CONSTRUCTION PRESENTATION TO JACKS LANE COMMUNITY LIAISON GROUP DECEMBER 2013 CONSTRUCTION TEAM: PAUL NICOLSON CONSTRUCTION PROJECT MANAGER, RES UK & IRELAND GARY SCROWTHER CONSTRUCTION SITE MANAGER, RES UK & IRELAND JAMES DOMINIAK


slide-1
SLIDE 1

CONSTRUCTION PRESENTATION TO JACKS LANE COMMUNITY LIAISON GROUP DECEMBER 2013

CONSTRUCTION TEAM: PAUL NICOLSON CONSTRUCTION PROJECT MANAGER, RES UK & IRELAND GARY SCROWTHER CONSTRUCTION SITE MANAGER, RES UK & IRELAND JAMES DOMINIAK CONSTRUCTION ASSISTANT SITE MANAGER, RES UK & IRELAND BRADLEY BOYD HSQE ADVISOR, RES UK & IRELAND

slide-2
SLIDE 2

RES CONSTRUCTION

  • Responsible for safety in preparation and execution of construction of wind

farm projects

  • Ensuring quality of installation through accurate design, organisation,

planning and documentation

  • Ensuring protection of the environment.
  • Manage programme, budget and client’s specification.
  • Management of contracts and contractors to build the construction team on

and around site

  • Liaise with public during construction.
slide-3
SLIDE 3

CIVIL ENGINEERING WORKS

  • Design
  • Roads Construction
  • Wind Turbine & Met Mast Foundations Construction
  • Substation Building and Compound Construction
  • Crane hardstanding and turbine assembly areas
  • Welfare facilities during construction
  • Ecology Enhancement
slide-4
SLIDE 4

ELECTRICAL ENGINEERING WORKS

  • Design
  • Equipment Specifications
  • Grid Interface: Substation Equipment
  • Wind Farm Network: Cabling
  • Earthing
  • Communication Network
  • Testing, Commissioning and Energisation
slide-5
SLIDE 5

TURBINE WORKS

  • Access Study prior to Delivery
  • Lifting Plan
  • Foundation interface
  • Supervision of delivery, erection and

pre-commissioning works

  • Coordination of energisation
  • SCADA Tests
  • Turbine Tests
  • Snagging Inspections
  • Met Mast / Power Performance
slide-6
SLIDE 6

INDICATIVE CONSTRUCTION MILESTONES

  • January 2014 – Site preparation work starts
  • May 2014 – Work on turbine foundations begins
  • July 2014 – Electrical work begins
  • September 2014 – Turbines delivered to site
  • Spring 2015 – Electricity generation
slide-7
SLIDE 7

INFRASTRUCTURE LAYOUT

slide-8
SLIDE 8
slide-9
SLIDE 9

GRID ROUTE

slide-10
SLIDE 10

170

slide-11
SLIDE 11

170

slide-12
SLIDE 12

P57

slide-13
SLIDE 13

P57

slide-14
SLIDE 14

P157

slide-15
SLIDE 15

44

slide-16
SLIDE 16

44

slide-17
SLIDE 17

91

slide-18
SLIDE 18

Wind Turbine Erection Time Lapse

slide-19
SLIDE 19
slide-20
SLIDE 20

Community Benefit

Sam Mayes – Community Relations Coordinator, RES

slide-21
SLIDE 21

Community Benefit Fund

It will become available once the wind farm is fully operational. Index linked annual payments will be paid for the 25 year lifetime of the project. A Fund Panel will be made up of local people. RES will appoint a Fund Administrator to:

  • support the Fund Panel and finalise fund criteria
  • handle enquiries from applicants
  • process grant offers and payments
slide-22
SLIDE 22

Local Electricity Discount Scheme (LEDS)

LEDS has been developed in response to feedback from local communities and offers residential, community and business properties closest to a proposed RES wind farm a minimum discount of £100 per year off their electricity bills. Eligible properties will be contacted directly and invited to register their interest in the scheme. The discounts will be paid directly to the electricity supplier and will commence within the first year that the wind farm becomes operational.

slide-23
SLIDE 23

23