Earned Value Management
Prepared For: PMI-L.I. Chapter Prepared By: Jean Cronan Presentation on: 11 January 2017
Earned Value Management Prepared For: PMI-L.I. Chapter Prepared - - PowerPoint PPT Presentation
Earned Value Management Prepared For: PMI-L.I. Chapter Prepared By: Jean Cronan Presentation on: 11 January 2017 Learning Objectives Earned Value Background Definitions Establishing a Performance Baseline Performance Management
Prepared For: PMI-L.I. Chapter Prepared By: Jean Cronan Presentation on: 11 January 2017
How Does EVM Relate to PMBOK Process Groups and Knowledge Areas ?
Organize Project through the Charter Assign Responsibilities through Stakeholder Management Establish a Performance Measurement Baseline (PMB):
Management
Management
Management
Management Direct and Manage Work against PMB:
Procurements
Resources Measurement against PMB: Generate:
Source: DAU;EMIG
1950’s Program Evaluation Review Techniques - PERT 1967 Department of Defense (DoD) creates Cost/Schedule Control System Criteria (C/S CSC) 1972 C/S CSC Joint Implementation Guide launched for use by all military branches 1991 DoD issues DoD Instruction 5000.2 Defense Acquisition Management Policies; use of EVM on DoD-wide Programs 1998 Initial issue of American National Standards Institute/Electronic Industries Alliance publishes Earned Value Management Systems (EVMS) called ANSI/EIA-A
Source: EVMPEDIA, EVM History
1999 Undersecretary of Defense adopts the ANSI/EIA-748 as agency standard on all US DoD acquisition contracts 2005 PMI releases 1st Edition EVM Standard 2009 Weapons Systems Acquisition Reform Act, all US DoD contractors to have fully compliant ANSI/EIA-748B compliant 2011 PMI releases 2nd Edition EVM Standard,PMBOK Releases
Increasing Oversight, Program Management Profession Acknowledged As Industry Experienced Delays and Overruns
2002 Sarbanes Oxley Act 2016 PMIAA – Program Management Improvement and Accountability Act
planned to work (hours/dollars) completed, formulae
Technical Schedule Cost Risk
Budget: $45 Actual: $55 Variance: ($10)
AC= $55 PV=$45 EV=$60 SVAR= $15
SVAR= EV-PV 60-45
CVAR= $5
CVAR= EV-AC 60-55
Source: PMBOK, 5th Edition
Management Reserve Projected Slip
Management Reserve Projected Slip
March Cumulative CVAR: EV-AC ($60-$55) $5 SVAR: EV-PV($60-$45) $15 CPI: EV/AC ($60/$55) 1.09 SPI: EV/PV($60/$45) 1.33 VAC: BAC-EAC ($85-$110) ($25) March Cumulative PV: $45 AC: $55 EV: $60 BAC: $85 EAC: $110 MR: $55 Total Authorized Budget/ Contract Baseline: $140
Source: PMBOK, 5th Edition
# EAC Description EAC Formula EAC Calculation EAC 1 Cost expected to remain constant EAC=BAC/CPI $140/1.09 $128 2 Future work will be accomplished at planned rate (PV) EAC=AC+(BAC-EV) $55+($85-$60) $80 3 Bottom-Up: Initial plan, PV, no longer valid EAC=AC+Bottum-Up ETC $55+55 $110 4 CPI and SPI influence remaining work EAC=AC+((BAC-EV)/(CPI*SPI)) $55+(($85-$60)/(1.09*1.33)) $80
1 2 3 4
Organize The Work: Responsibility Assignment Matrix (RAM)
Source: MIL STD 881-C
RADAR System Receiver Transmitter Antenna Antenna Electronics Antenna Control Transmit/Receive Modules Program Manager
Test IPT Elect IPT MFG IPT Design
Electrical Design
Drafting/Checking
Mech Design
Control Account Control Account Control Account Control Account Control Account
Organizational Breakdown Structure Work Breakdown Structure Level 1 Level 2 Level 3 Reporting
Organize The Work
Level 1 Level 2 Level 3 Reporting Level 4+ Planning and Performing
RADAR System Receiver Transmitter Antenna Antenna Electronics Antenna Control Transmit/Receive Modules Program Manager
Test IPT Elect IPT MFG IPT Design
Electrical Design
Drafting/Checking
Mech Design
Control Account Control Account Control Account Control Account Control Account
Organizational Breakdown Structure Work Breakdown Structure
Tier 0 – Customer/Contract
Specified Milestones
Tier 1 – Program Top Level Summary Schedule
Tier 2 – Integrated Master Schedule
Tier 3 – Detailed IPT Schedules
Tier 4 – Control Accounts
Horizontal/ Vertical
Scope : WBS: Define the work Time Management : Schedule the work
20 20 60 20 20 60 60 60
Cost Management : Distribute/allocate Budgets Risk Management : Plan risk responses
Risk #8
X
incorporated into planning
Earned Value is a Management Tool , when used properly, can successfully measure and manage a project to increase internal and external customer satisfaction