dundalk marine terminal remediation community
play

Dundalk Marine Terminal Remediation Community Participation Working - PowerPoint PPT Presentation

Dundalk Marine Terminal Remediation Community Participation Working Group Presentation January 8, 2014 Update on Remedy Implementation Corrective Measures Implementation Schedule updated quarterly in 2013; submitted to MDE 13 th Street


  1. Dundalk Marine Terminal Remediation Community Participation Working Group Presentation January 8, 2014

  2. Update on Remedy Implementation • Corrective Measures Implementation Schedule updated quarterly in 2013; submitted to MDE • 13 th Street Storm Drain Rehabilitation Project Construction Completion Report submitted to MDE in June 2013 • Supplemental Data Report for the Heave Investigation and Minimization Study submitted to MDE in June 2013 • Continued monthly coordination calls with MDE MDE provides oversight of Remedy implementation 2 2

  3. Update on Construction Activities • Design of truck wash station and storage tank complete; construction scheduled for 2014 • All 15 th Street Storm Drain vault installations complete A storage tank will be added to existing tanks • Storm Drains relined • 13 th Street, 13.5 Street: performing post- construction inspection and maintenance • Phases 1 and 2 of 15 th Street relining complete; Phase 3 scheduled for 2014 Installation of manhole at 15 th Street storm drain 15 th street storm drain relining in progress Remedy implementation on schedule / maintenance on-going 3 3

  4. Continued Monitoring and Maintenance Air • Monitoring of air at perimeter of Terminal since 2007; no detections of hexavalent chromium from COPR in perimeter air monitors Groundwater • Groundwater is monitored on semi-annual basis in 34 wells located at perimeter of COPR fill area; results confirm that hexavalent chromium is not leaving site boundary in groundwater at unacceptable levels Storm water • Storm water is monitored quarterly from 12 storm drain outfalls and outfall from treatment plant; final remedy addresses storm water Drinking Water • Drinking water is routinely monitored; no detections of hexavalent chromium in drinking water at Terminal Surface Cover • On-going Surface Cover inspection program for COPR fill area; 30 acres of surface cover repaired since 2005 Monitoring programs measure effectiveness of remedy 4

  5. Continued Success • Visual inspections and routine maintenance of storm drains demonstrate effectiveness of containment • Air monitoring program demonstrates no COPR being transported through the air • Demonstrated effectiveness of surface cover program and engineering controls • Semi-annual groundwater sampling continues to show no off-site movement of hexavalent chromium 5

  6. Storm Drain Repair Schedule 2013 2014 2015 Clean & Inspect 15 th Street Storm Drain Repair Clean & Inspect 14 th Street Storm Drain Repair 12 th Street Storm Drain Repair Clean & Inspect Clean & Inspect 12.5 th Street Storm Drain Repair Schedule submitted to MDE 6

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend