earned value management
play

Earned Value Management Prepared For: PMI-L.I. Chapter Prepared - PowerPoint PPT Presentation

Earned Value Management Prepared For: PMI-L.I. Chapter Prepared By: Jean Cronan Presentation on: 11 January 2017 Learning Objectives Earned Value Background Definitions Establishing a Performance Baseline Performance Management


  1. Earned Value Management Prepared For: PMI-L.I. Chapter Prepared By: Jean Cronan Presentation on: 11 January 2017

  2. Learning Objectives Earned Value • Background • Definitions • Establishing a Performance Baseline • Performance Management • Summary

  3. Background Earned Value –Why Use - Benefits? • Early trending leads to proactive management resolution • Improves customer communications and relationship • Ensures scope planned and risks and budget managed • Creates an open culture within IPT

  4. Background Earned Value – Current Standards • ANSI/EIA-478 • PMI Practice Standard for Earned Value • PMI EVM Community of Practice

  5. Background How Does EVM Relate to PMBOK Process Groups and Knowledge Areas ? Initiate Plan Execute Monitor and Control Establish a Organize Project Direct and Measurement against PMB: Performance through the Manage Work Generate: Measurement Charter against PMB: Change Requests • Baseline (PMB): Conduct Variance Analysis • • Assign Scope • Procurements Control Risks • Responsibilities Management Acquire • through Time • Resources Stakeholder Management Management Cost • Management Risk • Management

  6. Background ANSI/EIA-748 Source: DAU;EMIG

  7. Background 2016 PMIAA – Program Management Improvement and Accountability Act Earned Value -Timeline 2011 PMI releases 2nd Edition EVM Standard,PMBOK Releases 2009 Weapons Systems Acquisition Reform Act, all US DoD contractors to have fully compliant ANSI/EIA-748B compliant 2005 PMI releases 1 st Edition EVM Standard 2002 Sarbanes Oxley Act 1999 Undersecretary of Defense adopts the ANSI/EIA-748 as agency standard on all US DoD acquisition contracts 1998 Initial issue of American National Standards Institute/Electronic Industries Alliance publishes Earned Value Management Systems (EVMS) called ANSI/EIA-A 1991 DoD issues DoD Instruction 5000.2 Defense Acquisition Management Policies; use of EVM on DoD-wide Programs 1972 C/S CSC Joint Implementation Guide launched for use by all military branches 1967 Department of Defense (DoD) creates Cost/Schedule Control System Criteria (C/S CSC) 1950’s Program Evaluation Review Techniques - PERT Increasing Oversight, Program Management Profession Acknowledged As Industry Experienced Delays and Overruns Source: EVMPEDIA, EVM History

  8. Background Earned Value - Summary • Industry Standards Established • Continued Oversight • Increase use of EVM within DoD and Commercial Projects DoD, Commercial Industry, and PMI recognizes EVM as a critical Project Management Tool

  9. Definition Earned Value • Based on: Technical, Schedule, Cost, Risk elements • Measures project performance by comparing work (hours/dollars) planned to work (hours/dollars) completed, formulae • Management Tool • Performance Measurement- what is going on • Performance Management – what can be done

  10. Definition Earned Value – “Demand Diamond” Technical Schedule Cost Risk

  11. Definition Earned Value Budget: $45 Actual: $55 How is this project performing ? Variance: ($10)

  12. Definition Earned Value - Revisit AC= $55 PV=$45 EV=$60 SVAR= $15 SVAR= EV-PV 60-45 CVAR= $5 CVAR= EV-AC 60-55 How is this project performing adding EV ?

  13. Definition Earned Value – Formulae -Variances Source: PMBOK, 5 th Edition

  14. Definition Earned Value – Formulae -Variances Management Reserve Projected Slip

  15. Definition Earned Value – Formulae -Variances Management Reserve Projected Slip March Cumulative March Cumulative PV: $45 CVAR: EV-AC ($60-$55) $5 AC: $55 SVAR: EV-PV($60-$45) $15 EV: $60 CPI: EV/AC ($60/$55) 1.09 BAC: $85 SPI: EV/PV($60/$45) 1.33 EAC: $110 VAC: BAC-EAC ($85-$110) ($25) MR: $55 Total Authorized Budget/ Contract Baseline: $140

  16. Definition Earned Value – Formulae ETC/EAC Source: PMBOK, 5 th Edition

  17. Definition Earned Value – Formulae – ETC/EAC 1 3 4 2 # EAC Description EAC Formula EAC Calculation EAC 1 Cost expected to remain constant EAC=BAC/CPI $140/1.09 $128 Future work will be accomplished at EAC=AC+(BAC-EV) $55+($85-$60) $80 planned rate (PV) 2 Bottom-Up: Initial plan, PV, no longer EAC=AC+Bottum-Up ETC $55+55 $110 3 valid 4 CPI and SPI influence remaining work EAC=AC+((BAC-EV)/(CPI*SPI)) $55+(($85-$60)/(1.09*1.33)) $80

  18. Establishing a Performance Baseline Organize The Work Work Breakdown Structure Level 1 Organizational RADAR System Breakdown Structure Level 2 Antenna Receiver Transmitter Test IPT Transmit/Receive Level 3 Antenna Antenna Control Program Manager Modules Electronics Reporting Elect IPT Design Electrical Design Control Account Control Account Control Account Mech Design Control Account MFG IPT Drafting/Checking Control Account Organize The Work: Responsibility Assignment Matrix (RAM) Source: MIL STD 881-C

  19. Establishing a Performance Baseline Plan The Work Work Breakdown Structure Level 1 Organizational RADAR System Breakdown Structure Level 2 Antenna Receiver Transmitter Test IPT Transmit/Receive Antenna Level 3 Antenna Control Program Manager Modules Electronics Reporting Elect IPT Design Electrical Design Control Account Control Account Level 4+ Mech Design Control Account Control Account Planning and Drafting/Checking MFG IPT Control Account Performing

  20. Establishing a Performance Baseline Planning Techniques • Detail Planning • LOE • % Complete • Apportioned • Rolling Wave • Planning Packages Best Practice: No more than 10% of plan to consist of LOE

  21. Establishing a Performance Baseline Scheduling Tier 0 – Customer/Contract Specified Milestones Horizontal/ Vertical -Accountability Tier 1 – Program Top Level Summary Schedule Customer, Executive Management, Program Office • -Integration Customer/Contract specified milestones • Program major milestones, phases • -Use of Rollingwave One page • Tier 2 – Integrated Master Schedule Further delineation of Tier 1 • Major tasks within each phase • Significant inter-phase events • Task links/Critical path(s) • Tier 3 – Detailed IPT Schedules Further delineation of Tier 2 • End item deliverables, Tests, Services • Functional commitment to IPT • Tier 4 – Control Accounts Work Packages • Earned Value Performance Measurement •

  22. Establishing a Performance Baseline Budgeting Scope : WBS: Define the work Time Management : Schedule the work 20 20 60 Cost Management : 60 20 60 Distribute/allocate Budgets 60 20 Risk Management : Plan risk response s

  23. Establishing a Performance Baseline Incorporating Risk Plans Risk #8 X Identify Risks • Plan Risk Response Approved Reserves • • Perform Qualitative Risk Analysis • Approved Change Request • Perform Quantitative Risk Analysis • Risk Mitigated • Risk Mitigation Leads to Proactive Project Management

  24. Establishing a Performance Baseline Baselined • Ensure no more than 10% level of effort control accounts • Established management reserve, undistributed budget • Management Reserve Log established • Ready to start executing, monitoring/controlling, managing to baseline

  25. Performance Management Managing with Data - What Can Be Done • 10% into project, trend forecasts future performance • Focus on indicators that reveal trends • Reporting includes root cause/corrective action plans • Rigorously review Risk Register, ensure mitigation steps incorporated into planning • Utilize data to drive projects to success Ensures Oxley Act of 2002 Is Being Satisfied

  26. Summary • Early trending leads to proactive management resolution • Improves customer communications and relationship • Ensures scope planned and risks and budget managed • Creates an open culture within IPT Earned Value is a Management Tool , when used properly, can successfully measure and manage a project to increase internal and external customer satisfaction

  27. Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend