SLIDE 4 Recent Duratek Contract Awards
by Leila Crawford and Steve Horvath
4 DOE Work
In June and July, Duratek was awarded four new environmental remediation and waste management subcontracts that expand our presence at U.S. Department of Energy (DOE) sites where we are already working. The contracts are expected to be worth at least $70 million in additional revenue over the next five years. Together with work already in progress at Oak Ridge, Hanford, and Rocky Flats, these awards provide a firm base for continuing and expanding Duratek’s presence at these key DOE sites throughout this decade. Rocky Flats Waste Management: Duratek and a joint venture partner, Los Alamos Technical Associates (LATA), won one of three major waste management subcontracts awarded by Kaiser Hill Company at the Rocky Flats Environmental Technology Site (RFETS), DOE’s former weapons manufacturing complex located near Denver, Colorado. This subcontract authorizes Duratek-LATA to compete for about $67 million worth of waste management tasks to be performed in the next four years. These tasks are a follow-on and expansion of work that has been done by approximately 40 Duratek employees at RFETS since 1995. In July, Duratek-LATA was awarded the first task under this subcontract, development of a disposal strategy for RFETS low-level/mixed waste. Over the next year, bids will be prepared for approximately 40 additional tasks. Hanford Waste Treatment Plant Support: The 10-year, $4 billion Hanford Waste Treatment Plant (WTP) project will provide final treatment and disposal of 53 million gallons of radioactive waste currently stored in underground tanks at the DOE’s Hanford Site in Washington State. The project calls for designing, constructing, and commis- sioning a large complex of first-of-a-kind
- facilities. Duratek has supported the WTP effort
since 1997 by providing the vitrification technology and systems to be used for waste
- treatment. Last month, Duratek signed two
multi-year subcontracts with Bechtel National,
- Inc. (BNI), DOE’s prime contractor for the
design and construction of the WTP, to continue research, development, and testing for the pilot- scale, high-level and low-level radioactive waste vitrification systems and design support for the full-scale systems. The two subcontracts are valued at $18.6 million over the next six months, and will continue on a task order basis for up to five years. ! In July, BNI also awarded a subcontract to CH2M Hill Construc- tors to support commissioning of the WTP, which is scheduled to begin radioactive
- perations in 2007. Duratek, as a member of the
CH2M Hill team, will supply experts to help develop procedures, training, and testing
- programs. The subcontract is for one year with
possible future extensions and the volume of work will vary year by year. Oak Ridge K-25/27 D&D: Duratek recently received its fourth major subcontract at DOE’s Oak Ridge Reservation when the Company was selected by Bechtel Jacobs Company to perform the first phase of decontamination and decom- missioning (D&D) of the K-25/K-27 Buildings. The 4.5 million square-foot K-25/K-27 Building complex was constructed in the 1940s to support the nation’s uranium enrichment program and at that time was the largest building under a single roof in the world. Duratek’s subcontract is valued at approximately $22 million over three years and covers characteriza- tion and removal of hazardous materials in the buildings prior to demolition, followed by packaging and transportation of these materials for disposal. Government estimates for the complete D&D effort, which will be subcon- tracted in phases, exceed $200 million. Duratek plans to bid on future phases of the D&D work. Hanford Soils D&D: Based on the Company’s excellent performance on other Hanford subcontracts, Duratek was selected by Bechtel Hanford, Inc. (BHI) to remove 150,000 tons of radioactively contaminated soils from an abandoned reactor area near the Columbia River and haul it to the Environmental Restoration Disposal Facility (ERDF). On July 2, BHI asked Duratek to take over the project for three to six months pending re-bid of the entire subcontract due to nonperformance of the former subcontractor. Duratek has started strong, beating the three-week milestone for completion of the operational readiness review and initiating soil hauling to ERDF (which is also operated by Duratek) a week earlier than
- scheduled. The value of this work is $1.7 to
$3.7 million, depending on the duration. Duratek will also bid on the continuation subcontract, projected to be a four-year, $12 million effort.
Commercial Services Projects
Decommissioning cost estimate for a nuclear research reactor. Duratek was recently notified in July 2001 of an impending award to develop a decommissioning study for a nuclear research reactor facility planning their
- decommissioning. Duratek continues to win
recognition and awards associated with assisting the Test, Research, and Training Reactor community with decommissioning of their
- facilities. The project value is approximately
$17,000. Remediation planning and radioactive waste support for a Superfund site with a radioactively contaminated area. Duratek was awarded a contract in May 2001 to work with the site contractor and the U.S. Environmental Protection Agency (EPA) to remove and dispose
- f soil with radioactive contaminants. The first
planning phase of the project is valued at $150,000 and the total project scope has the potential to generate revenue of up to $5.5 million. Decommissioning services to a major pharmaceutical firm. Duratek was awarded a contract in July 2001 to provide characterization, remediation, and release services for laboratory buildings contaminated from radiopharmaceutical
- perations. The total project value is estimated at
approximately $200,000.
Waste Processing Projects
Radioactive waste processing contract extension from Exelon Corporation. In July, Duratek was awarded a five-year contract renewal for low-level radioactive waste process- ing services to Exelon’s Illinois nuclear plants, worth approximately $12.5 million. Process spent fuel racks from Limerick Nuclear Power Plant. Duratek was notified in July 2001 of an award by Exelon Corporation for the transportation, processing, and disposal of radioactively contaminated fuel racks from the Limerick station, during an outage in Spring
- 2002. Duratek will process the racks at Duratek’s
Memphis, Tennessee, facility. The total project value is estimated at $300,000. Additional scope awarded at Connecti- cut Yankee decommissioning project. Duratek was notified of additional work scope in July 2001 by Bechtel Power Corporation at the Connecticut Yankee decommissioning project. The scope of work is to provide radioactive waste transportation, processing, and disposition of large metal components from the turbine building at the Haddam Neck nuclear plant in Connecticut, which is undergoing decommissioning. The waste will be processed at Duratek’s facilities in
- Tennessee. This additional scope is valued at
approximately $3.5 million and the work will commence in August 2001.
Attention Duratek Investors:
The Investor Information section of the Duratek website (www.duratekinc.com) has an
- ption to sign up for e-mail alerts for news
and events. Sign up today for your alerts to news on Duratek (Nasdaq: DRTK). For calendar alerts, click on the Calendar button and enter your preferences where instructed. For news alerts, click on Information Request, then click on E-Mail Alerts.