(a) Better Consolidation Modelling of Soils under the Test Embankment - - PowerPoint PPT Presentation

a better consolidation modelling of soils under the
SMART_READER_LITE
LIVE PREVIEW

(a) Better Consolidation Modelling of Soils under the Test Embankment - - PowerPoint PPT Presentation

(a) Better Consolidation Modelling of Soils under the Test Embankment at Chek Lap Kok Airport !" Test Embankment at Chek Lap Kok Airport !" !" !" Radial coordinate r (mm) 0 0 100 200 300 400 500 600 700 800 900 r d


slide-1
SLIDE 1

(a) Better Consolidation Modelling of Soils under the Test Embankment at Chek Lap Kok Airport !" !" Test Embankment at Chek Lap Kok Airport !" !"

100 200 300 400 500 600 700 800 900

Radial coordinate r (mm)

10

  • 5

upper marine clay r d r s r e

  • 15
  • 10

n (mPD) upper alluvium Smear zone

  • 20

Elevation lower marine clay

  • 30
  • 25

lower alluvium Vertical drain

  • 35
slide-2
SLIDE 2

(a) Better Consolidation Modelling of Soils under the Test Embankment at Chek Lap Kok Airport !" !" Test Embankment at Chek Lap Kok Airport !" !"

3 2 2.5 1 Sondex anchor (a) 1.5 2 ement (m) 1 2 3 4 1 Settle 4 1 2 3 0.5 4 200 400 600 800 1000 1200 Contract Days

slide-3
SLIDE 3

(b) Application of Interferometric Synthetic Aperture Radar (InSAR) - satellite based radar remote sensing technology Radar (InSAR) - satellite based radar remote sensing technology

slide-4
SLIDE 4

Settlement of the Chek Lap Kok Airport #$%& #$%&

  • ver 315 Days: (29 12 98 - 09 11 99)

820500

  • ver 315 Days: (29.12.98 - 09.11.99)

9500 819 818500 17500 808500 809500 810500 811500 812500 81

  • 5
  • 10
  • 15
  • 25
  • 30
  • 40 -50

(mm)

slide-5
SLIDE 5
  • 5. Reclamation Methods for a Third
  • 5. Reclamation Methods for a Third

Runway at HK International Airport Runway at HK International Airport

(a) (a) Undredged Undredged mud with vertical drains mud with vertical drains (b) (b)Deep cement mixing (DCM) Deep cement mixing (DCM)

slide-6
SLIDE 6

(a) (a) Undredged Undredged mud with vertical drains mud with vertical drains

Wick Drains (Prefabricated (Prefabricated Vertical Drains)

Purpose: speed up consolidation, reduce post-construction settlement reduce post-construction settlement Limitation: no good for loose sand A li ti l il b l b bl Applications: clayey soils, below or above water table, very efficient and economy, easy to install …

slide-7
SLIDE 7

Band drains ('() '())

slide-8
SLIDE 8

Geo-textile Drainage channels

slide-9
SLIDE 9

2 2 2 2 2 2

) 1 ( z u c r u r r u c t u

e v e e h e

! ! " ! ! " ! ! # ! ! z r r r t ! ! ! !

) 1 )( 1 ( 1 ) 1 )( 1 ( ) 1 (

r v r v

U U U U U U $ $ $ # % $ $ # $

2 2

); ( ; ); ( t c T T f U t c T T f U

h r r r v v v v

# # # #

2 2

4 ); ( ; ); ( R f d f

r r r v v v

slide-10
SLIDE 10

'()*+,- '()*+,- %&.%/012 %&.%/012

slide-11
SLIDE 11

Pre-loading – removed afterward removed afterward

slide-12
SLIDE 12

Purpose of Vertical Drains and Preloading

(a) Vertical Drains '()

  • Speed up escaping/dissipation of excess

porewater/ pressure due to preloading (b) Preloading*+

  • Making the soil over-consolidated and reducing

both “primary” and creep consolidation More accurately speaking, reducing instant compression and creep

slide-13
SLIDE 13

Soil pressure/stress before construction Soil pressure/stress after construction Log(Pressure) (or Stress) Settlem ent/strain - large Settlem ent/strain - sm all Large creep settlem ent/strain Settlem ent/strain - sm all Sm all creep settlem ent Pre-loading to here

Illustration of settlement/strain reduction using pre-loading technique reduction in “primary” consolidation (instant) settlement/strain

  • reduction in primary consolidation (instant) settlement/strain
  • reduction in “secondary” consolidation (creep) settlement/strain
slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17
slide-18
SLIDE 18

(b) Deep cement mixing (DCM) (b) Deep cement mixing (DCM)

slide-19
SLIDE 19
slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23

Deep cement mixing Deep cement mixing (DCM) at marine site (DCM) at marine site (DCM) at marine site (DCM) at marine site

slide-24
SLIDE 24

Unconfined compression strength qpeak (kPa) vs. Aw and f UC t t ( ft Yi d L i 1998) wi from UC tests (after Yin and Lai 1998)

1500 2000 500 1000 w

i=100%

w

i=80%

qpeak (kPa)

500 5 10 15 20 w

i=60%

5 10 15 20 C em ent/S

  • il R

atio A

w%

slide-25
SLIDE 25

(c) Sand compaction pile (sand drains) (c) Sand compaction pile (sand drains)

slide-26
SLIDE 26
slide-27
SLIDE 27
  • 6. Conclusions and Recommendations
  • 6. Conclusions and Recommendations

6.1 6.1 Conclusions Conclusions

(1) (1) Reclamations were done in the past and also are needed in Reclamations were done in the past and also are needed in the future. the future. (2) (2) Confinements and improvement of mud in place are Confinements and improvement of mud in place are required and can be done using various methods. required and can be done using various methods. required and can be done using various methods. required and can be done using various methods. (3) (3) The two methods of (a) The two methods of (a) undredged undredged mud with vertical mud with vertical drains (plus preloading) and (b) deep cement mixing drains (plus preloading) and (b) deep cement mixing ( l l di ) t it t h i ll ibl t fi ( l l di ) t it t h i ll ibl t fi (plus preloading) at site are technically possible to confine, (plus preloading) at site are technically possible to confine, improve mud in place and to reduce the post improve mud in place and to reduce the post-

  • construction

construction settlement. settlement. (4) (4) Other methods such as sand drains (sand compaction pile) Other methods such as sand drains (sand compaction pile) and a combination of the methods could be used and even and a combination of the methods could be used and even better better better. better.

slide-28
SLIDE 28
  • 6. Conclusions and Recommendations
  • 6. Conclusions and Recommendations

(5) (5) Previous study and cases have indicated large settlements Previous study and cases have indicated large settlements

  • f marine reclamations (also large post
  • f marine reclamations (also large post-construction

construction

  • f marine reclamations (also large post
  • f marine reclamations (also large post construction

construction settlement such as Japan Kansai Airport. settlement such as Japan Kansai Airport. (6) (6) Care must be paid to the creep of the marine soils with Care must be paid to the creep of the marine soils with d i ( d DCM) d h l l i h d d i ( d DCM) d h l l i h d (i i (i i drains (and DCM) and the calculation methods drains (and DCM) and the calculation methods (it is (it is recommend to use Hypothesis B method and Yin’s recommend to use Hypothesis B method and Yin’s simplified method; also consolidation solutions by Yin simplified method; also consolidation solutions by Yin p ; y p ; y and Zhu) and Zhu). . (7) (7) No mater which method to be used, the reclamation with No mater which method to be used, the reclamation with l di h ll t t li ibl d h ll l t l di h ll t t li ibl d h ll l t pre pre-

  • loading shall start as earlier as possible and shall last

loading shall start as earlier as possible and shall last for a longer duration for a longer duration in order to reduce the post in order to reduce the post-

  • construction settlement)

construction settlement). . )

slide-29
SLIDE 29
  • 6. Conclusions and Recommendations
  • 6. Conclusions and Recommendations

6.2 6.2 Recommendations Recommendations

(1) (1) Study is needed on the proposed two methods of (a) Study is needed on the proposed two methods of (a) d d d d d d d i h i l d i ( l l di ) d d i h i l d i ( l l di ) d undredged undredged mud with vertical drains (plus preloading) and mud with vertical drains (plus preloading) and (b) deep cement (b) deep cement mixing ( mixing (plus preloading) at site. plus preloading) at site. (2) (2) Study is also needed on other methods such as sand drains Study is also needed on other methods such as sand drains ( ) ( ) y (sand compaction pile) and a combination of the methods. (sand compaction pile) and a combination of the methods. (3) (3) Large Large-

  • scale lab model tests are recommended to simulate

scale lab model tests are recommended to simulate th th d i di id ll bi ti f th th th d i di id ll bi ti f th these methods individually or a combination of them. these methods individually or a combination of them. (4) (4) Field trial study is also recommended on these methods. Field trial study is also recommended on these methods. (5) (5) Calculation methods shall be used to predict the Calculation methods shall be used to predict the p settlements of reclamations in lab models and in the field settlements of reclamations in lab models and in the field trial and pore water pressure dissipation inside the trial and pore water pressure dissipation inside the marine soils and are verified by comparing with measured marine soils and are verified by comparing with measured marine soils and are verified by comparing with measured marine soils and are verified by comparing with measured data. data.

slide-30
SLIDE 30

Thank You Thank You 3345 3345 3345 3345

Tel: 2766 6065, Mobile: 9716 5375 Email: cejhyin@polyu.edu.hk Webpage: www cse polyu edu hk/ cejhyin

94

Webpage: www.cse.polyu.edu.hk/~cejhyin