Design of Geofoam Embankment for the I-15 Reconstruction I 15 - - PowerPoint PPT Presentation

design of geofoam embankment for the i 15 reconstruction
SMART_READER_LITE
LIVE PREVIEW

Design of Geofoam Embankment for the I-15 Reconstruction I 15 - - PowerPoint PPT Presentation

Design of Geofoam Embankment for the I-15 Reconstruction I 15 Reconstruction Steven F. Bartlett, Ph.D., P.E. Research Project Manager, UDOT I-15 Reconstruction - Quick Facts Si Single Largest Highway Contract in U.S. l L t Hi h C t t i


slide-1
SLIDE 1

Design of Geofoam Embankment for the I-15 Reconstruction I 15 Reconstruction

Steven F. Bartlett, Ph.D., P.E. Research Project Manager, UDOT

slide-2
SLIDE 2

I-15 Reconstruction - Quick Facts

Si l L t Hi h C t t i U S

  • Single Largest Highway Contract in U.S.
  • 17 Miles of Urban Interstate
  • $1 5 Billion Design-Build

$1.5 Billion Design Build

  • 4 Year Construction Duration (Summer 2001)
  • 144 Bridges/Overpass Structures

g p

  • 160 Retaining Walls (mostly MSE Walls)
  • 3.8 Million m3 of Embankment Fill

100 000

3 G

f E b k

  • 100,000 m3 Geofoam Embankment
slide-3
SLIDE 3

Primary Uses of Geofoam on the I-15 Project

  • Reduce Settlement to Protect Buried Utilities
  • Improve Slope Stability of Embankments
  • Rapid Construction in Time Critical Areas
  • Rapid Construction in Time Critical Areas
slide-4
SLIDE 4

Settlement Reduction (continued) Subsurface Profile in Salt Lake Valley

CPT Tip Resistance, kPa

5 5000 10000 15000 20000 25000 30000 35000 40000

Alluvium

Soft Clay (10- m thick)

10 15

(m)

Bonneville Clay Pleistocene Alluvium

m thick)

20 25

Depth

Cutler Clay

30 35 40

y

40

slide-5
SLIDE 5

Settlement Reduction (continued) Settlement on I-15, Salt Lake City (1964 - 1968) , y ( )

11.6 m 11.6 m Fill Height Primary Settlement 1.4 m Settlement 2.5 year duration

slide-6
SLIDE 6

Settlement Reduction (continued) Buried Utilities

B i d Pi li Buried Pipeline NEW FILL Buried Pipeline NEW FILL Buried Pipeline Ruptured Pipeline

slide-7
SLIDE 7

Settlement Reduction (continued) Buried Utilities along Roadway g y

Buried Utilities Utilities Geofoam Embankment from State St. to 200 W. Along Interstate I-80, Salt Lake City, Utah

slide-8
SLIDE 8

Improve Slope Stability (continued) Diagram of Potential Instability at Bridges ag a

  • te t a

stab ty at dges

cracks Bridge Deck Failure surface Soft Clay Soft Clay

slide-9
SLIDE 9

Improve Slope Stability

Details of Geofoam Construction at Bridge Abutments

slide-10
SLIDE 10

Rapid Construction (Typical Embankment Construction for I-15) (Typical Embankment Construction for I 15)

Geotechnical

Wic k Dra ins T ypic a l Wic k Dra in

NEW EMBANKMENT SHOULDER 1/2 SLOPE WIDTH MINIMUM NEW

C L 1 5

SURCHARGE EXISTING EMBANKMENT

NEW EMBANKMENT

1.5 1.5 1 1 2 1

WICK DRAINS GEOTEXTILE

slide-11
SLIDE 11

Rapid Construction (Typical Embankment Construction for I-15) (Typical Embankment Construction for I 15)

Wick Drain Installation (4 weeks) Grading and Geotextile (4 weeks)) Wall Construction + Settlement Time (6 weeks + 24 weeks) Concrete Panel Placement (2 weeks)

slide-12
SLIDE 12

Rapid Construction (Typical Geofoam Construction for I-15) (Typical Geofoam Construction for I 15)

35 cm Concrete Pavement 15 cm Reinforced Concrete Load Distribution Slab Tilt-up Concrete Fascia 60 cm Base Material Fascia Panel Wall Geofoam Block Sloped Embankment (1.5 H to 1 V max.) Bedding Sand (20 cm min.) Wall Footing

slide-13
SLIDE 13

Rapid Construction (Typical Geofoam Construction for I-15) (Typical Geofoam Construction for I 15)

Grade Preparation (1 week) Block Placement (3 weeks)) Load Distribution Slab Construction (2 weeks) Panel Wall Construction (1 Week)

slide-14
SLIDE 14

Rapid Construction (Comparison of Construction Time) (Comparison of Construction Time)

35 25 30

Conventional Geofoam

(Weeks)

15 20

tion Time

5 10

Construct

5 ation ction ment Work Total

C

Prepara Construc Settlem Finish W T

slide-15
SLIDE 15

Design Considerations

  • Material Type
  • Moisture Absorption

Material Type

  • Dimensions
  • Density

C i St th Moisture Absorption

  • Buoyancy
  • Thermal Resistance

Diff ti l I i

  • Compressive Strength
  • Allowable Load & Creep
  • Interface Friction
  • Differential Icing
  • Chemical Attack
  • Flammability
  • Stability of Internal Slope
  • Bedding Material & Compaction
  • Concentrated Loads
  • Insect Infestation
  • Ultra Violet Degradation
  • Durability

Concentrated Loads Durability

slide-16
SLIDE 16

Design Considerations (Material Type) ( yp )

  • Expanded Polystrene (EPS)*

Expanded Polystrene (EPS)

  • virgin feedstock

i f 5 t i d t t

  • maximum of 5 percent regrind content

* Extruded Polystrene (XPS) is also available, but was not used

  • n the I-15 project
slide-17
SLIDE 17

Design Considerations (EPS Block Dimensions) ( )

81 cm 488 cm 122 cm

Dimension tolerance 0.5 percent Dimension tolerance 0.5 percent

  • If tolerance is met, no trimming is necessary
  • If tolerance is not met shop trimming is necessary
  • If tolerance is not met, shop trimming is necessary
slide-18
SLIDE 18

Design Considerations (EPS Density) ( y)

Property ASTM Test Type XI Type I Type VIII* Type II Type IX Test C 578 Nominal Density (kg/m3) C303 / D 1622 12 16 20 24 32 Minimum Density (k /

3)

C303 / D 1622 11 15 18 22 29 (kg/m3) * Type VIII was used for I-15 Reconstruction

slide-19
SLIDE 19

Design Considerations (EPS Minimum Compressive Strength) ( p g )

Property ASTM Test Type XI Type I Type VIII Type II Type IX kPa (10% C 165 / D 1621 35 69 90* 104 173 (10% Strain) D 1621 * Type VIII was used for I-15 Reconstruction St i R t f T ti 5 / i t Strain Rate for Testing = 5 mm / minute

slide-20
SLIDE 20

Design Considerations (EPS Minimum Compressive Strength (EPS Minimum Compressive Strength Versus Density)

(Source: Bartlett et al. 2000)

d = 7.3 * D - 47 where D = Density in kPa.

slide-21
SLIDE 21

Design Considerations (Allowable Stress and Creep) ( p)

Source: Negussey (1997) Type VIII d = stress 0.4 d Type VIII EPS @ 5% strain 0.4 d Simplified Formula: Allowable Stress = 0.4 d Allowable Stress = 0.4 x 120 = 48 kPa * Allowable Stress Must Maintained Below 1% Axial Strain to Minimize Long-Term Creep

slide-22
SLIDE 22

Design Considerations (Allowable Stress and Creep) ( p)

Allowable Stress (Dead Load + Live Load) < 0.4 d Dead Load = Weight of Load Distribution Slab + Dead Load Weight of Load Distribution Slab + Weight of Base Material + Weight of Pavement. Dead Load = 30 % of d = 0.3 d Live Load = Traffic Loads Live Load = 10 % of d = 0.1 d

slide-23
SLIDE 23

Design Considerations (Creep Data from Norway) ( p y)

Measured Data (3.5 years) Theoretical Model

(Source: Aaboe, 2000)

slide-24
SLIDE 24

Design Considerations (Creep Data from Norway) ( p y)

Theoretical Model Theoretical Model

(Source: Aaboe, 2000)

slide-25
SLIDE 25

Design Considerations (Interface Friction) ( )

n EPS BLOCK Lateral Force

  • Interface Friction Need for Design Against Sliding

  = n tan   = sliding shear resistance g n = normal stress tan  (Design Value)  degrees (Design Value)  degrees (Design Value)

slide-26
SLIDE 26

Design Considerations (Interface Friction) ( )

D i V l 31 d Design Value = 31 deg.

Source: Negussey (1997) Source: Negussey (1997)

slide-27
SLIDE 27

Design Considerations (Stability of Internally Sloped ( y y p Embankments)

Back Slope 1.0 Vertical 1 5 Horizontal 1.0 Vertical Force = 0 (Do Not Allow 1.5 Horizontal M i B k Sl 1 5 H t 1 0 V ti l (Do Not Allow Transfer of Horizontal Maximum Back Slope = 1.5 H to 1.0 Vertical for Embankment to Guarantee Internal Slope Stability Force)

slide-28
SLIDE 28

Design Considerations (Stability of Internally Sloped ( y y p Cuts and Hillsides)

Reinforced Slope Soil Nails, Soil Anchors,

  • r Other
  • r Other

Reinforcement Cut Slope or Cut Slope or Landslide

slide-29
SLIDE 29

Design Considerations (Bedding Material and Compaction) ( g p )

Bedding Sand Function g

  • free draining sand or fine gravel
  • provides leveling course

id d i

  • provides drainage

Bedding Sand (20 cm min.)

slide-30
SLIDE 30

Design Considerations (Bedding Material and Compaction) ( g p )

Gradation Specification for Bedding Sand Gradation Specification for Bedding Sand

Sieve Size 50mm 13mm 6mm 2mm 0.425mm 0.075 mm Sieve Size 50mm 13mm 6mm 2mm 0.425mm 0.075 mm % Passing 95 - 100 65-100 50-100 40-70 10-40 0-5 (Percent Passing)

* Materials with more than 20 percent of the samples containing between5 and 7 percent minus 0.075 mm material shall not be between5 and 7 percent minus 0.075 mm material shall not be accepted for use.

slide-31
SLIDE 31

Design Considerations (Bedding Material and Compaction) ( g p )

Light Weight Grade Preparation and Leveling Light-Weight Compaction Equipment (*Maximum lift thickness = 20 cm)

slide-32
SLIDE 32

Design Considerations (Concentrated Loads) ( )

  • Uncovered geofoam damages easily from tire loads
  • Do not use heavy equipment atop geofoam

until the load distribution slab is placed

  • Use light-weight construction equipment

g g q p

  • Protect with plywood sheeting
slide-33
SLIDE 33

Design Considerations (Moisture Absorption - Above High ( p g Groundwater Elevation)

(Source: Aaboe, 2000)

slide-34
SLIDE 34

Design Considerations (Moisture Absorption - Below ( p Groundwater)

(Source: Aaboe, 2000)

slide-35
SLIDE 35

Design Considerations (Moisture Absorption Design Values) (Moisture Absorption - Design Values)

  • Installation of EPS above high groundwater
  • Design Moisture Content = 1 percent by volume
  • Installation of EPS that is periodically submerged
  • Design Moisture Content = 5 percent by volume

Design Moisture Content 5 percent by volume

  • Installation of EPS below groundwater
  • Design Moisture Content

10 percent by volume

  • Design Moisture Content = 10 percent by volume
slide-36
SLIDE 36

Design Considerations (Buoyancy) (Buoyancy)

Fresisting

resisting

groundwater 100-year design flood event

Fuplift

Drainage Sand

Fresisting = 1.3 x Fuplift

slide-37
SLIDE 37

Design Considerations (Thermal Resistance) ( )

(Negussey, 1997)

  • R-value = heat flow through a unit width of material.
  • R-value for geofoam is about 4 (18 kg/m3 density).

R l f il d t i l th 1

  • R-value for soil and concrete is less than 1.
slide-38
SLIDE 38

Design Considerations (Differential Icing - Cold Regions only) ( g g y)

pavement No Icing EPS Icing soil p EPS Good Heat Transfer Poor Heat Transfer

60 mm base (min.)

No Icing

Base material has heat capacity and prevents pavement from icing idl as rapidly.

Proper Design to Prevent Icing

slide-39
SLIDE 39

Design Considerations (Chemical Attack) ( )

  • Solvents that Dissolve Geofoam

G li

  • Gasoline
  • Diesel
  • Other Petroleum Based Fuels

O e e o eu sed ue s

  • Organic Fluids
  • Protection Against Accidental Spills
  • Concrete Load Distribution Slab
  • Geomembrane

Geomembrane

  • Fascia Panel Wall with Coping
slide-40
SLIDE 40

Design Considerations (Chemical Attack - Protective Barriers) ( )

Concrete Pavement (35 cm) Load Distribution Slab (15 cm Reinforced) (15 cm - Reinforced) Geomembrane P l R i Petroleum Resistant (3 component) for exposed side slope p p

  • nly

Tilt-up Panel Wall

slide-41
SLIDE 41

Design Considerations (Chemical Attack - Protective Barriers) ( )

  • Tripolymer Geomembrane
  • Polyvinyl Chloride
  • Ethylene Interpolymer Alloy
  • Polyurethane

y

  • 9 mm thickness minimum (total)
slide-42
SLIDE 42

Design Considerations (Flammability) ( y)

  • Geofoam is Combustible and Must Be Protect Against
  • Geofoam is Combustible and Must Be Protect Against

Open Flame or Heat

  • Material Specification should include:
  • Material Specification should include:

“Flame Retardant Additive and a UL Certification of Classification as to External Fire Exposure and Classification as to External Fire Exposure and Surface Burning Characteristics.”

slide-43
SLIDE 43

Design Considerations (Insect Infestation) ( )

  • Chemical (Borate) can be added to stop termite

( ) p

  • r insect infestation.
slide-44
SLIDE 44

Design Considerations (UV Degradation) ( g )

(Bartlett et al., 2000)

Prolonged Exposure ( > 90 days) to sunlight can lead to discoloration of geofoam and decrease in the internal angle

  • f friction on the surface of the geofoam.
slide-45
SLIDE 45

Design Considerations (UV Degradation) ( g )

  • Geofoam should not be left uncovered more than 90 days.
  • UV exposure times greater than 90 days require

p g y q “power-washing” to remove degraded geofoam surface where the load distribution slab is placed

  • Side surface where tilt-up panel wall is placed do not

require power-washing.

slide-46
SLIDE 46

Design Considerations (Durability Data from Norway) ( y y)

Note: No loss of compressive strength with time is evident (Source: Aaboe, 2000).

slide-47
SLIDE 47

(Questions ? ? ?)