Dominion Blvd. Reconstruction ASHE Greater Hampton Roads Chapter - - PowerPoint PPT Presentation

dominion blvd reconstruction
SMART_READER_LITE
LIVE PREVIEW

Dominion Blvd. Reconstruction ASHE Greater Hampton Roads Chapter - - PowerPoint PPT Presentation

Dominion Blvd. Reconstruction ASHE Greater Hampton Roads Chapter Site Visit September 27, 2016 Kevin Lundgren, PE, Mike Prezioso, PE, CCM Victor Ryzhikov, PE, SE Project Manager Project Manager Segmental Bridge Specialist City of Chesapeake


slide-1
SLIDE 1

1

Dominion Blvd. Reconstruction

ASHE Greater Hampton Roads Chapter Site Visit September 27, 2016

Kevin Lundgren, PE, Mike Prezioso, PE, CCM Victor Ryzhikov, PE, SE Project Manager Project Manager Segmental Bridge Specialist City of Chesapeake MBP, Inc. WSP Parsons Brinkerhoff

slide-2
SLIDE 2

Dominion Boulevard Reconstruction

2

  • Owner: City of Chesapeake, Virginia (Locally

Administered Project – largest in the state)

  • Design: Parsons Brinckerhoff
  • Construction Engineering/Inspection: MBP
  • Contractors: Dominion Blvd Constructors

– McLean Contracting – Bryant Contracting – R. R. Dawson Bridge – E. V. Williams

slide-3
SLIDE 3

Project Timeline

  • Start Design (Parsons Brinckerhoff): 2004
  • Design Public Hearing: Aug 2008
  • FoNSI: Mar 2009
  • Advertisement: Jul 2012
  • Contractor NTP: Jan 2013
  • Fixed Completion Date: Apr 2017*

*Incentive for Early Completion

slide-4
SLIDE 4

Dominion Boulevard Reconstruction

  • Project Overview

– April 1, 2017: Contract Completion – 4-lane limited access highway (3.8 miles) – 3 interchanges – 9 bridges

4

slide-5
SLIDE 5

Cost Estimates by Major Element

  • 1. Maximum incentive based on $26,279/day for early completion

Dominion Boulevard - Projected Project Costs Estimate Contingency Total Engineering 16,088,768

  • 16,088,768

Right-of-Way 58,476,858 20,000,000 78,476,858 Utility Relocations 8,688,269 1,000,000 9,688,269 Wetland Mitigation 358,873

  • 358,873

Construction 187,711,447 22,568,438 210,279,885 Inspection/Administration 23,378,052 1,908,006 25,286,058 Incentive Clause1

  • 5,000,000

5,000,000 Total $294,702,267 $50,476,444 $345,178,711

 The winning construction bid came in $70 million lower than Engineer’s estimate, thus total costs went down from $416 million to $346 million.

slide-6
SLIDE 6

New Wetlands Mitigation Basin

slide-7
SLIDE 7

Source of Funds

RSTP $ 86,040,980 Bonds $ 107,244,236 VTIB Loan* $ 151,893,495 TOTAL $ 345,178,711

*First VTIB loan in the state All project savings revert to VTIB for future projects

7

slide-8
SLIDE 8

Right-of-Way Acquisition

  • 46 Total Takes

– 17 Residential Relocations – 8 Non-Residential Relocations – Parcel acquired for on-site tidal wetlands mitigation

  • 132 Partial Takes

2 outstanding condemnation cases

8

slide-9
SLIDE 9

Risk Management

  • Risk Management Workshop
  • Establish Risk Management Register

– Soil conditions – Environmental Impacts – Differing Site Conditions – Safety – MOT, Materials, Access, Etc.

  • Regular review of risks (biweekly / monthly)

9

slide-10
SLIDE 10

Bridge Concept Study

slide-11
SLIDE 11

Preliminary Recommendation Elizabeth River Crossing

  • Multi-span continuous structure
  • Five superstructure types considered:

– Concrete Spliced Girders (bulb-tees) – Steel Plate Girders (50 ksi) – Steel Plate Girders (70 ksi) – Steel Plate Girders w/Variable Depth Web (50 ksi) – Segmental Box Girders

  • Approaches similar for each alternative
slide-12
SLIDE 12

Structure Types

  • Channel Crossing:

– Fixed – longer spans; steel plate girder - $250/sf – Moveable – shorter span; non-standard built-up steel framing; electrical & mechanical equipment; special foundation - $1,850/sf

  • Approaches:

– Low Level – “trestle” type; short spans - $70/sf – Mid Level – pier columns; 105-115’ spans - $115/sf – High Level – pier columns; up to 140’ spans - $250/sf

slide-13
SLIDE 13

Structure Type – cont’d

  • Concrete spliced girder and box girder were considered
  • Steel constant depth and variable depth girder options
  • Abutment, pier, and foundation types similar for each
  • Preliminary size & quantities for each alternative
  • Unit costs researched from historical bid data
  • Costs adjusted for project specific conditions
  • Cost applied for each alternative
slide-14
SLIDE 14

Summary of Findings

  • Concrete Spliced Girders (bulb-tees) - $98.7 m
  • Steel Plate Girders (50 ksi) - $108.5 m
  • Steel Plate Girders (70 ksi) - $106.5 m
  • Steel Plate Girders w/Variable Depth Web (50 ksi) -

$106 m

  • Segmental Box Girders - $118.3 m
slide-15
SLIDE 15

Recommendation

  • Spliced Concrete Bulb-Tee chosen for the channel crossing unit

– Cheaper than steel – Lower life-cycle cost

  • Standard PCBT beams made continuous using standard continuity

diaphragms will be used for all approach superstructures

  • Due to bridge width and height several pier types will be used:

– Trestle bents – Multi-column piers on pre-stressed concrete piles – Hammerhead piers on pre-stressed concrete piles

slide-16
SLIDE 16
  • S. Branch Elizabeth River Crossing
  • Bridge Length: 6000’ (SB), 5200’ (NB)
  • Bridge Height: Over 110’ (95’ vertical clearance)
  • Channel Crossing Unit: 222’-285’-222’

– Spliced Girder Construction

  • 91 Piers (50 SB & 41 NB)
  • Over 50,000 CY CIP Concrete
  • Over 90,000 LF Concrete Pile
  • Over 8 Million lbs Reinforcing Steel
slide-17
SLIDE 17

Before After

slide-18
SLIDE 18
  • S. Branch Elizabeth River Crossing
slide-19
SLIDE 19
  • S. Branch Elizabeth River Channel Crossing Unit
slide-20
SLIDE 20

Elizabeth River Piers

slide-21
SLIDE 21

Stage 1: Construct Piers and Temporary Supports

Spliced Girder Sequence

slide-22
SLIDE 22

Erect Span 15NB End Girders

slide-23
SLIDE 23

Spliced Girder Sequence

Stage 2: Erect Pier Segments & End Span Girders

slide-24
SLIDE 24
slide-25
SLIDE 25

Erect Pier 13NB Pier Girder – Balanced Condition

slide-26
SLIDE 26

Spliced Girder Sequence

Stage 3: Install Drop-In Segment using Strong Backs, Cast Closures Stage 4: Stage 1 Post-Tensioning

slide-27
SLIDE 27

Elizabeth River Crossing – Construction Sequence

slide-28
SLIDE 28

Drop In Beams

slide-29
SLIDE 29

Spliced Girder Sequence

Stage 5: Remove Strongbacks, Cast Deck Stage 6: Stage 2 Post-Tensioning

slide-30
SLIDE 30

Elizabeth River Crossing

30

730 Ft. Main Span

slide-31
SLIDE 31

NB Bridge over the Elizabeth River (Post Tensioning)

slide-32
SLIDE 32
slide-33
SLIDE 33

Spliced Girder Sequence

Stage 7: End Diaphragms, Barriers and Overlay

slide-34
SLIDE 34
  • Demo. of Old Steel Bridge
slide-35
SLIDE 35

Dominion Boulevard Reconstruction

35

Cedar Road

slide-36
SLIDE 36

Cedar Road Interchange - SPUI

36

slide-37
SLIDE 37

Dominion Boulevard Reconstruction

37

Dominion Lakes

slide-38
SLIDE 38

38

Dominion Lakes Interchange

slide-39
SLIDE 39

Dominion Boulevard Reconstruction

39

Great Bridge Blvd.

slide-40
SLIDE 40

Great Bridge Boulevard Interchange (north end)

40

“Access to I-64/I-464 and the Chesapeake Expressway”

slide-41
SLIDE 41

Dominion Boulevard Reconstruction

41

Elizabeth River Crossing.

slide-42
SLIDE 42

Elizabeth River Crossing

42

slide-43
SLIDE 43

43

Elizabeth River Crossing - Substructure

slide-44
SLIDE 44

Elizabeth River Crossing - Substructure

slide-45
SLIDE 45

Ground Improvements

slide-46
SLIDE 46

Ground Improvements – Wick Drains

slide-47
SLIDE 47

Wick Drains

slide-48
SLIDE 48
slide-49
SLIDE 49

Wick Drains

  • 5,813,829 Vertical Linear Feet (VLF)
  • 30 to 60 feet deep
slide-50
SLIDE 50

Wick Drains

slide-51
SLIDE 51

Vertical Wick Drains

slide-52
SLIDE 52

Mechanically Stabilized Earth (MSE) Walls

52

slide-53
SLIDE 53

Open Road Tolling System

Toll Gantries and Hub Building

slide-54
SLIDE 54

Dominion Blvd. - Overview

– New Roadway: 18 new lane miles (current 7.6 lane miles) – Earthwork: 1.6 Million CY

  • 400,000 CY Excavation
  • 1.2 Million CY Embankment Fill

– Ground improvements:

  • Vertical Wick Drains: 4.5 Million LF
  • Embankment Surcharge: 23 Locations
  • Ground Improvement Piles: 600 each

54

slide-55
SLIDE 55
  • 2500+ piles (157,500 lf – over 30miles)
  • 66,400 lf beams (over 13 miles)
  • 245,000 sf MSE walls (4,160 cy)
  • 26,000 sf sound barrier (1,200 cy)
  • 1,000 lf box culvert (650 cy)
  • 36,000 lf RCP
  • 160 pipe end sections
  • 90 end walls
  • 380 drop inlets
  • Over 75,000 cy of precast concrete!
  • Cast-in-Place Concrete: 65,000 CY
slide-56
SLIDE 56

Dominion Blvd. Animated Video (See Project Website)

slide-57
SLIDE 57

www.cityofchesapeake.net/Dominion

Dominion Blvd. – Public Relations

Dominion Boulevard Improvement Project