Dale Drive Pedestrian Facilities Improvements Project Facility - - PowerPoint PPT Presentation

dale drive pedestrian facilities improvements project
SMART_READER_LITE
LIVE PREVIEW

Dale Drive Pedestrian Facilities Improvements Project Facility - - PowerPoint PPT Presentation

Dale Drive Pedestrian Facilities Improvements Project Facility Planning Study Life of A Transportation Project Facility Planning Phase 1 Facility Planning Phase 2 Final Design and Construction Collect data, obtain Develop 35%


slide-1
SLIDE 1

Dale Drive Pedestrian Facilities Improvements Project

Facility Planning Study

slide-2
SLIDE 2

Life of A Transportation Project

Facility Planning – Phase 1

  • Collect data, obtain

public input, develop concept plans

  • Evaluate and select

preferred alignment/typical section

  • Obtain Director’s and

Montgomery County Council’s Transportation Infrastructure, Energy and Environment Committee (T&E) Approval Facility Planning – Phase 2

  • Develop 35% design

plans

  • Refined project

schedule & cost

  • Mandatory Referral
  • Submittal to County

Council for Approval to include in Capital Improvement Project (CIP) Final Design and Construction

  • If approved for full

funding and is included in CIP, complete final design and construction Currently Funded Not Funded

Legend

slide-3
SLIDE 3

Project Overview

slide-4
SLIDE 4

Potential Concept Alternatives

Alternative 0 – Sidewalk or Shared Use Path on 1 side

slide-5
SLIDE 5

Potential Concept Alternatives

Alternative 1 – Sidewalk on both side

slide-6
SLIDE 6

Potential Concept Alternatives

Alternative 3 – Sidewalk on both side with separated bike facilities Alternative 2 – Sidewalk on north side, SUP on south side

slide-7
SLIDE 7

Potential Concept Alternatives

https://platform.remix.com/streets/plan/48e52cc5?latlng=39.00747,-77.03206,z16.471,p0,b0

slide-8
SLIDE 8

Tentative Milestones Schedule

Jul ’18 • Project Kickoff

Aug ’18 • Base Mapping & Topographic Survey

Sept ‘18 • Conceptual (15%) Design

Oct ’18 • Public Workshop Dec ’18

  • Environmental Coordination &

Submittal

Jan ’19

  • Preliminary Engineering (30%) Design
  • SWM Concept Submittal

Mar ’19

  • Mandatory Referral Submittal to

MNCPPC

May ’19

  • Mandatory Referral Hearing

(Estimated)

Jun ’19

  • Revised Preliminary Engineering (35%)

Design

  • End Facility Planning