2020 Capital Design & Construction 2020 CEA Edmonton Area Title of Presentation January 16, 2020 www.leduc.ca Presented by: Kyle van Steenoven, P.Eng. Manager, Capital Projects and Development Insert Title Here Thank you to our


slide-1
SLIDE 1

Title of Presentation

www.leduc.ca

2020 Capital Design & Construction

Presented by: Kyle van Steenoven, P.Eng. Manager, Capital Projects and Development

2020 CEA Edmonton Area January 16, 2020

slide-2
SLIDE 2

Insert Title Here Thank you to our consultants throughout 2019

slide-3
SLIDE 3

Insert Title Here City of Leduc Engineering

slide-4
SLIDE 4

Insert Title Here

Capital Projects and Development

  • Design and construction of capital projects
  • Review, inspection and acceptance of new developments
  • Review, inspection and approval of residential, commercial and

industrial lot grading.

slide-5
SLIDE 5

Insert Title Here

Infrastructure

  • Condition assessments
  • Functional, master and multi-jurisdictional

planning

  • Offsite Levy Model

Environmental

  • Environmental policies, initiatives and

projects

  • Curbside cart collection & recycling

program

slide-6
SLIDE 6

Insert Title Here Overview

  • Capital Roads Program
  • Capital Utility Program
  • Community Development Program
  • Master Plans
  • Standalone Projects

‒ Grant MacEwan Blvd. ‒ Drawdown Wells

slide-7
SLIDE 7

Insert Title Here

  • This contract is up for renewal in 2020. The two/four

year contract was previously awarded to Select Engineering.

  • The contract will include 2020/2021 design and

corresponding 2021/2022 construction management.

  • This contract has the potential to be extended by

2 years.

  • This program includes roadway renewal projects

including overlays and reconstructions as well as annual laneway rehabilitations.

Capital Roads Program

slide-8
SLIDE 8

Insert Title Here Capital Utility Program

  • This contract is up for renewal in 2020. The two/four

year contract was previously awarded to ISL Engineering.

  • The contract will include 2020/2021 design and

corresponding 2021/2022 construction management.

  • This contract has the ability to be extended up to

2 years.

  • This program includes any upgrade and repairs

required to the City of Leduc’s storm, sanitary and water

  • networks. This includes mainline and lateral liners, spot

repairs and replacements.

slide-9
SLIDE 9

Insert Title Here

  • This contract was up for renewal in 2019. The

two/four year contract has been awarded to WSP.

  • The current contract includes 2019/2020

design and corresponding 2020/2021 construction management.

  • This contract has the ability to be

extended for an additional 2 years.

  • This program includes community driven

projects such as park and recreation upgrades, multiway, trail systems, and art installations

Community Development Program

slide-10
SLIDE 10

Insert Title Here

Water Master Plan

  • Completion of a new Water Master Plan
  • Awarded to AECOM in 2019
  • Expected to be completed in 2020

Storm Master Plan

  • Creation of the City’s first Storm Water Master Plan
  • RFP expected to take place in Spring of 2020
  • Expected to be completed in 2021

Transportation Master Plan

  • Previously completed by Castleglenn Consultants in

2018

  • Next update is tentatively scheduled for 2023

(depending on the outcome of the 65 Avenue interchange)

Sanitary Master Plan

  • Previously completed by Cole Engineering in 2019
  • A new Sanitary master plan is to take place in 2024

Engineering Master Plans

All master plans are on a 5 year update/renewal rotation

slide-11
SLIDE 11

Insert Title Here Standalone Projects

When a project doesn’t fit within an existing program, is considered unique/complex, involves greenfield construction or is part of

  • ffsite levies then it is usually put out as a

standalone RFP. Upcoming Standalone Projects:

  • Grant MacEwan Boulevard
  • Drawdown Wells
slide-12
SLIDE 12

Insert Title Here Grant MacEwan Boulevard

  • Widening 450 meters of an

existing 2 lane arterial roadway to 4 lanes

  • Converting the RoW cross-

section from rural to urban

  • Design and construction of

noise attenuation

  • Relocation of overhead

primary power and streetlights underground

  • Realignement of the 3 meter

multiway

slide-13
SLIDE 13

Insert Title Here Drawdown Wells

2020: Design and construction management for the installation of 2 Drawdown wells within Elks Park to remove chlorine leachated groundwater. 2021: Design and construction management for the installation of 2 Drawdown wells within Lede Park to remove saline leachated groundwater.

slide-14
SLIDE 14

Insert Title Here

All RFP’s listed above will be posted on APC

For any questions and inquires please contact: Kyle van Steenoven Manager, Capital Projects and Developments (780) 980-8415 kvansteenoven@leduc.ca