
- Allow to pursue projects STRATEGICALLY
Master Planning Process
- 1. Identify projects & define scope
- 2. Determine budgetary costs of projects
- 3. Prioritize projects
- 4. Schedule and budget for projects based on priority
and contingent on availability of funds (over several years)
- 5. Execute projects according to annual budgets
Master Planning – Example Projects
- Classroom Flooring, Lighting, Casework and Painting
- Technology Infrastructure Upgrades
- Activities Room Improvements & Furniture
- Administrative Office Renovation & Security Improvements
- Air Conditioning & HVAC Upgrades
- Window Replacement
- School Roof Replacement