may 6 2016 erika murphy p e or jwc project manager genset
play

May 6, 2016 Erika Murphy, P.E. (OR) JWC Project Manager Genset - PowerPoint PPT Presentation

May 6, 2016 Erika Murphy, P.E. (OR) JWC Project Manager Genset Installation August 27, 2015 Why is Backup Power Important? Power outages are everyday occurrences in the US Can take hours to weeks to months to restore power Short of


  1. May 6, 2016 Erika Murphy, P.E. (OR) JWC Project Manager

  2. Genset Installation August 27, 2015

  3. Why is Backup Power Important?  Power outages are everyday occurrences in the US  Can take hours to weeks to months to restore power  Short of an earthquake, power loss is the WTP’s biggest vulnerability  Expectation that drinking water will come online faster than power  AWWA Best Management Practices recommend a backup power source for minimum 40% - 50% WTP capacity  CRITICAL FACILITY: One of our missions as a water provider is reliability. This project is paramount in ensuring reliability.

  4. Partnership Opportunity  Local power provider is Portland General Electric (PGE)  Dispatchable Standby Generation (DSG)  With 5MW of JWC power, the DSG program achieved 100MW of dispatchable standby power  PGE provided funding incentives at completion of project for additional equipment ($222,000) and aid in construction ($1,117,850 for 5MW)  PGE contract is for 10 years, with automatic 1-year renewals thereafter unless terminated

  5. PGE DSG Benefits  While under contract, PGE provides:  Monthly testing of the generators under load  Diesel fuel – testing and fill-ups  Preventative maintenance on generators and switchgear  Engine tune-ups and general wear repairs  Emissions DEQ permit modifications and renewals  24/7 monitoring and assistance  PGE may use the generators to offset peak loading (<50 hours/year)  Emergency operations by JWC always take priority

  6. Project Schedule Generator Generator Commissioning and Commissioning and Construction Begins Load Testing by JWC Start-Up by PGE March 9, 2015 March 14, 2016 December 7, 2015 2015 Apr 2016 Mar May Jun Jul Mar Aug Oct Feb Apr Sep Nov Dec Jan Rough Grading & Auger Cast Piles Substantial Final Completion Conduit Installation Completion March 14, 2016 Building Structure Generator Delivery Switchgear Delivery Building Finishing Raw Water Pump Station Power Switch WTP Power Feed Switch

  7. Total Project Costs Approved Project Budget $ 6,000,000 PGE Aid in Construction $ 1,383,850 PGE Accelerated Schedule Contribution $ 150,000 Total Available Budget $ 7,533,850 Construction $ 6,191,740 Engineering $ 825,674* Initial Diesel Fuel Tank Fill $ 22,994 Current Project Cost $ 7,040,408 *not final

  8. Auger Cast Pile Installation

  9. Conduit Duct Banks – Pile Supported

  10. Fuel Tank Piping

  11. South Elevation

  12. View from the WTP

  13. Generator and Muffler

  14. Project Challenges

  15. Project Challenges What exactly is a non-segregated phase bus duct?

  16. Project Challenges What exactly is a non-segregated phase bus duct?

  17. Project Challenges What exactly is a non-segregated phase bus duct? assembly of bus conductors with joints, connections, and insulating supports without interphase barriers

  18. Project Challenges

  19. Conduit Trench Easements - Multiple Property Owners

  20. Project Challenges Permitting

  21. Fuel Considerations How much fuel is the right amount?

  22. Fuel Considerations  After a large seismic event, fuel will be hard to get  Roads will be out  Everyone will need fuel for utility repairs  Maintaining fuel quality  Diesel fuel degrades over time  Biological growth and moisture create issues  Our solution?  48 hours of fuel  Monthly fuel testing  Fuel polishing system

  23. 15,000 Gallon Fuel Tank

  24. Commissioning Party  Joint Water Commission  Carollo Engineers  WTP Operators/Electricians  2KG Contractors  JWC SCADA Technician  Design Electric  Peterson Caterpillar  PGE DSG  R&W Engineering  PGE Distribution  CurrenTechnologies  Taurus Power & Controls

  25. Commissioning Party  Joint Water Commission  Carollo Engineers  WTP Operators/Electricians  2KG Contractors  JWC SCADA Technician  Design Electric  Peterson Caterpillar  PGE DSG  R&W Engineering  PGE Distribution  CurrenTechnologies  Taurus Power & Controls

  26. Commissioning and Load Testing

  27. Commissioning and Load Testing

  28. And everything went perfect

  29. Commissioning and Load Testing

  30. Safety in Design

  31. Safety in Design SWITCHGEAR ROOM GENERATOR CONTROL 12.47kV ROOM ROOM 480V

  32. Murphy’s Law March 2016

  33. Murphy’s Law March 2016 FAILED TEST

  34. Murphy’s Law March 2016 FAILED TEST NEXT SCHEDULED TEST

  35. Murphy’s Law March 2016 FAILED TEST NEXT WIND SCHEDULED STORM TEST

  36. Commissioning and Load Testing

  37. Commissioning and Load Testing

  38. Success! ~3.2MW Load at WTP/SHPS 52MSG – Main Switchgear for WTP 52SH – Spring Hill Pump Station

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend