May 6, 2016 Erika Murphy, P.E. (OR) JWC Project Manager Genset - - PowerPoint PPT Presentation

may 6 2016 erika murphy p e or jwc project manager genset
SMART_READER_LITE
LIVE PREVIEW

May 6, 2016 Erika Murphy, P.E. (OR) JWC Project Manager Genset - - PowerPoint PPT Presentation

May 6, 2016 Erika Murphy, P.E. (OR) JWC Project Manager Genset Installation August 27, 2015 Why is Backup Power Important? Power outages are everyday occurrences in the US Can take hours to weeks to months to restore power Short of


slide-1
SLIDE 1

May 6, 2016 Erika Murphy, P.E. (OR) JWC Project Manager

slide-2
SLIDE 2

Genset Installation

August 27, 2015

slide-3
SLIDE 3

Why is Backup Power Important?

 Power outages are everyday occurrences in the US  Can take hours to weeks to months to restore power  Short of an earthquake, power loss is the WTP’s biggest vulnerability  Expectation that drinking water will come online faster than power  AWWA Best Management Practices recommend a backup power

source for minimum 40% - 50% WTP capacity

 CRITICAL FACILITY: One of our missions as a water provider is

  • reliability. This project is paramount in ensuring reliability.
slide-4
SLIDE 4

 Local power provider is Portland General Electric (PGE)  Dispatchable Standby Generation (DSG)  With 5MW of JWC power, the DSG program achieved 100MW of

dispatchable standby power

 PGE provided funding incentives at completion of project for

additional equipment ($222,000) and aid in construction ($1,117,850 for 5MW)

 PGE contract is for 10 years, with automatic 1-year renewals

thereafter unless terminated

Partnership Opportunity

slide-5
SLIDE 5

 While under contract, PGE provides:

  • Monthly testing of the generators under load
  • Diesel fuel – testing and fill-ups
  • Preventative maintenance on generators and switchgear
  • Engine tune-ups and general wear repairs
  • Emissions DEQ permit modifications and renewals
  • 24/7 monitoring and assistance

 PGE may use the generators to offset peak loading (<50 hours/year)

 Emergency operations by JWC always take priority

PGE DSG Benefits

slide-6
SLIDE 6

2015 2016

Mar

Construction Begins

March 9, 2015

Substantial Completion

March 14, 2016

Final Completion

Rough Grading & Auger Cast Piles Apr May Jun Jul Aug Sep Oct Nov Dec Feb Jan Mar

Generator Commissioning and Start-Up by PGE

December 7, 2015

Project Schedule

Apr

Generator Commissioning and Load Testing by JWC

March 14, 2016 Building Structure Generator Delivery Switchgear Delivery Raw Water Pump Station Power Switch WTP Power Feed Switch Building Finishing Conduit Installation

slide-7
SLIDE 7

Approved Project Budget $ 6,000,000 PGE Aid in Construction $ 1,383,850 PGE Accelerated Schedule Contribution $ 150,000 Total Available Budget $ 7,533,850 Construction $ 6,191,740 Engineering $ 825,674* Initial Diesel Fuel Tank Fill $ 22,994 Current Project Cost $ 7,040,408

Total Project Costs

*not final

slide-8
SLIDE 8

Auger Cast Pile Installation

slide-9
SLIDE 9

Conduit Duct Banks – Pile Supported

slide-10
SLIDE 10

Fuel Tank Piping

slide-11
SLIDE 11

South Elevation

slide-12
SLIDE 12

View from the WTP

slide-13
SLIDE 13

Generator and Muffler

slide-14
SLIDE 14

Project Challenges

slide-15
SLIDE 15

Project Challenges

What exactly is a non-segregated phase bus duct?

slide-16
SLIDE 16

Project Challenges

What exactly is a non-segregated phase bus duct?

slide-17
SLIDE 17

Project Challenges

What exactly is a non-segregated phase bus duct?

assembly of bus conductors with joints, connections, and insulating supports without interphase barriers

slide-18
SLIDE 18

Project Challenges

slide-19
SLIDE 19
slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22

Conduit Trench

Easements - Multiple Property Owners

slide-23
SLIDE 23

Permitting

Project Challenges

slide-24
SLIDE 24

Fuel Considerations

How much fuel is the right amount?

slide-25
SLIDE 25

 After a large seismic event, fuel will be hard to get

 Roads will be out  Everyone will need fuel for utility repairs

 Maintaining fuel quality

 Diesel fuel degrades over time  Biological growth and moisture create issues

 Our solution?

 48 hours of fuel  Monthly fuel testing  Fuel polishing system

Fuel Considerations

slide-26
SLIDE 26

15,000 Gallon Fuel Tank

slide-27
SLIDE 27

 Joint Water Commission  WTP Operators/Electricians  JWC SCADA Technician  Peterson Caterpillar  R&W Engineering  CurrenTechnologies  Carollo Engineers  2KG Contractors  Design Electric  PGE DSG  PGE Distribution  Taurus Power & Controls

Commissioning Party

slide-28
SLIDE 28

 Joint Water Commission  WTP Operators/Electricians  JWC SCADA Technician  Peterson Caterpillar  R&W Engineering  CurrenTechnologies  Carollo Engineers  2KG Contractors  Design Electric  PGE DSG  PGE Distribution  Taurus Power & Controls

Commissioning Party

slide-29
SLIDE 29

Commissioning and Load Testing

slide-30
SLIDE 30

Commissioning and Load Testing

slide-31
SLIDE 31

And everything went perfect

slide-32
SLIDE 32

Commissioning and Load Testing

slide-33
SLIDE 33

Safety in Design

slide-34
SLIDE 34

Safety in Design

SWITCHGEAR ROOM 12.47kV GENERATOR ROOM CONTROL ROOM 480V

slide-35
SLIDE 35

Murphy’s Law

March 2016

slide-36
SLIDE 36

Murphy’s Law

March 2016

FAILED TEST

slide-37
SLIDE 37

Murphy’s Law

March 2016

NEXT SCHEDULED TEST

FAILED TEST

slide-38
SLIDE 38

Murphy’s Law

March 2016

FAILED TEST

NEXT SCHEDULED TEST

WIND STORM

slide-39
SLIDE 39

Commissioning and Load Testing

slide-40
SLIDE 40

Commissioning and Load Testing

slide-41
SLIDE 41

Success!

52MSG – Main Switchgear for WTP 52SH – Spring Hill Pump Station ~3.2MW Load at WTP/SHPS