Earl Pumping Station Community Liaison Working Group
24 September 2018
Earl Pumping Station Community Liaison Working Group 24 September - - PowerPoint PPT Presentation
Earl Pumping Station Community Liaison Working Group 24 September 2018 Construction update 2 EARPS Earl Pumping Station 3 EARL PUMPIN PING S G STATIO ION PROG OGRES ESS 4 Current Progress fence: Silo slab Bundwall and Started
Earl Pumping Station Community Liaison Working Group
24 September 2018
2
3
Earl Pumping Station
4
EARL PUMPIN PING S G STATIO ION –PROG OGRES ESS
5
Current Progress
Geomix: Completed a further 12 panels and the 2 soft panels as well as continuing backfilling the bound trenches. fence: Started installation of fence line Silo slab Bundwall and piping: 95% of the bund wall and pipe connections completed
Silo slab 1 to 2 Pipe
duct connection: 95% finished installation
connection of pipes between the two silo slabs. UKPN substation: 90% completion of palisade fencing around UKPN sub-station Croft street hoarding: 50% finished installation new hoarding at croft street
6
What w we a are bu building ng
7
September 2018
8
Earl P Pumpin ing S Statio tion
September 2018
9
September 2018
10
September 2018
11
September 2018
12
13
Construction Work
Muck bin construction Foul water pipe diversion Offices in operation Grout Bag Trials Sewer coring Platform partly constructed
14
Ov Over p pumpi ping a and si site d e drainage
15
Platform form exca cavation,
pumping e exca cavation
and local se al sewer er d diver ersi sions
16
Muck b k bin c constr truc uctio tion
17
New w workin king e environme ment
Start of shift briefing Staff in the new office Welfare room
18
Obstructio ion cor
ing Dia iaphragm wall ll construct uction Geom eomix ix
Upcoming work
19
Upcomin ing W Work k
Working Hours Standard Extended Monday – Friday 08:00 – 18:00 Until 22:00 Saturday 08:00 – 13:00 Until 17:00
1 hour allowed before & after for mobilisation
Programme Overview
2018 2019
May June July Aug Sept Oct Nov Dec Jan Feb March April
Substations installation cable pulling (excavation on Chilton Grove and Croft Street) Temporary sewer diversion construction Platform construction (including muck bin) Water main diversion on Croft Street Coring of existing Earl sewer (obstruction coring) Geomix Diaphragm wall construction Standard Working Hours (08:00 - 18:00) Monday to Friday, (08:00 - 13:00) Saturday Extended Working Hours (08:00 - 22:00) Monday to Friday, (08:00 - 13:00) Saturday
20
Earl Pumping Station site
Entrance on Yeoman Street Exit on Croft Street Thames Water access to pumping station Temporary exit during road closure works Croft Street road closure Note: abnormal loads will be allowed to use Yeoman Street gate as an exit
Traf affic Mo Movem ement
21
Traffic Update – works completed 6-7 September
22
Vehi ehicle Ho e Holding A Area rea – Bes estwood S Street reet
CVB will use part of the bus lane on Bestwood Street as a vehicle holding area to manage deliveries to the site more efficiently. Vehicles will be registered on arrival, checked for safety compliance and then leave for site as soon as is reasonably practical.
Duration: May 2018 to December 2021 Wor
hou
Monday to Friday, 07:00 – 18:00 Saturday, 07:00 - 13:00 What w we will do:
movements
idling within holding area
Vehicle holding area
23
24
Noise e and Ai Air Qu Quali lity no exceedances
Noise Monitor Air Quality Monitor
Month Noise Air Quality S61 Exceedances 24h PM10 Exceedance Jan-18 Feb-18 Mar-18 Apr-18
25
Od Odour Ma Manag agement
To minimise this, odour will be managed in the following ways:
covered and removed from site as soon as possible
deal effectively with odour sources
confirm control measures are working
mask odour when necessary When excavating, odour from ground conditions may become more noticeable
26
27
RIV IVER T TIME IMES – Summe ummer Editi dition n del eliver ered ed
A digital copy of this publication can be found here https://www.tideway.london/media/4081/river-times_east_summer_18.pdf
28
Staff C Char arity 20 2018 T 8 Tid ideway E Eas ast
Great Ormond Street Hospital was chosen by staff in June to be this year's chosen charity
The money was raised through a variety of staff activities including a raffle and a World Cup Sweepstake
Since April, Tideway East has raised over £2,000
29
Charity ity
In July, five members of staff from Chambers Wharf completed the British 10K run. The team ran in support of the Deborah Ubee Trust, a Greenwich based mental health charity neighbouring our Greenwich Pumping Station site. The team managed to raise over £800
30
Women in Engineering 2018
#raisethebar
Brownies raise the bar
As part of Women in Engineering Week 2018 in June, Tower Hamlets Guides and Brownies visited Chambers Wharf, and we visited a Brownie pack in Bow. They learnt that women can make a positive impact in Engineering and Construction - as well as taking part in some fun tasks. After a quick talk about engineering and the Tideway project, the girls got stuck into lots
engineers. These included building spaghetti and marshmallow towers, balloon hovercrafts, lava lamps and lemon fizz volcanoes. And of course a challenge to ‘raise the bar’
31
World of Work visit from students taking part in the National Citizen Service summer programme ‘The Challenge’ They were working on a project to raise money for charity tackling domestic violence. They practised their Dragon’s Den style presentation with us.
Appren entic ices eships ips
joined our team
studying at the London Design Engineering UTC
Work e exper erien ience
Four work experience students with us over the Summer. Two from the St Michael's College, one from Walworth Academy and one from East Young Leaders Academy (EYLA). Here’s some of their feedback:
“Thanks to my work experience I have been able to develop a wide range of skills, including working as part of a team, listening and
“Getting a feel of engineering at Tideway has really encouraged me to go on and work in engineering.” “Engineering is now definitely an option for my future.”
32
Foresh shor
e clean an-up up King Edward M rd Memori
Fore reshore
Site
Tideway East volunteers headed down to the foreshore in July to clean up plastic rubbish. The team made a great effort and were able to collect many bags full of plastic. This waste is taken away and properly disposed of.
Plastic is a hazardous material polluting our waterways. It’s putting wildlife at risk, harming and in some cases mutating aquatic life.
33
Foresh shor
e clean an-up o p on th the I e Isl sle e of D Dogs s
Staff volunteers, accompanied by the neighbouring Ecology Consultancy, based at Bermondsey Wall West, took to the Isle of Dogs foreshore to remove plastic waste embedded within its beach. Within the fifty bags of plastic rubbish collected they found a bag of Smiths salted peanuts with an expiry date of January 1984 - Which makes them 34 years old!
Newcastle Draw Dock - August 2018
34
More information can be found at: https://www.tideway.london/our-community/foreshore-festival/Shadwell-Activities
35
Any questions please contact the Tideway Helpdesk on: Telephone: 08000 3 00 308080 080 Email: Helpdesk@Tideway.London
Thanks for attending Any questions?
37
THANK YOU
Earl Pumping Station Community Liaison Working Group
21 May 2018