Heathwall Pumping Station & Kirtling Street Community Liaison Working Group Thursday, 5 September 2019 1 Agenda Apologies Minutes of last meeting Heathwall Pumping Station site progress Heathwall Pumping Station environmental


slide-1
SLIDE 1

1

Heathwall Pumping Station & Kirtling Street Community Liaison Working Group

Thursday, 5 September 2019

slide-2
SLIDE 2

2

Agenda

  • Apologies
  • Minutes of last meeting
  • Heathwall Pumping Station site progress
  • Heathwall Pumping Station environmental update
  • Kirtling Street site progress
  • Kirtling Street environmental update
  • Community relations
  • Any other business
slide-3
SLIDE 3

3

HEATHWALL PUMPING STATION UPDATE

Ponciano ciano Perez ez – Proje ject t Manager ager

slide-4
SLIDE 4

4

Heathwall Pumping Station Overview

Camp shed CSO Shaft Pumping Station Shaft Site Offices

slide-5
SLIDE 5

5

Heathwall Pumping Station Progress In-land Combined sewage overflow shaft

June 2019 August 2019

  • We have installed 29 segment rings
  • CSO shaft at 30m depth
  • Excavated down 28.5 metres, producing 6,565m3 of excavated material
  • Once complete, the shaft will be 47m deep
  • Muck away via river commenced
  • Mooring piles and campshed complete for Battersea barge and FLO muckaway strategy
slide-6
SLIDE 6

6

Heathwall Pumping Station Progress Pumping Station Shaft

June 2019 August 2019

  • 13 Heathwall Pumping Station (HPS) Shaft concrete rings have been installed
  • HPS shaft at 14m depth
  • Moving to Sprayed Concrete Lining (SCL) method for remainder of shaft
  • 2,154m3 material has been excavated, all disposed by River
slide-7
SLIDE 7

7

Heathwall Pumping Station Lookahead (Sept – Dec ‘19)

  • September:
  • HPS shaft caisson installation to be complete this week
  • Commence SCL on HPS shaft next week (24/5 working)
  • CSO shaft 24/5 caisson installation next week
  • CSO shaft to commence SCL 24/5 week commencing 23/9
  • October:
  • CSO shaft SCL ongoing
  • HPS shaft SCL to be completed
  • HPS shaft base and culvert portal to be constructed
  • November:
  • Complete HPS shaft base and portal
  • Commence connection culvert SCL 24/5 working
  • CSO shaft SCL ongoing
slide-8
SLIDE 8

8

HEATHWALL PUMPING STATION ENVIRONMENTAL UPDATE

IRAM MIRZA – ENVIRONMENTAL ADVISOR

slide-9
SLIDE 9

9

Heathwall ll Pumping St Station – Air ir Qualit ity (14 (14 Jun Jun – 5 5 Se Sep 201 2019)

6 x Exceedances No Exceedance Air Quality Monitors Noise Monitors

Exceedances:

24 June 2019

  • Sub-Contractor demobilising from the West compound

11 July 2019

  • Sweeping directly under the monitor in the west Compound

27 July 2019 & 8 August 2019

  • No obvious dust creating activities occurred at these times

23 August 2019 & 3 September 2019

  • Exceedance caused by saw dust from timber cutting without a vacuum on the West compound

Riverlight One

slide-10
SLIDE 10

10

Heathwall ll Pumping St Station – No Nois ise (14 (14 Jun Jun – 5 5 Se Sep 20 2019 19)

Air Quality Monitors Noise Monitors

No Exceedance No Exceedance

Riverlight One

slide-11
SLIDE 11

11

KIRTLING STREET PROJECT UPDATE

Noel el Cooper per – Tunnel nnel Constr struct uction ion Manager ager

slide-12
SLIDE 12

Tunnelling Progress 5 September 2019

2,109 3,804 910 1,635

slide-13
SLIDE 13

London Heliport Falconbrook Pumping Station

TBM B West 2,109R 3,804m

slide-14
SLIDE 14

TBM C East 910R 1,635m

Albert Embankment

slide-15
SLIDE 15

15

slide-16
SLIDE 16

Bar arge movements so so far

800,000t of spoil removed by barge 560 Barge movements since the start

  • f tunnelling

40,000 heavy goods vehicles taken off the road 25,500 Segments delivered to site 6,400 heavy goods vehicles taken

  • ff the road
slide-17
SLIDE 17
slide-18
SLIDE 18

How we ar are man anagin ing th the si site

  • Extra acoustic blankets around conveyor transfer

hopper and the main conveyor hopper in Brooks Court

  • Mixing new geology with London Clay in Brooks

Court when possible

  • Additional acoustic barriers installed around chain

conveyor

  • Ongoing liaison with manufacturer over sound

from chain conveyor

  • Plant operatives continually briefed to allow muck

to pile up in Brooks Court where possible

  • Conveyor alarm switched to flashing lights outside
  • f daylight hours
  • White noise alarms on plant
  • Muck bay damped down when safe to do so

during dry weather to limit dust

  • Dedicated road sweeper both inside and outside

site

slide-19
SLIDE 19

Tid ideway Central l Tar arget Programme

Kirtling Street Heathwall Pumping Station

Programme Overview

2019 2020 2021 2022 2023 2024

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Kirtling Street Tunnelling Secondary lining Site reinstatement Reinstate houseboats Heathwall Pumping Station Inland shaft excavation Cofferdam shaft excavation Connection tunnelling works Shaft lining works Inland Interception chambers Cofferdam interception chamber Site reinstatement and Thames path connection Project wide system commissioning

slide-20
SLIDE 20

20

KIRTLING STREET ENVIRONMENTAL UPDATE

IRAM MIRZA – ENVIRONMENTAL ADVISOR

slide-21
SLIDE 21

21

Kirt irtli ling Str Street Envir ironment – Air ir Quali lity (14 (14 Jun Jun – 5 5 Se Sep 20 2019 19)

1 Exceedance No Exceedance

Air Quality Monitors Noise Monitors Brooks Court

R6 R4 R5 Exceedances:

29 June 2019

  • This exceedance was not caused by

Tideway works, the exceedance was most likely caused by non-Tideway resurfacing road works taking place close to the site.

slide-22
SLIDE 22

22

Kirt irtli ling Str Street Envir ironment – No Nois ise (14 (14 Jun Jun – 5 5 Se Sep 20 2019 19)

No Exceedance No Exceedance

Air Quality Monitors Noise Monitors Brooks Court

R4 R4 R5 R6

slide-23
SLIDE 23

23

55 60 65 70 75 80 01/06/2019 02/06/2019 03/06/2019 04/06/2019 05/06/2019 06/06/2019 07/06/2019 08/06/2019 09/06/2019 10/06/2019 11/06/2019 12/06/2019 13/06/2019 14/06/2019 15/06/2019 16/06/2019 17/06/2019 18/06/2019 19/06/2019 20/06/2019 21/06/2019 22/06/2019 23/06/2019 24/06/2019 25/06/2019 26/06/2019 27/06/2019 28/06/2019 29/06/2019 30/06/2019 Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun

dB(A)

Daytime (Core) - June'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-24
SLIDE 24

24

55 57 59 61 63 65 67 69 71 73 75 01/06/2019 02/06/2019 03/06/2019 04/06/2019 05/06/2019 06/06/2019 07/06/2019 08/06/2019 09/06/2019 10/06/2019 11/06/2019 12/06/2019 13/06/2019 14/06/2019 15/06/2019 16/06/2019 17/06/2019 18/06/2019 19/06/2019 20/06/2019 21/06/2019 22/06/2019 23/06/2019 24/06/2019 25/06/2019 26/06/2019 27/06/2019 28/06/2019 29/06/2019 30/06/2019 Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun

dB(A)

Evening (Extended) - June'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-25
SLIDE 25

25

54 56 58 60 62 64 66 68 70 72 01/06/2019 02/06/2019 03/06/2019 04/06/2019 05/06/2019 06/06/2019 07/06/2019 08/06/2019 09/06/2019 10/06/2019 11/06/2019 12/06/2019 13/06/2019 14/06/2019 15/06/2019 16/06/2019 17/06/2019 18/06/2019 19/06/2019 20/06/2019 21/06/2019 22/06/2019 23/06/2019 24/06/2019 25/06/2019 26/06/2019 27/06/2019 28/06/2019 29/06/2019 30/06/2019 Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun

dB(A)

Night - June'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-26
SLIDE 26

26

55 60 65 70 75 80 01/07/2019 02/07/2019 03/07/2019 04/07/2019 05/07/2019 06/07/2019 07/07/2019 08/07/2019 09/07/2019 10/07/2019 11/07/2019 12/07/2019 13/07/2019 14/07/2019 15/07/2019 16/07/2019 17/07/2019 18/07/2019 19/07/2019 20/07/2019 21/07/2019 22/07/2019 23/07/2019 24/07/2019 25/07/2019 26/07/2019 27/07/2019 28/07/2019 29/07/2019 30/07/2019 31/07/2019 Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

dB(A)

Daytime (Core) - July'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-27
SLIDE 27

27

55 57 59 61 63 65 67 69 71 73 75 01/07/2019 02/07/2019 03/07/2019 04/07/2019 05/07/2019 06/07/2019 07/07/2019 08/07/2019 09/07/2019 10/07/2019 11/07/2019 12/07/2019 13/07/2019 14/07/2019 15/07/2019 16/07/2019 17/07/2019 18/07/2019 19/07/2019 20/07/2019 21/07/2019 22/07/2019 23/07/2019 24/07/2019 25/07/2019 26/07/2019 27/07/2019 28/07/2019 29/07/2019 30/07/2019 31/07/2019 Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

dB(A)

Evening (Extended) - July'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-28
SLIDE 28

28

55 57 59 61 63 65 67 69 71 73 01/07/2019 02/07/2019 03/07/2019 04/07/2019 05/07/2019 06/07/2019 07/07/2019 08/07/2019 09/07/2019 10/07/2019 11/07/2019 12/07/2019 13/07/2019 14/07/2019 15/07/2019 16/07/2019 17/07/2019 18/07/2019 19/07/2019 20/07/2019 21/07/2019 22/07/2019 23/07/2019 24/07/2019 25/07/2019 26/07/2019 27/07/2019 28/07/2019 29/07/2019 30/07/2019 31/07/2019 Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

dB(A)

Night - July'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-29
SLIDE 29

29

55 60 65 70 75 80 01/08/2019 02/08/2019 03/08/2019 04/08/2019 05/08/2019 06/08/2019 07/08/2019 08/08/2019 09/08/2019 10/08/2019 11/08/2019 12/08/2019 13/08/2019 14/08/2019 15/08/2019 16/08/2019 17/08/2019 18/08/2019 19/08/2019 20/08/2019 21/08/2019 22/08/2019 23/08/2019 24/08/2019 25/08/2019 26/08/2019 27/08/2019 28/08/2019 29/08/2019 30/08/2019 Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri

dB(A)

Daytime (Core) - August'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-30
SLIDE 30

30

55 57 59 61 63 65 67 69 71 73 75 01/08/2019 02/08/2019 03/08/2019 04/08/2019 05/08/2019 06/08/2019 07/08/2019 08/08/2019 09/08/2019 10/08/2019 11/08/2019 12/08/2019 13/08/2019 14/08/2019 15/08/2019 16/08/2019 17/08/2019 18/08/2019 19/08/2019 20/08/2019 21/08/2019 22/08/2019 23/08/2019 24/08/2019 25/08/2019 26/08/2019 27/08/2019 28/08/2019 29/08/2019 30/08/2019 Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri

dB(A)

Evening (Extended) - August'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-31
SLIDE 31

31

54 56 58 60 62 64 66 68 70 72 01/08/2019 02/08/2019 03/08/2019 04/08/2019 05/08/2019 06/08/2019 07/08/2019 08/08/2019 09/08/2019 10/08/2019 11/08/2019 12/08/2019 13/08/2019 14/08/2019 15/08/2019 16/08/2019 17/08/2019 18/08/2019 19/08/2019 20/08/2019 21/08/2019 22/08/2019 23/08/2019 24/08/2019 25/08/2019 26/08/2019 27/08/2019 28/08/2019 29/08/2019 30/08/2019 Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri

dB(A)

Night - August'19

KRTST-NM1 HEAPS-NM2 KRTST Trigger HEAPS Trigger

slide-32
SLIDE 32

32

Compensation an and Mitig itigation

CENTRAL REGION ICP CLAIMS JAN 2018 - DATE CLAIMS SUBMITTED : 24 REJECTED : 3 12% APPROVED : 21 88% GONE TO APPEAL : 2 8%

How to make a claim if you are affected by Tideway’s work

Who do I go to for advise?

  • Independent Advisory Service (IAS) Helpline for independent advise: 0800 917 8845 or

info@tidewayias.co.uk

  • Tideway’s Compensation and Mitigation Lead, Louise Walsh, for personal assistance and

advice: via Tideway Helpdesk 08000 30 80 80 or helpdesk@tideway.london or direct 07971 077165 or louise.walsh@tideway.london

How do I submit my claim?

  • Louise can submit your claim to the Independent Compensation Panel (ICP) on your

behalf or

  • You can submit your claim direct to the ICP: admin@tidewayicp.london
  • The IAS can send you a claim form, or you can download a claim form off the Tideway

website

slide-33
SLIDE 33

33

COMMUNITY ENGAGEMENT

ALICK WHITFIELD – COMMUNITY RELATIONS MANAGER

slide-34
SLIDE 34

34

Complaints & Enquiries (June - September 2019)

33% 66%

Heathwall Pumping Station Complaints & Enquiries Complaints Enquiries

Total - 6

33% 67%

Heathwall Pumping Station Complaints Barges Lighting

93% 6% 1%

Kirtling Street Complaints & Enquiries March - June 2019

Complaints Enquiries Invalid complaints

93% 2% 2% 1% 1% 1%

Kirtling Street Complaints Breakdown

Noise Lighting Acoustic Shed Doors open Dust Operative Behaviour Engine Idling

Total - 124 Total - 117 Total - 3

slide-35
SLIDE 35

35

Community Engagement

236

STEM hours

394 810

Community Investment Programme hours

21

Schools

586

Beneficiaries

Activities Round Up May – September 2019

312

slide-36
SLIDE 36

36

Community Engagement 20 2019 19

  • Litter Survey and Clean-up in with Thames21 in Battersea
  • SPIRAL Education programme – careers workshops with local schools
  • Attending jobs fairs across Central area
  • Bounce Back programme to get ex-offenders into work
  • 15 Work Experience places for students within the Tideway Central

boroughs for Summer 2019, more planned for the Autumn

  • Supporting the South London Cares activity programme for the elderly
  • STEM Ambassador Training
  • London Youth Rowing and Breaking Barriers (from this month)

If you have any suggestions for community investment, please contact us via the Tideway Helpdesk

slide-37
SLIDE 37

37

AOB

slide-38
SLIDE 38

38

THANK YOU Contact details: