CEQA Workshop
February 28, 2019 Presented by: Chris Mundhenk, Principal Patrick Angell, Senior Director
El Dorado County Planning Commission
19-0255 A 1 of 75
Commission CEQA Workshop February 28, 2019 Presented by: Chris - - PowerPoint PPT Presentation
El Dorado County Planning Commission CEQA Workshop February 28, 2019 Presented by: Chris Mundhenk, Principal Patrick Angell, Senior Director 19-0255 A 1 of 75 Background of CEQA 19-0255 A 2 of 75 What is CEQA? California
February 28, 2019 Presented by: Chris Mundhenk, Principal Patrick Angell, Senior Director
19-0255 A 1 of 75
19-0255 A 2 of 75
– “The foremost principle under CEQA is that the Legislature intended the act ‘to be interpreted in such manner as to afford the fullest possible protection to the environment within the reasonable scope of the statutory language.’ [citing Friends of Mammoth]"
University of California (1988) 47 Cal.3d 376
19-0255 A 3 of 75
(CEQA Guidelines 15002)
environmental effects of proposed activities
reduce environmental damage
feasible alternatives or mitigation measures
for agency approval of projects with significant environmental effects
coordination in review of projects
in planning process, but it not a planning act
denies a project
19-0255 A 4 of 75
– Require changes in a project to lessen or avoid significant effects, when feasible – Disapprove a project to avoid significant effects – Approve a project with unavoidable significant effects if project’s benefits outweigh those effects – Comment on CEQA documents prepared by other agencies – Impose fees from project applicants for CEQA implementation
(CEQA Guidelines 15041 – 15045 and 15204)
19-0255 A 5 of 75
– Superior Court decision – applies only to the case at hand – Appellate Court decision – if “published”, becomes law of the land – Supreme Court decision – law of the land
– Non-regulatory advice, carries no force of law
19-0255 A 6 of 75
actions not causing significant effects (subject to limitations)
Declaration
power over the project
natural resources held in trust for all Californians
19-0255 A 7 of 75
(CEQA Guidelines 15051)
19-0255 A 8 of 75
(CEQA Guidelines 15381)
19-0255 A 9 of 75
– CA Department of Fish and Wildlife – State Lands Commission – State Department of Parks and Recreation – University of California
(CEQA Guidelines 15386)
19-0255 A 10 of 75
19-0255 A 11 of 75
19-0255 A 12 of 75
– This is usually a quick and informal step
– This action is a “project” under CEQA (CEQA Guidelines Section 15060[c]) – The project is subject to a CEQA exemption
– Selecting the exemption – Documenting the project’s “fit” – Filing the optional Notice of Exemption
19-0255 A 13 of 75
Is it an activity with no possibility of a significant impact?
Is the activity outside the definition of a project? Is the project described in a Statutory Exemption? Is the project described in Categorical Exemption? Is the project covered adequately by previous EIR, Program EIR, or Master EIR? Does the Initial Study show that project will have no significant impact? Project requires an EIR NO NO NO NO NO 2 3 6 YES YES YES YES YES YES NO Activities outside CEQA Notice of Exemption (optional) Finding of no new impact or MND ND or MND 19-0255 A 14 of 75
– the whole of an action, which has a potential for resulting in either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment
– requires the exercise of judgment or deliberation when the public agency or body decides to approve or disapprove a particular activity
(CEQA Guidelines 15357, 15378)
19-0255 A 15 of 75
– public works construction and related activities clearing or grading of land, improvements to existing public structures
19-0255 A 16 of 75
– Activity A and B are part of the same project when:
– Activity B is a reasonably foreseeable future consequence of Activity A, – Activity B is a future phase of Activity A, – Activity B provides essential public services need to implement Activity A, or – Activity A and B are integral parts and lack independent utility.
19-0255 A 17 of 75
– i.e., taking an action that will lead to project implementation
Save Tara v. City of West Hollywood (2008) 45 Cal.4th 116
19-0255 A 18 of 75
19-0255 A 19 of 75
– Qualifying projects must fit the definition in the statute – No public review is required – File a Notice of Exemption for a 35-day statute of limitations
– 33 classes – Qualifying project is not subject to CEQA – No public review is required – File a Notice of Exemption for a 35-day statute of limitations – Restrictions
– Must fit one or more classes of exemptions – No “exceptions” can apply – Can not require mitigation
19-0255 A 20 of 75
– Location (Classes 3, 4, 5, 6, and 11) – Significant cumulative impacts – Significant effect on the environment – Scenic highways – damage to resources – Hazardous waste sites – Historical resource
19-0255 A 21 of 75
– First step: are there “unusual circumstances?”
– Something that sets the project apart from similar development in the area – Lead agency determination is based on substantial evidence
– Second step: if unusual circumstances exist, is there potential for significant impact?
– “Fair argument” standard applies – may the project result in a significant impact? Berkeley Hillside Preservation v. City of Berkeley (2015) __ Cal.App.4th
19-0255 A 22 of 75
19-0255 A 23 of 75
(CEQA Guidelines 15382)
19-0255 A 24 of 75
(CEQA Guidelines 15064.7)
19-0255 A 25 of 75
materials
19-0255 A 26 of 75
What CEQA does…
the effects a project could have on the environment
measures
alternatives to the proposed project
input throughout process What CEQA doesn’t do…
environmental conditions
under evaluation
significant environmental impacts
social issues (e.g., property values)
19-0255 A 27 of 75
– Similar and overlapping consultation with AB 52
19-0255 A 28 of 75
– When it can be fairly argued, based on substantial evidence, in light of the whole record, that a project may have a significant environmental effect
(CEQA Guidelines 15064[a])
19-0255 A 29 of 75
– Facts – Reasonable assumption predicated on facts – Expert opinion supported by facts
– Argument – Speculation – Unsubstantiated opinion or narrative – Clearly inaccurate or erroneous information – Socioeconomic impact not linked to physical environmental impact
19-0255 A 30 of 75
19-0255 A 31 of 75
(CEQA Guidelines 15065)
19-0255 A 32 of 75
(Cont.)
19-0255 A 33 of 75
– Note: The fair argument also applies to an MND’s mitigation
substantial evidence that its mitigation is infeasible
19-0255 A 34 of 75
19-0255 A 35 of 75
Negative Declaration Time Limitation
Initial Study prepared
Mitigation measures identified and agreed upon by project proponent Negative Declaration prepared Proposed Negative Declaration issued for public notice and review
Comments considered Negative Declaration adopted
Mitigation reporting and monitoring program adopted Lead Agency takes action on project
Notice of Determination filed
approval Notice of Determination posted
filing Responsible agency makes decision on project
Agency
19-0255 A 36 of 75
19-0255 A 37 of 75
19-0255 A 38 of 75
(1) revisions in the project plans or proposals made by, or agreed to by, the applicant before the proposed negative declaration and initial study are released for public review would avoid the effects
would occur, and (2) there is no substantial evidence in light of the whole record before the public agency that the project, as revised, may have a significant effect on the environment
19-0255 A 39 of 75
(CEQA Guidelines 15071)
19-0255 A 40 of 75
– Must be essential nexus (Nollan v. CCC), and roughly proportional to impacts (Dolan v. Tigard)
19-0255 A 41 of 75
Five Questions for Drafting Effective Mitigation Measures
– What is the objective of the mitigation measures/why it is recommended
– Explain the specifics: how it will be designed and implemented – What are the measurable performance standards for determining the success of the mitigation – Identify a contingent mitigation if monitoring reveals that the success standards are not satisfied
– Identify the agency, organization, or individual responsible for the measure
– Identify the specific location where the mitigation measure will be applied
– Develop a schedule for implementation
19-0255 A 42 of 75
‘may’ or ‘should’), but lead agency may have standards or preferences
mitigation
impact in the description
19-0255 A 43 of 75
together with any comments received during the public review process prior to taking action on a project
if it finds on the basis of the whole record that there is no substantial evidence that the project will have a significant effect on the environment and that the ND or MND reflects the lead agency’s independent judgment and analysis
program for reporting on or monitoring the changes which it has either required in the project or made a condition of approval to mitigate or avoid significant environmental effects
approval
19-0255 A 44 of 75
– Fair argument must be backed by substantial evidence – Once a fair argument exists, it generally does not matter how much evidence supports the opposite conclusion of a less- than-significant effect
19-0255 A 45 of 75
Notice of Preparation (NOP) Draft EIR Notice of Completion (NOC) & Notice of Availability (NOA) to start minimum 45-day Draft EIR public review Final EIR (with responses to public comments) Certification/Decision
Notice of Determination (NOD)
19-0255 A 46 of 75
– Staged, Redevelopment, Base Reuse, General Plan
19-0255 A 47 of 75
– Description of project – Location of project (by map or street address) – Probable environmental effects of the project
(CEQA Guidelines 15082)
19-0255 A 48 of 75
19-0255 A 49 of 75
19-0255 A 50 of 75
(CEQA Guidelines 15126.6)
a successful manner within a reasonable period of time, taking into account economic, environmental, social, and technological factors.”
Economic Social Environmental Technical
19-0255 A 51 of 75
(CEQA Guidelines 15089)
– embedded in responses, in an errata chapter, or track changes in full text discretionary
– Good-faith, explain rationale behind responses (use substantial evidence, refer to Draft EIR coverage) – Respond to significant environmental points
– At least 10 days prior to certification
19-0255 A 52 of 75
– Significant new impact – Substantial increase in severity of an impact—unless mitigated – New feasible alternative or mitigation measure that lessens significant impact but that project proponent declines to adopt – Draft EIR so fundamentally and basically inadequate and conclusory that meaningful public review and comment were precluded
(CEQA Guidelines 15088.5)
19-0255 A 53 of 75
(CEQA Guidelines 15090 – 15093)
– Final EIR is in compliance with CEQA and reflects lead agency’s independent judgement
– Impact is mitigated or avoided – Mitigation of impact is the responsibility of another agency – Mitigation/alternatives are infeasible
– Specific economic, legal, social and/or technological benefits outweigh the significant unavoidable impacts
approval
19-0255 A 54 of 75
19-0255 A 55 of 75
– No new CEQA document required, except as Sections 15162-15164 apply – Checklist should be used to document determination – Feasible mitigation measures must be incorporated into activity
– New Initial Study is required – Either EIR, ND, or MND is prepared
19-0255 A 56 of 75
– An activity within the same project as analyzed in the PEIR – An activity within the same geographic area encompassed by the PEIR
19-0255 A 57 of 75
19-0255 A 58 of 75
– Substantial changes in project would result in new or worsened significant environmental impacts – Substantial changes in circumstances would result in new worsened significant impacts
19-0255 A 59 of 75
(Cont.) – New information of substantial importance shows: – The project will have new or worsened significant effects – Mitigation measures or alternatives previously infeasible are now feasible, but project proponent declines to adopt them
19-0255 A 60 of 75
19-0255 A 61 of 75
– Pertinent mitigation measures from the certified EIR that apply to the later project – Uniformly applicable development policies and standards (UADPS) that reduce its impact
19-0255 A 62 of 75
19-0255 A 63 of 75
– Average conditions – Maximum actual activity level
– Maximum permitted level if never reached
– Must be supported by substantial evidence (Neighbors for Smart Rail v. Exposition Metro Line Construction Authority, 2012)
19-0255 A 64 of 75
19-0255 A 65 of 75
19-0255 A 66 of 75
19-0255 A 67 of 75
19-0255 A 68 of 75
19-0255 A 69 of 75
19-0255 A 70 of 75
– Land use projects: Presumption of less than significant if development near transit or if project reduces VMT – Transportation projects: Presumption of less than significant for VMT reducing projects and projects with no impact on VMT – Lead agencies may analyze project VMT qualitatively if existing models or methods are not available to estimate VMT for the project being considered – Lead agency discretion in choosing appropriate methodology
19-0255 A 71 of 75
– Residential and office: “OPR finds that in most instances a per capita or per employee VMT that is fifteen percent below that of existing development may be a reasonable threshold.” – Retail: “A net increase in total VMT may indicate a significant transportation impact.”
19-0255 A 72 of 75
19-0255 A 73 of 75
Fresno identified that the air quality analysis for the Friant Ranch project failed to adequately disclose the nature and magnitude
from emissions of ozone precursors
impossible for the public to translate the bare numbers provided into adverse health impacts or to understand why such translation is not possible at this time,” the EIR’s discussion of air quality impacts was inadequate to inform the public
complex factors, including the presence of sunlight and precursor pollutants, natural topography, nearby structures that cause building downwash, atmospheric stability, and wind patterns.
cannot accurately estimate dispersion of ozone and its health effects, which is a secondary pollutant derived from the
19-0255 A 74 of 75
19-0255 A 75 of 75