Cost Overruns and Their Precursors : An Empirical Examination of - - PowerPoint PPT Presentation

cost overruns and their precursors
SMART_READER_LITE
LIVE PREVIEW

Cost Overruns and Their Precursors : An Empirical Examination of - - PowerPoint PPT Presentation

Cost Overruns and Their Precursors : An Empirical Examination of Major DoD Acquisition Programs International Cost Estimating and Analysis Association Denver, CO 10-13 June 2014 Alan K. Gideon, P.E. Dr. James Wasek Dr. Enrique Campos-Naez


slide-1
SLIDE 1

Cost Overruns and Their Precursors:

An Empirical Examination of Major DoD Acquisition Programs

International Cost Estimating and Analysis Association

Denver, CO 10-13 June 2014

Alan K. Gideon, P.E.

  • Dr. James Wasek
  • Dr. Enrique Campos-Nañez
  • Dr. Pavel Fomin

The School of Engineering and Applied Science

  • f The George Washington University

in partial satisfaction of the requirements for the degree of Doctor of Philosophy

slide-2
SLIDE 2

2

  • Trends across the

wider commodity list improved into the 1990’s (Younssi)

  • Aircraft remained

relatively immune to improvement

  • Graphic does not

include outliers Cost overruns remain a serious problem

* From Younossi, et al, using a wider group of commodities

`A million dollars here, and a million dollars there, and pretty soon, gentlemen, you`re talking about real money.` Attributed to Senator E. Dirksen

The Persistence of the Problem

Aircraft/Missiles

Combat Aircraft/Ships

95% CI for the Mean 3.0 2.5 2.0 1.5 1.0 0.5

slide-3
SLIDE 3

3

  • Cost and schedule overruns are not a new problem
  • Previous work
  • Has tended to cast “cost overrun” as an amorphous lump, or
  • Investigators have dug deeper into the details of their specialties
  • Previous papers and policy changes have failed to resolve the issue
  • RAND

Inadequate initial funding Unexpected technical difficulties Requirement changes Estimating errors Cost growth ~ ƒ (quantity purchased) (Dews et al. 1979)

  • IDA added

Supply, labor shortages Concurrency Force majeur Cost growth ~ ƒ (median domain growth rates) (Asher and Maggelet 1984)

  • WSARA 2009, updates to DoDI 5000 series, lower level directives

(P.L. 111-23) Previous approaches have addressed symptoms of the basic question

Previous Approaches to the Problem

slide-4
SLIDE 4

4

Technical Risk as a Precursor to Cost

  • There are no truly independent variables:
  • Programmatic/Business
  • Technical
  • Schedule
  • Cost

“All roads lead to Rome”, and additional cost Contract Changes Technical/Performance Schedule Cost

slide-5
SLIDE 5

5

Decisions, Decisions, Decisions…

Work scope and costs are tied to Milestone decisions

From: Naval Sea Systems Engineering Technical Review Handbook

Notice the caveat

Material Solution Analysis (MSA)

Material Development Decision System Requirements & Technology Development Systems Architecture & Technology Demonstration

A

Technology Development

System Design System Demonstration

Engineering & Manufacturing Development Production & Deployment

LRIP/ IOT&E /Full Rate Production & Deployment FRP Decision Review Sustainment & Disposal Post PDR A Post CDR A

Pass 1 Pass 2 Annual Sufficiency Reviews

1 2 3 4 5 6

Operations & Support ITR ASR SRR I SRR II SFR PDR2 IBR CDR2 Preferred System Concept System Specification System Functional Baseline Allocated Baseline Product Baseline TRA SSR TRA IRR PDR12 TRR FRR OTRR SVR/ FCA/PRR PCA ISR Product Baseline

1 PDR Closure 2 For ships, PDR and CDR to take

place prior to MS B B C

Systems Engineering Technical Reviews

slide-6
SLIDE 6

6

Significant work scope and costs begin before MS B for ships

The Cost Prediction Initialization Point

  • It is important to note a significant normally unstated difference between

the acquisition of ships and the acquisition of other customized purchases the Department of Defense makes

  • We don’t build prototype ships
  • Outcomes occasionally notwithstanding, the intent is that every ship built for

the U.S. Navy will become an operational asset.

  • This affects the definition of “baseline cost”, used later
slide-7
SLIDE 7

7

Knowing the Neighborhood

  • Metaphorically speaking, the more interesting destinations sometimes pass

through or near some bad neighborhoods – creating risks

  • Cox paper
  • Does not show confidence levels
  • “Grade inflation”
  • Cannot show

performance to plan

(From: Rippe, Hogan, Elliot 2011)

Joint Confidence Level Scatterplot Risk “Cube” (Matrix)

$800K $700K $600K $500K $400K $300K $200K $100K

50 65 80 95 110

Months Duration Total Cost

1 2 3 4 5 Consequence Probability 1 2 3 4 5

slide-8
SLIDE 8

8

How Bad Can it Get?

  • Like asking how low a

particular stock price can go

  • Sound decisions can only be made with sound information

Sound program and portfolio decisions require solid data, sound analysis

Program Cost Ratio

Probability

1 2 3 4

Program Cost Ratio

0.4 0.3 0.2 0.1 0.0 1 2 3 4 5 6 7 8 9

Years Since MS 0 6000 5000 4000 3000 2000 1000 $M (BY14)

1990 1992 1994 1996 1998 2000 2002 5.0K 4.5K 4.0K 3.5K 3.0K 2.5K 2.0K 1.5K 1.0K 0.5K

NASDAQ Composite (^IXIC)

slide-9
SLIDE 9

9

The Cost Risk Box Canyon

  • Markowitz “portfolio effect”
  • Risk is minimized through

diversification

  • Requires that assets be truly

independent

  • Presumes investors are rational
  • DoD 7000.14R: recommends

budgeting to the most probable cost

  • DAPA Report 2006: recommended

an 80% confidence level Official policy is at odds with program behavior and decision patterns

  • DTM 09-027 (5)(e): requires justification if the recommended confidence level

is less than 80%

  • Possible maximum values associated with violating these “most probable

costs” is not part of anyone’s spreadsheet.

slide-10
SLIDE 10

Avoiding the Box Canyon

“Six months after winning a coveted $35 billion aerial tanker contract, Boeing Co. announced last year that the first planes would cost $1 billion more than promised during the contract’s competition. “ CQ WEEKLY – IN FOCUS, Jan. 21, 2012

  • Smart
  • Reminded us of the “flaw of averages”
  • Value at Risk: “the maximum loss not exceeded with a given probability”
  • Recommended lognormal v. normal distribution for lower risk
  • Conditional Tail Expectation
  • “Conspiracy of hope” percentile funding is, unfortunately, built on faulty

logic and does not work

  • The way an aviator avoids becoming another “box canyon statistic” is by

not flying into them Avoiding box canyons requires adopting different decision inputs

10

slide-11
SLIDE 11

11

Five Year Family Tendencies

Unlike previous approaches

  • We limit ourselves to a five

year “crystal ball”

  • Not claiming to see too far

into the future

  • Consistent with the needs of

the Five Year Defense Plan

  • Add two more factors
  • Difficulty of the task to be

performed

  • Funding dedicated to risk

mitigation

  • Different points of reference
  • Obviously different outcome

spectra

where y = years between program approval and IOC 0 = Program approval point

slide-12
SLIDE 12

12

Distribution of Five Year Cost Ratios

Different Outcomes Imply Different Input Details Ratio of 5yr Cost to Initial Cost

1.0 1.5 2.0 2.5 3.0

Number of Instances

slide-13
SLIDE 13

13

The Leading Edge of Technology

  • Estimates for

“modest” improvements are more accurate

  • No penalty for under-

estimating costs

  • ~1970 marks the

availability of greater computing power

  • Engine design
  • Reduced RCS
  • Aircraft were divided

into three groups

  • Pre-1970
  • Post 1970
  • Derivatives & special

cases

All data taken from open sources Computing power has made significant improvements possible

slide-14
SLIDE 14

14

The Leading Edge of Technology

All data taken from open sources

  • ~1970 marks the

availability of greater computing power

  • Engine design
  • Reduced RCS
  • Ships were divided

into three groups

  • Pre-1970
  • Post 1970
  • Derivatives

Some progress was being made before significant computing improvement

Intentionally avoided “cutting edge” performance in favor of greater reliability

slide-15
SLIDE 15

30000 25000 20000 15000 10000 5000 30000 25000 20000 15000 10000 5000 Actual 5 yr Q-A Cost Data Fitted per Model

Combat Aircraft 5 yr Cost per 3-Variable Model

15

Results to Date: Aircraft

R2 = 99.12% R2 (adj) = 98.68% S = 967.3

Cost|5yr = ƒ(domain tendencies, tech risk, [RDTE/Q-A Cost]0)

Analysis of Variance Variable P Cost @ MS B 0.0000 Tech risk 0.7304 (RDTE/Cost)B 0.3396

slide-16
SLIDE 16

40000 30000 20000 10000 40000 30000 20000 10000 Actual 5 yr Q-A Cost Data Fitted per Model

Combatant Ship 5 yr Cost per 3-Variable Model

16

Results to Date: Ships

R2 = 93.36% R2 (adj) = 83.40% S = .8023

  • Not quite as good, but respectable
  • Johnson transform required

Cost|5yr = ƒ(domain tendencies, tech risk, [RDTE/Q-A Cost]0)

Analysis of Variance Variable P Cost @ MS 0 0.6801 Tech risk 0.9389 (RDTE/Cost)B 0.0951

slide-17
SLIDE 17

Using the Asher-Maggelet Approach: Aircraft

where y = years between program approval and IOC 0 = Program approval point

P = 0.0000000

slide-18
SLIDE 18

Using the Asher-Maggelet Approach: Ships

where y = years between program approval and IOC 0 = Program approval point

P = 0.0656

slide-19
SLIDE 19

19

Contract Implications

  • “There ain’t no such thing as a free lunch.” (TANSTAAFL)
  • Robert Heinlein
  • Risk doesn’t go away just because the contractor is forced to assume it
  • The contractor has to make a profit in order to stay in business
  • Contractor’s answer is to calculate the six-sigma probabilities and be very, very

stubborn – especially when he is the only available supplier

  • Can we use this new method to have more complete discussions about risk and

the need to establish more accurate costs? DoD’s Monopsic Status Skews Negotiations

slide-20
SLIDE 20

20

Portfolio Implications

  • Upper management needs to balance the entire portfolio, especially if

future budgets are reduced as many people have postulated

  • No one likes surprises
  • DoD cannot afford egg on its face – every service and program will suffer
  • Intended to augment, not replace current methods
  • Portfolio and “Grand Portfolio” views of available budgets
  • Provides a higher level comparison to other programs in the same domain
  • Allows a head start on resolving problems
  • Where next?
  • The two examples presented here were chosen because of the authors’

familiarity with the end products.

  • Similar relationships can be derived for other product lines

The Proposed Approach May Provide Lower Portfolio Risk

slide-21
SLIDE 21

21

Thank You

Questions?

GideonAK@GWU.edu

slide-22
SLIDE 22

22

Asher, Norman J., and Theodore F. Maggelet. 1984. “On Estimating the Cost Growth of Weapon Systems”. P-1494. Institute for Defense Analyses. Congress of the United States. 2009. Weapons Systems Acquisition Reform Act of 2009. Cox, Anthony (Tony) Louis. 2008. “What’s Wrong with Risk Matrices?” Risk Analysis 28 (2) (April): 497–512. doi:10.1111/j.1539-6924.2008.01030.x. Department of the Navy. 2009. “Naval Systems Engineering Technical Review Handbook”. Naval Sea Systems Command. Dews, Edmund, Giles K. Smith, Allen Barbour, Elwyn Harris, and Michael Hesse. 1979. “Acquisition Policy Effectiveness: Department of Defense Experience in the 1970s”. R-2516-DR&E. RAND Corporation. Editors, Air Force Magazine. 2009. “Clarification.” Air Force Magazine, March. Heinlein, Robert A. 1966. The Moon Is a Harsh Mistress. New York: Orb. Jackson, Paul, Kenneth Munson, and Lindsay Peacock. 2010. Jane’s All the World’s Aircraft. 2010th– 2011th ed. Alexandria, VA: Jane’s Information Group, Inc. Khan, Jawad, Wenyang Duan, and Salma Sherbaz. 2012. “Radar Cross Section Prediction and Reduction for Naval Ships.” Journal of Marine Science and Application 11 (2) (June): 191–199. doi:10.1007/s11804-012-1122-5.

References

slide-23
SLIDE 23

23

References

Lambert, Mark, Kenneth Munson, and Michael J. H. Taylor. 1993. Jane’s All the World’s Aircraft. 1993rd–1994th ed. Alexandria, VA: Jane’s Information Group, Inc. Markowitz, Harry M. 1990. “Foundations of Portfolio Theory” presented at the Nobel Lecture, December 7, Royal Swedish Academy of Sciences. Marshall, A. W., and W. H. Meckling. 1959. “Predictability of the Costs, Time, and Success of Development”. P-1821. RAND Corporation. McPherson, Joe. undated. “DDG 100 Zumwalt Class”

  • Muldoon. 2013. “F-35 vs F-15SE: South Korea’s F-X-III Competition - Part III The Silent Eagle.”

American Innovation. http://manglermuldoon.blogspot.com/2013/06/f-35-vs-f-15se-south-koreas- f-x-iii.html. Office of the Under Secretary, Acquisition, Technology and Logistics. 2006. “Risk Management Guide for DoD Acquisistion, Sixth Edition, Version 1.0”. Department of Defense. http://www.acq.osd.mil/se/docs/2006-RM-Guide-4Aug06-final-version.pdf. ———. 2009. “Directive-Type Memorandum (DTM) 09027 - Implementation of the Weapon Systems Acquisition Reform Act of 2009.” Office of the Under Secretary, Comptroller. 2013. “National Defense Budget Estimates for FY2014”. Department of Defense. http://comptroller.defense.gov/defbudget/fy2014/FY14_Green_Book.pdf.

slide-24
SLIDE 24

24

References

Pike, John. 2013. “Radar Cross Section (RCS)”. Global Security. Radtke, J.L.. 2008. “The Energetic Performance of Vehicles.” The Open Fuels & Energy Science

  • Journal. 1 (2008): 11-18. http://www.benthamscience.com/open/toefj/articles/V001/11TOEFJ.pdf

Rich, Ben R, and Leo Janos. 1994. Skunk Works: A Personal Memoir of My Years at Lockheed. Boston: Little, Brown. O’Donnell, Robert M. 2010. “Radar Systems Engineering Lecture 7, Part 1: Radar Cross Section” presented at the IEEE New Hampshire Section Meeting, January 1. Rippe, Antonio, Greg Hogan, and Darren Elliot. 2011. “Joint Cost Schedule Model (JCSM)” presented at the ISPA/SCEA Conference, June. Sanchez, Hynuk, Benoit Robert, Mario Bourgault, and Robert Pellerin. 2008. “Risk Management Applied to Projects, Programs, and Portfolios.” International Journal of Managing Projects in Business 2 (1) (July): 14–35. doi:10.1108/17538370910930491. Sharpe, Richard. 1994. Jane’s Fighting Ships. 1994th–1995th ed. Alexandria, VA: Jane’s Information Group, Inc. Skolnik, Merrill I. 1974. “An Empirical Formula for the Radar Cross Section of Ships at Grazing Incidence.” IEEE Transactions on Aerospace and Electronic Systems 10 (2) (March): 1.

slide-25
SLIDE 25

25

References

Smart, Christian B. 2012. “Here, There Be Dragons: Considering the Right Tail in Risk Management.”

  • J. of Cost Analysis and Parametrics 5 (2): 65–86.

Williams, P.D.L., H.D. Cramp, and Kay Curtis. 1978. “Experimental Study of the Radar Cross Section

  • f Maritime Targets.” Electronic Circuits and Systems 2 (4) (July): 121–136. doi:10.1049/ij-

ecs:19780026. Younossi, Obaid, Mark V. Arena, Robert S. Leonard, Charles Robert Jr. Roll, Arvind Jain, and Jerry M.

  • Sollinger. 2007. “Is Weapon System Cost Growth Increasing?” RAND Corporation.

Yahoo! Finance, NASDAQ Composite (^IXIC), 1990-2002 http://finance.yahoo.com/echarts?s=^ixic+interactive#symbol=^ixic;range=19900102,20020102;co mpare=;indicator=volume;charttype=area;crosshair=on;ohlcvalues=0;logscale=off;source=;