Construction of Laboratory and Construction of Laboratory and - - PowerPoint PPT Presentation

construction of laboratory and construction of laboratory
SMART_READER_LITE
LIVE PREVIEW

Construction of Laboratory and Construction of Laboratory and - - PowerPoint PPT Presentation

Construction of Laboratory and Construction of Laboratory and Construction of Laboratory and Field Demonstration Modified Field Demonstration Modified Field Demonstration Modified Beam- -in in- -Slab Bridges Slab Bridges Beam


slide-1
SLIDE 1

Construction of Laboratory and Field Demonstration Modified Beam-in-Slab Bridges Construction of Laboratory and Construction of Laboratory and Field Demonstration Modified Field Demonstration Modified Beam Beam-

  • in

in-

  • Slab Bridges

Slab Bridges

  • T. F. Konda, F. W. Klaiber,

T.J. Wipf

Iowa State University Bridge Engineering Center

slide-2
SLIDE 2

Iowa’s Deficient Off System Bridges Iowa’s Deficient Off System Iowa’s Deficient Off System Bridges Bridges

Approximately 30% of Off System

Structures are Deficient

Limited Replacement Funding Develop Alternative Designs

slide-3
SLIDE 3

Alternative Replacement Designs Alternative Replacement Designs Alternative Replacement Designs

Design Requirements

– Lower Cost – Constructible by County Forces – Accommodate Recycled Materials – Require Minimal Maintenance

slide-4
SLIDE 4

Alternative Replacement Designs Alternative Replacement Designs Alternative Replacement Designs

Beam-in-Slab Bridge (BISB) System

– Conservatively Designed – In Service For 25 Years + – Exists only in Iowa?

slide-5
SLIDE 5

Beam-in-Slab Bridge System Beam Beam-

  • in

in-

  • Slab Bridge System

Slab Bridge System

W 12 Girders, 24 in.

  • n Center, Typ.

Steel Confining Straps Plywood Concrete

slide-6
SLIDE 6

Beam-in-Slab Bridge System Beam Beam-

  • in

in-

  • Slab Bridge System

Slab Bridge System

Conclusions to BISB Testing

– Structurally Adequate System

Advantages

– Easy to Construct – Cost Competitive

Limitations

– Lack of Efficiency – Limited Span Length

slide-7
SLIDE 7

Increasing Applicability Increasing Applicability Increasing Applicability

Increase the Efficiency of the System

– Develop Composite Action – Reduce Self Weight of the Section

slide-8
SLIDE 8

Composite Action Composite Action Composite Action

Use of Alternative Shear Connector (ASC)

slide-9
SLIDE 9

Reduce Self Weight With Arched Section Reduce Self Weight With Reduce Self Weight With Arched Section Arched Section

Advantages

– Wider Girder Spacing – Deeper Girder Sections – Longer Spans – Reduced Reinforcement

Complication

– Forming the Section

slide-10
SLIDE 10

Formwork Investigation Formwork Investigation Formwork Investigation

Various Materials and Configuration

– Polyethylene Pipe – Arched Plywood – Corrugated Metal Pipe (CMP) – Custom Rolled Corrugated Section

slide-11
SLIDE 11

Custom Rolled Corrugated Sections Custom Rolled Corrugated Custom Rolled Corrugated Sections Sections

slide-12
SLIDE 12

Laboratory Testing Laboratory Testing Laboratory Testing

Specimen # 1 (Preliminary Section)

– Investigate Feasibility

#4 ASC Reinforcement 2” x 1/4” Strap 21” Radius, 42”

  • Dia. Poly Pipe

W 21 x 62 Girders 84” 8” 8” 2.5” 45” 19.5” Concrete

slide-13
SLIDE 13

Laboratory Testing Laboratory Testing Laboratory Testing

Specimen # 2 & # 3

– Investigate Punching Shear

slide-14
SLIDE 14

Laboratory Testing Laboratory Testing Laboratory Testing

Specimen # 4

– Investigate Load Distribution – Investigate Flexural Failure Mode

slide-15
SLIDE 15

Demonstration Bridge Demonstration Bridge Demonstration Bridge

Design Based on:

– AASHTO LRFD Bridge Design Specification – Laboratory Testing Results

6 – W27 x 129 Girders Outfitted with ASC Custom Rolled Corrugated Sections

slide-16
SLIDE 16

Demonstration Bridge Demonstration Bridge Demonstration Bridge

slide-17
SLIDE 17

Demonstration Bridge Demonstration Bridge Demonstration Bridge

slide-18
SLIDE 18

Demonstration Bridge Demonstration Bridge Demonstration Bridge

slide-19
SLIDE 19

Demonstration Bridge Demonstration Bridge Demonstration Bridge

slide-20
SLIDE 20

Demonstration Bridge Demonstration Bridge Demonstration Bridge

slide-21
SLIDE 21

Conclusions Conclusions Conclusions

BISB System

– Alternative Replacement – Span Limited to 50 ft due to Structural Inefficiencies

Modifications to Improve Efficiency of

Design

– ASC and Transverse Arched Section – Increase Span Length to 75 ft – Improved Use of Materials

slide-22
SLIDE 22

Acknowledgements Acknowledgements Acknowledgements

– Sponsor: Iowa Department of Transportation, Highway Division and the Iowa Highway Research Board – Tama County Engineer and Bridge Crew – ISU Research Laboratory Manager – Numerous ISU undergraduate students