I-15 Reconstruction Project: Innovative Foundation and Embankment - - PowerPoint PPT Presentation

i 15 reconstruction project innovative foundation and
SMART_READER_LITE
LIVE PREVIEW

I-15 Reconstruction Project: Innovative Foundation and Embankment - - PowerPoint PPT Presentation

I-15 Reconstruction Project: Innovative Foundation and Embankment Construction Steven F. Bartlett, Ph.D., P.E. Steven F. Bartlett, Ph.D., P.E. Assistant Professor University of Utah I-15 Reconstruction Project Extents End Project 600 N


slide-1
SLIDE 1

I-15 Reconstruction Project: Innovative Foundation and Embankment Construction

Steven F. Bartlett, Ph.D., P.E. Steven F. Bartlett, Ph.D., P.E. Assistant Professor University of Utah

slide-2
SLIDE 2

I-15 Reconstruction – Project Extents

End Project 600 N 600 N.

  • Beg. Project 10600 S.
slide-3
SLIDE 3

I-15 Reconstruction - Quick Facts

  • Single Largest Design Build Highway Contract in U S
  • Single Largest Design-Build Highway Contract in U.S.
  • 17 Miles of Urban Interstate
  • $1.5 Billion (Project Cost)
  • Wasatch Constructors (Prime Contractor)
  • Kiewit, Granite, Washington Construction
  • 4 Year Construction Duration (1997 - 2001)
  • 144 Bridges/Overpass Structures
  • 160 Retaining Walls (mostly MSE Walls)

g ( y )

  • Approximate $6 M Research Program (4 years)
slide-4
SLIDE 4

Geotechnical Issues

  • Large Primary Consolidation Settlement (1 to 1.5 m)

g y ( )

  • Time Rate of Consolidation (2 years to end of primary)
  • Creep Settlement (Bump at Bridge)
  • Creep Settlement (Bump at Bridge)
  • Foundation Stability (Large Embankments on Soft Soils)
  • Schedule Constraints (two 2-year projects)
  • Maintenance of Traffic (Had to be maintained)
  • New Technologies and Development of Specifications
slide-5
SLIDE 5

Selected Topics

PV Drains Surcharging Geotextile Reinforced Slopes

slide-6
SLIDE 6

Selected Topics (cont.)

2-Stage MSE Walls Lime Cement Columns Geofoam – Light Weight Fill

slide-7
SLIDE 7

Quantity and Cost Summary

slide-8
SLIDE 8

Subsurface Profile in Salt Lake Valley

5000 10000 15000 20000 25000 30000 35000 40000

CPT Tip Resistance, kPa

5 10

Bonneville Clay Alluvium

Primary Settlement

10 15 20

h (m)

Bonneville Clay Pleistocene Alluvium

20 25

Depth

Cutler Clay

Secondary Settlement

30 35

y

40

slide-9
SLIDE 9

Settlement of Soft Clays in Salt Lake Valley

Primary Settlement Secondary Settlement Approximate 2 years of primary settlement

slide-10
SLIDE 10

Consolidation Properties

100 200 300 400 500 600 700 800

I it

0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70

Preconsolidation Stress (kPa) Compression Ratio

5 10

In situ Vertical Effective Stress

5 10 15 (m) 15 20

D e p th ( m )

20 25 Depth 25 30 35

D

30 35 35 40 40

slide-11
SLIDE 11

Typical I-15 Embankment Construction

Surcharge Temporary Wire Wall New embankment Existing embankment 2-Stage MSE Wall Geotextile Alluvium Lake Bonneville Silts and Clays Prefabricated Vertical Drains Pleistocene Sands and Gravels Sands and Gravels

slide-12
SLIDE 12

Prefabricated Vertical Drains

Installed drain PV Drain Spacing 1.5 to 2.5 m Installed drain PV Drain Spacing 1.5 to 2.5 m triangular spacing PV drain pushed into ground Placement of anchor bar

slide-13
SLIDE 13

PVD Installation Issues

1. Consolidation times need to be reduced to 3 to 6 month to accommodate schedule to accommodate schedule 2. Large, atypical mandrels and anchor plates may cause excessive disturbance and reduce time rate of consolidation 3. PV drains spaced too closely together may cause disturbance and reduce time rate of consolidation 4. PV drain contractor may not be able to push drains p through existing embankment Mandrel used on the I-15 Project

slide-14
SLIDE 14

Rate of Consolidation Vs. Drain Spacing

) t95 (days) t Triangular Drain Spacing (m)

slide-15
SLIDE 15

Pre-drilling of PV Drains Required through Existing Embankment g g

Cost: $1.50/ m (without predrilling) $3.00/m (with predrilling) Approximate 3 drill rigs req’d for one PV drain rig

slide-16
SLIDE 16

PV Drain Summary

  • 1. PVDs reduced settlement to 3 to 6 months and were the

k I 15 key component to I-15 success.

  • 2. PVDs performed as expected.
  • 3. Size and geometry of installation mandrel and anchor

plate should be controlled by specification.

  • 4. PVDs should not be spaced closer than 1.5 m

triangular spacing for Lake Bonneville Deposits 5 P d illi i d f i t ll ti th h l

  • 5. Predrilling was required for installation through large

(8 m high) preexisting embankments.

slide-17
SLIDE 17

Surcharging to Reduce Settlement

5 million cubic meters of embankment placed on project

Model for Secondary Consolidation

End of Primary Settlement Remove Surcharge Beginning of Primary Settlement SV Remove Surcharge Rate of Secondary Settlement w/ Surcharge

3 inches in 10 years

Log Time (years)

C C’

Rate of Secondary Settlement w/o Surcharge

slide-18
SLIDE 18

Surcharging to Reduce Settlement

Amount of Surcharge

slide-19
SLIDE 19

Surcharging Summary

  • 1. Design goal was to reduce secondary settlement to 3

inches or less in 10 years. inches or less in 10 years.

  • 2. Post construction monitoring has shown that

surcharging has been successful in achieving this goal. g g g g

  • 3. Surcharges of 30 to 40 percent of the final

embankment height were used.

  • 4. Large surcharged fills introduced stability concerns in

some locations.

  • 5. Surcharge were to remain in place until 98 percent

EOP consolidation was reached.

slide-20
SLIDE 20

Geotextile Installation in Reinforced Slopes

Geotextile Installed on 3H:1V slope Geotextile Installed on 3H:1V slope Geotextile placement on sloped, p p , pre-existing embankment Geotextile lapped into MSE wall

slide-21
SLIDE 21

Stability Criteria for Reinforced Slopes

Stability Parameter Threshold Level 1 Threshold Level 2 Threshold Level 3 Horizontal 3 8 - 7 6 7 6 - 25 0 > 25 0 Horizontal Displacement Rate (mm/day) 3.8 7.6 7.6 25.0 > 25.0 Displacement 0.2 - 0.3 0.3 – 0.4 > 0.4 p Ratio (DR) Piezometric Head Increase

  • > 200% of Load

due to Fill same as threshold 2 Placement Response Action

  • Notify Field

Construction

  • Stop Fill

Placement

  • Buttress Slope

and Remove Manager of threshold 1

  • Increase

Monitoring Frequency

  • Prepare

Specific Action Plan

  • Implement

Plan if Fill

  • Notify Senior

Project Management

  • Notify UDOT

Frequency Plan if Conditions Worsen

  • Notify UDOT
slide-22
SLIDE 22

Stability Criteria -Displacement Ratio

80 70 80

DR = horz Displacement

50 60 t (cm)

DR = horz. Displacement / vert. settlement

40 lative Settlement Displacement Ratio = 0.3

  • Horz. displacement from

Vertical inclinometers

20 30 Cumul 1

  • Vert. Settlement from

Settlement plates

10 Displacement Ratio = 0.2 DR 5 10 15 20 25 Cumulative Horizontal Displacement (cm)

slide-23
SLIDE 23

Stability Summary

  • 1. Large embankments with surcharge introduced

foundation stability issues at many bridge crossings.

  • 2. No embankment failures occurred on the project.
  • 3. High strength geotextile (max. 3 layers) was used to

achieve global stability with a FS of 1.3.

  • 4. Staged construction was used in many locales to reduce

geotextile requirements.

  • 5. Vertical inclinometers and settlement plates were used

t it t bilit to monitor stability

  • 6. Stability criteria based on the displacement ratio (DR)

proved to be the most useful means of monitoring proved to be the most useful means of monitoring embankment stability.

slide-24
SLIDE 24

2-Stage MSE Walls

Right-of-way constraints required many slopes to be built vertically. y p y Beginning of 2-stage MSE Wall

slide-25
SLIDE 25

2-Stage MSE Wall Connections

Female threaded rod coupler Attachment of Panels with threaded rod Concrete Fascia Panel

slide-26
SLIDE 26

MSE Wall Settlement and Deformation Issues

Deformation of Welded Wire Face at Toe of Wall Settlement Impacts to Adjacent Structures

slide-27
SLIDE 27

3500 South MSE Wall Array

Instrumented Reinforcing Elements Survey Points Embankment Fill Horizontal Inclinometers Reference Bench Mark Magnet-Reed Extensiometer Vertical Inclinometers g

slide-28
SLIDE 28

Objectives of MSE Wall Arrays

  • 1. Monitor Stress and Strains

within Wall and Foundation

  • 2. Determine Settlement

Distribution Away from W ll Wall

  • 3. Monitor Transitions Zones
  • 4. Deformation Modeling
slide-29
SLIDE 29

Strain Gauges on Welded-Wire Reinforcing

Horizontal reinforcing (bar mat) with strain gages. Strain gage wiring at face g g g

  • f MSE wall
slide-30
SLIDE 30

3500 South MSE Wall Array

I li t d S d Reading of Sondex Inclinometer and Sondex Locations Extensometer

slide-31
SLIDE 31

3500 S. MSE Wall Deformations

slide-32
SLIDE 32

MSE Wall Summary

  • 1. Large primary consolidation settlement req’d use of

two stage MSE wall with flexible wire face.

  • 2. Flexible faces can deform during construction and

post-construction.

  • 3. Increasing the horizontal reinforcement in the bottom

half of the wall can reduce the deformation, but not completely eliminate it (horzizontal buldge reduce by a p y ( g y factor of 2.)

  • 4. Material type, compaction and construction

procedures can also help in reducing face deformation.

  • 5. Specifications should be written to control allowable

face deformation.

  • 6. Zone of settlement influence is 1.5 times wall height.
slide-33
SLIDE 33

Geofoam Embankment For Settlement Reduction

Buried Utilities Utilities Geofoam Embankment from State St. to 200 W. Along Interstate I-80, Salt Lake City, Utah

slide-34
SLIDE 34

Geofoam Placement Areas

100,000 cubic meters of Geofoam

slide-35
SLIDE 35

Geofoam Cross Section (Typical)

35 cm Concrete Pavement 15 cm Reinforced Concrete Load Distribution Slab Tilt-up Concrete Fascia 60 cm Base Material Fascia Panel Wall Geofoam Block Sloped Embankment (1.5 H to 1 V max.) Bedding Sand (20 cm min.) Wall Footing

slide-36
SLIDE 36

Geofoam Properties

* I-15 used 1.25 pcf density exclusively (i.e., type VIII geofoam)

slide-37
SLIDE 37

Geofoam Embankment

Leveling Course of Sand Construction of Geofoam Embankment and Footing for Tilt-up Panel Wall Leveling Course of Sand for Geofoam Embankment

slide-38
SLIDE 38

Geofoam Embankment

Geofoam cut and placed around piling at bridge abutment Nearly Completed Geofoam Embankment with Vertical Face Transition Zone with MSE Wall

slide-39
SLIDE 39

Load Distribution Slab Atop Geofoam

Reinforced Concrete Completed Load Distribution Slab Reinforced Concrete Load Distribution Slab atop Geofoam

slide-40
SLIDE 40

Geofoam (Finished Cross Section)

slide-41
SLIDE 41

Geofoam for Rapid Construction C i f C t ti Ti Comparison of Construction Times

30 35

Conventional Geofoam

eeks)

20 25

Time (We

10 15

struction

5 Preparation Construction Settlement Finish Work Total

Cons

Preparation Construction Settlement Finish Work Total

slide-42
SLIDE 42

Geofoam Wall Costs

Geofoam wall system (total cost) is about 2 ¼ times more expensive than conventional 2-Stage MSE wall with PV drains

slide-43
SLIDE 43

3300 South Geofoam Array

ROW OF SURVEY POINTS AT FACE OF WALL 25 MM - PVC STAND PIPE ROW OF SURVEY POINTS ALONG OUTSIDE EDGE OF EMERGENCY LAN ROW OF SURVEY POINTS ALONG INSIDE EDGE OF MOMENT SLAB CONCRETE PAVEMENT ROAD BASE LOAD DISTRIBUTION SLAB SQUARE PLATE WITH MAGNET RING LEVEL 6 6.5 TO 7.3 m GEOFOAM BLOCKS LEVEL 4 LEVEL 2 HEIGHT VARIES GRANULAR BACKFILL LEVEL 0 LEVEL 2 BEDDING SAND 2.5 m VIBRATING WIRE TOTAL PRESSURE CELL

slide-44
SLIDE 44

Objectives of Geofoam Arrays

  • Measure Creep Settlement of Geofoam Mass (10 yr.)
  • Measure the Pressure Distribution within Mass

Measure the Pressure Distribution within Mass

  • Measure Differential Settlement in Transition Zones
  • Measure Lateral Earth Pressure at Abutments
  • Measure Lateral Earth Pressure at Abutments
  • Monitor for Differential Icing at Geofoam /

Embankment Transition Zones

  • Model Stress / Strain Behavior
slide-45
SLIDE 45

3300 South Geofoam Array Installation

Magnet Extensometer and Pressure Cell Installation Pressure Cell in Base Sand Pressure Cell Installation First Method of Placing Pressure Cell Pressure Cell Cast in Bridge Abutment

slide-46
SLIDE 46

Improved Method of Placing Pressure Cell

Hot Wire Cut Pressure Cell Placed in Cut

slide-47
SLIDE 47

3300 South Magnet Extensometer Data

01/20/99 03/21/99 05/20/99 07/19/99 09/17/99 11/16/99 01/15/00 03/15/00 05/14/00 07/13/00 09/11/00 11/10/00 01/09/01 03/10/01 05/09/01 07/08/01 09/06/01

Date

10 20 30

)

30 40 50

ement (mm

LEVEL 4 LEVEL 6

60 70 80

Settle

LEVEL 0 LEVEL 2

90 100

Level 0 Level 2 Construction Completed (7/28/99)

1% Construction Strain

Level 4 Level 6 Level 8 Level 9 Load Distribution Slab placed Load Distribution Slab Curb placed Granular Borrow Open Graded Base

slide-48
SLIDE 48

100 South Magnet Extensometer Data Post-Construction Settlement Post-Construction Settlement

1% construction strain 2% total in 50 yrs 2% total in 50 yrs.

slide-49
SLIDE 49

3300 South Geofoam Array

Damage to Connections During Construction g g Loading

Damaged Connection

  • Approximately 1%

loading strain can be expected.

  • Strain due to seating of

g untrimmed block and elastic compression.

  • Damaged connection

Damaged connection was later repaired by dowels. Ri id t h ld b

  • Rigid connect should be

avoided.

slide-50
SLIDE 50

Geofoam Transition Zones Post-Construction Settlement

Transition slope 3.5 H : 1 V

25.0

m ent

face of wall 5/30/00 face of wall 3/18/01

Transition zone

10 0 15.0 20.0

ruction Settlem e (m m )

inside edge of moment slab 5/30/00 inside edge of moment slab 3/18/01

  • utside edge

0.0 5.0 10.0 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490

Post-Constr

  • utside edge
  • f emergency

lane 5/30/00

  • utside edge
  • f emergency

lane 3/18/01 baseline survey completed on 11/10/99. 2534 2535 2536 2537 2538 2539 2540 254 2542 2543 2544 2545 2546 2547 2548 2549

Mainline Stationing (m)

slide-51
SLIDE 51

Geofoam Pressure Cell Measurements

Pressure Versus Time 3300 South Street Geofoam Array

60.0 70.0 80.0

Pa)

  • Sta. 25+315, Level 0
  • Sta. 25+347, Level 0
  • Sta. 25+315, Level 6
  • Sta. 25+347, Level 5
  • Sta. 25+315, Level 9

30 0 40.0 50.0 60.0

Pressure (kP

  • Sta. 25+347, Level 8

LEVEL 4 LEVEL 6

0 0 10.0 20.0 30.0

LEVEL 0 LEVEL 2

0.0 1/20/99 3/21/99 5/20/99 7/19/99 9/17/99 11/16/99 1/15/00 3/15/00 5/14/00 7/13/00 9/11/00 11/10/00 1/9/01 3/10/01 5/9/01 7/8/01 9/6/01 11/5/01

Date Date

slide-52
SLIDE 52

Geofoam Conclusions

1. Geofoam fills are performing as expected with no major issues. 2 A i l 1 i l i d d i 2. Approximately 1 percent vertical strain occurred during construction. a. Strain due to seating and compression of geofoam. b. This strain can damage rigid connections. 3. Approximately 0.2 percent creep strain (15 mm) has occurred in a 2-year post construction period. 4. The vertical stress distribution that develops in a geofoam wedge fill is complex, but generally diminishes with depth. p , g y p 5. Pressure cell measurements suggest that approximately 45 kPa of vertical stress has developed in the center of the geofoam mass. This is approximately 50 percent of the compressive strength of the This is approximately 50 percent of the compressive strength of the geofoam.

slide-53
SLIDE 53

Geofoam Conclusions (cont.)

6. Creep strain will be relatively small for dead loads that are less than 50 percent of the compressive strength. than 50 percent of the compressive strength. 7. Creep strain in a 10 year post-construction period is expected to be 0.25 to 0.3 percent (18 to 21 mm). 8. Transition zones with the MSE wall need to be designed carefully to minimize differential settlement in the transition zone

slide-54
SLIDE 54

Lime Cement Stabilized Soil

Auger / Mixer for Lime and Cement Lime Cement Column Rig 125 kg/m3 15% lime 85% cement M = 30 Mpa (design); Su 300 to 400 kPa

slide-55
SLIDE 55

Lime Cement Treatment Area

slide-56
SLIDE 56

Lime Cement Column Installation Pattern

slide-57
SLIDE 57

Lime Cement Column Installation X-Section

slide-58
SLIDE 58

1-Stage MSE Wall Construction

Finished MSE wall 1-stage MSE placed over columns

slide-59
SLIDE 59

Lime Cement Column Array

slide-60
SLIDE 60

Objectives of Lime Cement Column Array

  • 1. Determine the Primary Consolidation
  • 1. Determine the Primary Consolidation
  • 2. Measure the Primary Settlement in the Treated Area

and at adjacent structure

  • 3. Measure the Secondary Settlement over 10 yr. Period
  • 4. Determine the Modulus of Treated Area versus

Untreated Ground

  • 5. Measure the Shear Strength of the Treated Ground

6 M d l th C t ti d L T D f ti

  • 6. Model the Construction and Long-Term Deformation

Behavior

slide-61
SLIDE 61

Pressure and Settlement Cells at Lime Cement Column Array

Pressure and Settlement Cells Atop Column Atop Column

slide-62
SLIDE 62

Horizontal Inclinometers

slide-63
SLIDE 63

Borehole Magnetic Extensometer

slide-64
SLIDE 64

Fill Height vs. Load on Lime Cement Columns

14 7/24/98 11/1/98 2/9/99 5/20/99 8/28/99 12/6/99 3/15/00 6/23/00 10/1/00 1/9/01 4/19/01 7/28/01 11/5/01

Date

(m )

2 4 6 8 10 12 14

ill H e ig h t (

Fill 2 Fill 1

F

Stress ratio = 10:1

100 200 300

u re (k P a )

PC1 (off column) PC2 (on 400 500 600

P re s s u

PC2 (on column)

slide-65
SLIDE 65

Inclinometer Measurements at LCC Array

5 10 15 20 25 30 35 40 Meters into Embankment (Inc 302)

10/10/98 10/22/98

Date 10 20 30 40

10/22/98 11/16/98 11/23/98 12/1/98 12/8/98 12/16/98

50 60 70 80 (mm)

12/16/98 12/30/98 1/22/99 2/25/99 3/26/99

90 100 110 120 130 Settlement

5/3/99 5/27/99 7/8/99 8/16/99 9/15/99

130 140 150 160 170

11/2/99 12/29/99 2/3/00 6/1/00 6/8/2000

180 190

6/8/2000 10/3/00 3/22/01

Wall face

slide-66
SLIDE 66

Ground Settlements at LCC Array

(July 98 to November 01)

20 40 60

mm)

Ftg 1 Ftg 2 Inc 1 Inc 2 LC1 80 100 120 140 160

Settlement (m

LC2 LC3 LC4 LC5 LC6 160 180 200 LC7 LC8 10 LC9

Wall face

  • 10

10

mm)

LC9 LC10 LC11 LC12 LC13 LC14 20 30 40

Settlement (m

LC14 LC15 LC16 LC17 LC18 LC19

S b ildi

50 60 LC19 LC20 LC21

  • S. building
slide-67
SLIDE 67

Magnetic Extensometer Measurement

23 cm of settlement at magnet extensometer 23 cm of settlement at magnet extensometer location w/ 12 cm of settlement below column installation depth

slide-68
SLIDE 68

Horizontal Displacements from Vertical Inclinometer

  • Max. = 4 cm
slide-69
SLIDE 69

LCC Construction Performance

1. Primary Consolidation Settlement was reduced from about 1.0m to 0.2 m at LCC array. 2. Construction Settlement of about 18 cm occurred at MSE wall face. 3 Construction Settlement of about 3 to 4 cm occurred at nearby 3. Construction Settlement of about 3 to 4 cm occurred at nearby bldg. 4. Lateral Displacement of about 4 cm occurred at wall face. 5. Column is carrying about 10 times the stress as the adjacent untreated ground. 6 I t ll ti t d t b i ith W t h 6. Installation rates and cost became an issue with Wasatch Constructors and this technology was only used at one location.

slide-70
SLIDE 70

Long-Term Array Locations

Location Type I 80 @ 300 W MSE W ll Li C t C l I-80 @ 300 W. MSE Wall on Lime Cement Columns I-15 @ 3300 S. Geofoam Wall (Creep & Load) I-15 @ 3500 S. MSE Wall (Deformation & Settlement) I 15 @ 200 S MSE W ll (S ttl t) I-15 @ 200 S. MSE Wall (Settlement) I-15 @ S. Univ. Embankment (Settlement) I-80 @ W. Temple MSE Wall (Lt. Weight Backfill) I-15 @ 800 S. Geofoam (Lateral Earth Pressure) I-15 @ 100 S. Geofoam (Differential Icing) I-15 @ 2100 S. Embankment (Settlement) I-15 @ 400 S. Embankment (Settlement)

slide-71
SLIDE 71

Questions

Bartlett@civil.utah.edu